Stuff for Type B to do in April 2018 while waiting for deliveries

Possible actual schedule of tasks selected from below

  • Week of 4/2
    • Glue SR3 (if available - still uncertain)
    • Build 2xIM, 2xIRM
  • Week of 4/9
    • Finish IMs and IRMs
    • Build 1xRM
  • Week of 4/16
    • Start SR3 Hang?
  • Week of 4/23
    • F0 blade prototype test
  • Week of 4/30
    • (Golden Week)

Tasks held over from March for lack of time

  • Geophones
  • Top filter disassembly
  • SF inspection/test/setup
  • BF rebuild

Things we're NOT doing in March OR April because we'd have to bump something else

  • Geophones
  • Top filter disassembly

Tasks that we have the necessary items for by the beginning of March

KAGRA/Subgroups/VIS/TypeB/March2018

Tasks that we have the necessary items for by the beginning of April

  • Install LBB damper rings in tanks.
    • First set arrives ≈3/26.
    • ≈2 days work each for 3-4 people.
  • Build SR3 and SRM IMs.
    • Parts for both arrive 3/30.
  • Build SR3 and SRM RMs
    • First cylinder part arrives ≈4/2 from ATC but needs cleaning by company => ≈4/9

    • Second to follow about two weeks later (≈4/23).