Line 37: | Line 37: |
== Things we're ''not'' doing in March because we'd have to bump something else == | == Things we're NOT doing in March because we'd have to bump something else == |
Line 43: | Line 43: |
== Tasks that we have the necessary items to do in March == | == Tasks that we have the necessary items to do by the beginning of March == |
Line 51: | Line 51: |
* |
Stuff for Type B to do in March 2018 while waiting for deliveries
Possible schedule of selected tasks from below
- Week of 3/5
- Finish any remaining SR2 SF stuff. (Enzo+2)
- Get SRM mushroom installed (Hirata-san, Kimura-san, Sawada-san)
- BF filter rebuild (Hirata-san+1)
- Move filter table into SRM area.
- Get additional heavy table.
- Disassemble two filters
- Week of 3/12
- Rack work (Enzo+1)
- Find boxes for SR3 and SRM at Mozumi
- Add boxes to SR3 and SRM racks
- Do SR3 and SRM in-rack cables and labeling
- Do SR3 in-air cables.
- BF filter rebuild continued (Hirata-san+1)
- Characterize 10 blades
- Choose two matched sets
- Rebuild two filters
- Rack work (Enzo+1)
- Week of 3/19 (Mitaka)
- Make two sets of IM OSEMs
- Make last in-air pico adapter cable
- Make three in-air stepper splitter cables for SR2, SR3 and SRM.
- Set up Dummy BS prism removal.
- Week of 3/26
- SF Setup, Test
- Set up SR3 assembly frame, weights.
- Bring in remaining two SFs.
- Remeasure load capacity, check for tilted keystone.
- Install Cu segments on cap.
- Wire and test LVDT.
- SF Setup, Test
Things we're NOT doing in March because we'd have to bump something else
- Geophones
- Top filter disassembly
- SF inspection/test/setup
- BF rebuild
Tasks that we have the necessary items to do by the beginning of March
- Make box of stuff to send to Mitaka
- OSEM coils and connectors for assembly.
- Pico in-air adapter parts.
- BS soaking cup.
- Anti-feedthrough adapter parts.
- Geophone parts?
- Build four geophone assemblies (Okutomi-kun has built five):
- Have most parts:
- Four sets of canister parts (body, neck, head).
- Five geophones.
- Three circuit boards - probably more exist but need to find.
- 20 x M8*35 (need 4*16=64)
- 35 x M8*30 (need 4*8=32)
- 4 x Viton disks (need 4? or 8?)
- 123 M8 washers (need 4*24=96)
- Have most parts:
- Assemble more OSEMs.
- Have 6 wound coils and connectors at Kamioka (one set, for SR3).
- Have 6 more at Mitaka.
- Set up SR3 and SRM racks.
Miyakawa-san gave us an empty rack for SR3 => can add boxes and do internal cabling and labels.
SR3 rack position is decided (on -X,+Y corner of SR3 cleanbooth) => can do in-air cabling from rack to assembly frame.
Miyakawa-san will soon give us an empty rack for SRM and decide position => will be able to do set-up.
- Disassemble broken top filters
- Set up heavy table in SRM area (first floor, -X side).
- Find jig and blade tensioning screw.
- Remove blades from #3 (in SRM area).
- Store #3 in box.
- Remove floor panel in SRM second floor.
- Crane #1 (in SR3 area) to SRM area.
- Remove blades from #1.
- Put test weights on table.
- BF rebuild - Hirata-san + 1
- Move BS Test Hang BF to tent and remove blades. (These blades are for BS-BF and will not be used again.)
- Find SR-BF blades that were removed to free up a BF base for the BS Final Hang.
- Move BF with tilted keystone to tent and remove blades.
- Characterize all SR-BF blades and choose two similar groups.
- Rebuild two filters.
- Etc
- Move all SFs to cleanbooth and inspect for keystone tilt and/or other issues.
- Make one set of in-air pico splitter cables (triple and double) for SRM.
- Make three in-air stepper splitter cables for SR2, SR3 and SRM.
- Soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
- Do buoyancy calculation (see LIGO-T1100616).
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Stuff to have done by other teams
- Add mushroom top to SRM tank.
- Put up safety bars