Differences between revisions 16 and 17
Revision 16 as of 2018-03-23 09:24:08
Size: 3781
Editor: EnzoTapia
Comment:
Revision 17 as of 2018-03-23 09:26:24
Size: 3841
Editor: EnzoTapia
Comment:
Deletions are marked like this. Additions are marked like this.
Line 38: Line 38:
  * Take inside the mine on monday or tuesday : Breadboard Spring   * Take inside the mine on monday or tuesday : Breadboard spring

  * Finish BF assembly

  * Finish SR3 and SRM rack
 

Stuff for Type B to do in March 2018 while waiting for deliveries

Possible schedule of selected tasks from below

  • Week of 3/5
    • Finish any remaining SR2 SF stuff. (Enzo+2)
    • Get SRM mushroom installed (Hirata-san, Kimura-san, Sawada-san)
    • BF filter rebuild (Hirata-san+1)
      • Move filter table into SRM area.
      • Get additional heavy table.
      • Disassemble two filters
  • Week of 3/12
    • Rack work (Enzo+1)
      • Find boxes for SR3 and SRM at Mozumi
      • Add boxes to SR3 and SRM racks
      • Do SR3 and SRM in-rack cables and labeling
      • Do SR3 in-air cables.
    • BF filter rebuild continued (Hirata-san+1)
      • Characterize 10 blades
      • Choose two matched sets
      • Rebuild two filters
  • Week of 3/19 (Mitaka)
    • Geophones
    • Make two sets of IM OSEMs
    • Make last in-air pico adapter cable
    • Make three in-air stepper splitter cables for SR2, SR3 and SRM.
    • Set up Dummy BS prism removal.
  • Week of 3/26
    • SF Setup, Test
      • Set up SR3 assembly frame, weights.
      • Bring in remaining two SFs.
      • Remeasure load capacity, check for tilted keystone.
      • Install Cu segments on cap.
      • Wire and test LVDT.
    • Take inside the mine on monday or tuesday : Breadboard spring
    • Finish BF assembly
    • Finish SR3 and SRM rack

Things we're NOT doing in March because we'd have to bump something else

  • Top filter disassembly

Tasks that we have the necessary items to do by the beginning of March

  • Make box of stuff to send to Mitaka
    • OSEM coils and connectors for assembly.
    • Pico in-air adapter parts.
    • BS soaking cup.
    • Anti-feedthrough adapter parts.
    • Geophone parts?
  • Build four geophone assemblies (Okutomi-kun has built five):
    • Have most parts:
      • Four sets of canister parts (body, neck, head).
      • Five geophones.
      • Three circuit boards - probably more exist but need to find.
      • 20 x M8*35 (need 4*16=64)
      • 35 x M8*30 (need 4*8=32)
      • 4 x Viton disks (need 4? or 8?)
      • 123 M8 washers (need 4*24=96)
  • Assemble more OSEMs.
    • Have 6 wound coils and connectors at Kamioka (one set, for SR3).
    • Have 6 more at Mitaka.
  • Set up SR3 and SRM racks.
    • Miyakawa-san gave us an empty rack for SR3 => can add boxes and do internal cabling and labels.

    • SR3 rack position is decided (on -X,+Y corner of SR3 cleanbooth) => can do in-air cabling from rack to assembly frame.

    • Miyakawa-san will soon give us an empty rack for SRM and decide position => will be able to do set-up.

  • Disassemble broken top filters
    • Set up heavy table in SRM area (first floor, -X side).
    • Find jig and blade tensioning screw.
    • Remove blades from #3 (in SRM area).
    • Store #3 in box.
    • Remove floor panel in SRM second floor.
    • Crane #1 (in SR3 area) to SRM area.
    • Remove blades from #1.
    • Put test weights on table.
  • BF rebuild - Hirata-san + 1
    • Move BS Test Hang BF to tent and remove blades. (These blades are for BS-BF and will not be used again.)
    • Find SR-BF blades that were removed to free up a BF base for the BS Final Hang.
    • Move BF with tilted keystone to tent and remove blades.
    • Characterize all SR-BF blades and choose two similar groups.
    • Rebuild two filters.
  • Etc
    • Move all SFs to cleanbooth and inspect for keystone tilt and/or other issues.
    • Make one set of in-air pico splitter cables (triple and double) for SRM.
    • Make three in-air stepper splitter cables for SR2, SR3 and SRM.
    • Soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
    • Do buoyancy calculation (see LIGO-T1100616).
    • Set up SR2 Guardian.
    • Install damping filters for SR2.
  • Stuff to have done by other teams
    • Add mushroom top to SRM tank.
    • Put up safety bars

KAGRA/Subgroups/VIS/TypeB/March2018 (last edited 2018-04-20 15:24:15 by YoshinoriFujii)