Line 5: Line 5:
  * Finish any remaining SR2 SF stuff. (Enzo+2)
  * Get SRM mushroom installed (Hirata-san, Kimura-san, Sawada-san)
  * --(Finish any remaining SR2 SF stuff.)-- (Enzo+2)
Line 8: Line 7:
   * Move filter table into SRM area.
   * Get additional heavy table.
   *
Disassemble two filters
   * --(Move filter table into SRM area.)--
   * --(Disassemble two filters)--
Line 13: Line 11:
  * Rack work (Enzo+1)
   *
Find boxes for SR3 and SRM at Mozumi
   *
Add boxes to SR3 and SRM racks
   *
Do SR3 and SRM in-rack cables and labeling
   *
Do SR3 in-air cables.
  * BF filter rebuild continued (Hirata-san+1)
   *
Characterize 10 blades
   *
Choose two matched sets
   *
Rebuild two filters
  * --(Rack work (Enzo+1))--
   * --(
Find boxes for SR3 and SRM at Mozumi)--
   * --(
Add boxes to SR3 and SRM racks)--
   * --(
Do SR3 and SRM in-rack cables and labeling)--
   * --(
Do SR3 in-air cables)--.
  * --(BF filter rebuild continued (Hirata-san+1))--
   * --(
Characterize 10 blades)--
   * --(
Choose two matched sets)--
   * --(
Rebuild two filters)--
Line 25: Line 23:
  * Make two sets of IM OSEMs
  * Make last in-air pico adapter cable
  * --(Make two sets of IM OSEMs)--
  * --(Make last in-air pico adapter cable)--
Line 28: Line 26:
  * Set up Dummy BS prism removal.   * --(Set up Dummy BS prism removal.)--
Line 32: Line 30:
  * Finish BF assembly #1   * --(Finish BF assembly #1)--
Line 36: Line 34:
   * --(Move out of cleanbooth)--
Line 42: Line 41:
   * Move out of cleanbooth
Line 45: Line 45:
   * Bring in remaining two SFs.    * --(Bring in remaining two SFs.)--
Line 49: Line 49:

  * Take breadboard spring inside the mine on monday or tuesday.

  *
Finish SR3 and SRM rack + SR3 In air cabling.
   * Move out of cleanbooth
  * --(Finish SR3 and SRM rack + SR3 In air cabling.)--
Line 61: Line 59:
 * Make box of stuff to send to Mitaka
  * OSEM coils and connectors for assembly.
  * Pico in-air adapter parts.
  * BS soaking cup.
  * Anti-feedthrough adapter parts.
  * Geophone parts?
 * --(Make box of stuff to send to Mitaka)--
  * --(OSEM coils and connectors for assembly.)--
  * --(Pico in-air adapter parts.)--
  * --(BS soaking cup.)--
  * --(Anti-feedthrough adapter parts.)--
Line 70: Line 67:
   * Four sets of canister parts (body, neck, head).
   *
Five geophones.
   *
Three circuit boards - probably more exist but need to find.
   *
20 x M8*35 (need 4*16=64)
   *
35 x M8*30 (need 4*8=32)
   *
4 x Viton disks (need 4? or 8?)
   *
123 M8 washers (need 4*24=96)
   * --(Four sets of canister parts (body, neck, head).)--
   * --(
Five geophones.)--
   * --(
Three circuit boards - probably more exist but need to find.)--
   * --(
20 x M8*35 (need 4*16=64))--
   * --(
35 x M8*30 (need 4*8=32))--
   * --(
4 x Viton disks (need 4? or 8?))--
   * --(
123 M8 washers (need 4*24=96))--
  * --(Build first geophone assembly)--
  * Get more Cu O-rings
  * Complete three more geophone assemblies
Line 78: Line 78:
 * Assemble more OSEMs.  * --(Assemble more OSEMs.)--
Line 81: Line 81:
  * Build OSEMs
  * Characterize OSEM.
Line 82: Line 84:
 * Set up SR3 and SRM racks.
  * Miyakawa-san gave us an empty rack for SR3 => can add boxes and do internal cabling and labels.
  * SR3 rack position is decided (on -X,+Y corner of SR3 cleanbooth) => can do in-air cabling from rack to assembly frame.
  * Miyakawa-san will soon give us an empty rack for SRM and decide position => will be able to do set-up. 
 * --(Set up SR3 and SRM racks.)--
  * --(Miyakawa-san gave us an empty rack for SR3 => can add boxes and do internal cabling and labels.)--
  * --(SR3 rack position is decided (on -X,+Y corner of SR3 cleanbooth) => can do in-air cabling from rack to assembly frame.)--
  * --(Miyakawa-san will soon give us an empty rack for SRM and decide position => will be able to do set-up.)--
Line 88: Line 90:
  * Set up heavy table in SRM area (first floor, -X side).
  * Find jig and blade tensioning screw.
  * Set up heavy table in SRM area (first floor, -X side) => use ladder?
  * --(Find jig and blade tensioning screw.)--
Line 98: Line 100:
  * Move BS Test Hang BF to tent and remove blades. (These blades are for BS-BF and will not be used again.)
  * Find SR-BF blades that were removed to free up a BF base for the BS Final Hang.
  * Move BF with tilted keystone to tent and remove blades.
  * Characterize all SR-BF blades and choose two similar groups.
  * Rebuild two filters. 
  * --(Move BS Test Hang BF to tent and remove blades. (These blades are for BS-BF and will not be used again.))--
  * --(Find SR-BF blades that were removed to free up a BF base for the BS Final Hang.)--
  * --(Move BF with tilted keystone to tent and remove blades.)--
  * --(Characterize all SR-BF blades and choose two similar groups.)--
  * --(Rebuild two filters.)--
Line 105: Line 107:
  * Move all SFs to cleanbooth and inspect for keystone tilt and/or other issues.
  * Make one set of in-air pico splitter cables (triple and double) for SRM.
  * Make three in-air stepper splitter cables for SR2, SR3 and SRM.
  * --(Move all SFs to cleanbooth and inspect for keystone tilt and/or other issues.)--
  * --(Make one set of in-air pico splitter cables (triple and double) for SRM.)--
  * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
Line 115: Line 117:
  * Put up safety bars   * --(Put up safety bars.)--

Stuff for Type B to do in March 2018 while waiting for deliveries

Possible schedule of selected tasks from below

  • Week of 3/5
    • Finish any remaining SR2 SF stuff. (Enzo+2)

    • BF filter rebuild (Hirata-san+1)
      • Move filter table into SRM area.

      • Disassemble two filters

  • Week of 3/12
    • Rack work (Enzo+1)

      • Find boxes for SR3 and SRM at Mozumi

      • Add boxes to SR3 and SRM racks

      • Do SR3 and SRM in-rack cables and labeling

      • Do SR3 in-air cables.

    • BF filter rebuild continued (Hirata-san+1)

      • Characterize 10 blades

      • Choose two matched sets

      • Rebuild two filters

  • Week of 3/19 (Mitaka)
    • Geophones
    • Make two sets of IM OSEMs

    • Make last in-air pico adapter cable

    • Make three in-air stepper splitter cables for SR2, SR3 and SRM.
    • Set up Dummy BS prism removal.

  • Week of 3/26
    • Finish BF assembly #1

      • Compression of blades and frequency measurement.

      • Check Keystone tilt.

      • LVDT+Pico-motor+Stepper-motor cabling, check and calibration.

      • Move out of cleanbooth

    • Finish BF assembly #7
      • Assembly of the blades.

      • Compression of blades and frequency measurement.

      • Check Keystone tilt.

      • LVDT+Pico-motor+Stepper-motor cabling, check and calibration.

      • Move out of cleanbooth
    • SF Setup, Test
      • Set up SR3 assembly frame, weights.

      • Bring in remaining two SFs.

      • Remeasure load capacity, check for tilted keystone.

      • Install Cu segments on cap.
      • Wire and test LVDT.

      • Move out of cleanbooth
    • Finish SR3 and SRM rack + SR3 In air cabling.

Things we're NOT doing in March because we'd have to bump something else

  • Top filter disassembly

Tasks that we have the necessary items to do by the beginning of March

  • Make box of stuff to send to Mitaka

    • OSEM coils and connectors for assembly.

    • Pico in-air adapter parts.

    • BS soaking cup.

    • Anti-feedthrough adapter parts.

  • Build four geophone assemblies (Okutomi-kun has built five):
    • Have most parts:
      • Four sets of canister parts (body, neck, head).

      • Five geophones.

      • Three circuit boards - probably more exist but need to find.

      • 20 x M8*35 (need 4*16=64)

      • 35 x M8*30 (need 4*8=32)

      • 4 x Viton disks (need 4? or 8?)

      • 123 M8 washers (need 4*24=96)

    • Build first geophone assembly

    • Get more Cu O-rings
    • Complete three more geophone assemblies
  • Assemble more OSEMs.

    • Have 6 wound coils and connectors at Kamioka (one set, for SR3).
    • Have 6 more at Mitaka.
    • Build OSEMs
    • Characterize OSEM.
  • Set up SR3 and SRM racks.

    • Miyakawa-san gave us an empty rack for SR3 => can add boxes and do internal cabling and labels.

    • SR3 rack position is decided (on -X,+Y corner of SR3 cleanbooth) => can do in-air cabling from rack to assembly frame.

    • Miyakawa-san will soon give us an empty rack for SRM and decide position => will be able to do set-up.

  • Disassemble broken top filters
    • Set up heavy table in SRM area (first floor, -X side) => use ladder?

    • Find jig and blade tensioning screw.

    • Remove blades from #3 (in SRM area).
    • Store #3 in box.
    • Remove floor panel in SRM second floor.
    • Crane #1 (in SR3 area) to SRM area.
    • Remove blades from #1.
    • Put test weights on table.
  • BF rebuild - Hirata-san + 1
    • Move BS Test Hang BF to tent and remove blades. (These blades are for BS-BF and will not be used again.)

    • Find SR-BF blades that were removed to free up a BF base for the BS Final Hang.

    • Move BF with tilted keystone to tent and remove blades.

    • Characterize all SR-BF blades and choose two similar groups.

    • Rebuild two filters.

  • Etc
    • Move all SFs to cleanbooth and inspect for keystone tilt and/or other issues.

    • Make one set of in-air pico splitter cables (triple and double) for SRM.

    • Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
    • Soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
    • Do buoyancy calculation (see LIGO-T1100616).
    • Set up SR2 Guardian.
    • Install damping filters for SR2.
  • Stuff to have done by other teams
    • Add mushroom top to SRM tank.
    • Put up safety bars.