Differences between revisions 20 and 21
Revision 20 as of 2018-04-15 20:45:11
Size: 4623
Editor: MarkBarton
Comment:
Revision 21 as of 2018-04-20 14:10:48
Size: 4652
Comment:
Deletions are marked like this. Additions are marked like this.
Line 6: Line 6:
  * BF filter rebuild  (Hirata-san+1)   * --(BF filter rebuild)-- (Hirata-san+1)
Line 36: Line 36:
  * Finish BF assembly #7   * --(Finish BF assembly #7)--
Line 41: Line 41:
   * Move out of cleanbooth    * --(Move out of cleanbooth)--
Line 49: Line 49:
   * Move out of cleanbooth    * --(Move out of cleanbooth)--
Line 99: Line 99:
 * BF rebuild - Hirata-san + 1  * --(BF rebuild)-- - Hirata-san + 1

Stuff for Type B to do in March 2018 while waiting for deliveries

Possible schedule of selected tasks from below

  • Week of 3/5
    • Finish any remaining SR2 SF stuff. (Enzo+2)

    • BF filter rebuild (Hirata-san+1)

      • Move filter table into SRM area.

      • Disassemble two filters

  • Week of 3/12
    • Rack work (Enzo+1)

      • Find boxes for SR3 and SRM at Mozumi

      • Add boxes to SR3 and SRM racks

      • Do SR3 and SRM in-rack cables and labeling

      • Do SR3 in-air cables.

    • BF filter rebuild continued (Hirata-san+1)

      • Characterize 10 blades

      • Choose two matched sets

      • Rebuild two filters

  • Week of 3/19 (Mitaka)
    • Geophones
    • Make two sets of IM OSEMs

    • Make last in-air pico adapter cable

    • Make three in-air stepper splitter cables for SR2, SR3 and SRM.
    • Set up Dummy BS prism removal.

  • Week of 3/26
    • Finish BF assembly #1

      • Compression of blades and frequency measurement.

      • Check Keystone tilt.

      • LVDT+Pico-motor+Stepper-motor cabling, check and calibration.

      • Move out of cleanbooth

    • Finish BF assembly #7

      • Assembly of the blades.

      • Compression of blades and frequency measurement.

      • Check Keystone tilt.

      • LVDT+Pico-motor+Stepper-motor cabling, check and calibration.

      • Move out of cleanbooth

    • SF Setup, Test
      • Set up SR3 assembly frame, weights.

      • Bring in remaining two SFs.

      • Remeasure load capacity, check for tilted keystone.

      • Install Cu segments on cap.
      • Wire and test LVDT.

      • Move out of cleanbooth

    • Finish SR3 and SRM rack + SR3 In air cabling.

Things we're NOT doing in March because we'd have to bump something else

  • Top filter disassembly

Tasks that we have the necessary items to do by the beginning of March

  • Make box of stuff to send to Mitaka

    • OSEM coils and connectors for assembly.

    • Pico in-air adapter parts.

    • BS soaking cup.

    • Anti-feedthrough adapter parts.

  • Build four geophone assemblies (Okutomi-kun has built five):
    • Have most parts:
      • Four sets of canister parts (body, neck, head).

      • Five geophones.

      • Three circuit boards - probably more exist but need to find.

      • 20 x M8*35 (need 4*16=64)

      • 35 x M8*30 (need 4*8=32)

      • 4 x Viton disks (need 4? or 8?)

      • 123 M8 washers (need 4*24=96)

    • Build first geophone assembly

    • Get more Cu O-rings
    • Complete three more geophone assemblies
  • Assemble more OSEMs.

    • Have 6 wound coils and connectors at Kamioka (one set, for SR3).
    • Have 6 more at Mitaka.
    • Build OSEMs
    • Characterize OSEM.
  • Set up SR3 and SRM racks.

    • Miyakawa-san gave us an empty rack for SR3 => can add boxes and do internal cabling and labels.

    • SR3 rack position is decided (on -X,+Y corner of SR3 cleanbooth) => can do in-air cabling from rack to assembly frame.

    • Miyakawa-san will soon give us an empty rack for SRM and decide position => will be able to do set-up.

  • Disassemble broken top filters
    • Set up heavy table in SRM area (first floor, -X side) => use ladder?

    • Find jig and blade tensioning screw.

    • Remove blades from #3 (in SRM area).
    • Store #3 in box.
    • Remove floor panel in SRM second floor.
    • Crane #1 (in SR3 area) to SRM area.
    • Remove blades from #1.
    • Put test weights on table.
  • BF rebuild - Hirata-san + 1

    • Move BS Test Hang BF to tent and remove blades. (These blades are for BS-BF and will not be used again.)

    • Find SR-BF blades that were removed to free up a BF base for the BS Final Hang.

    • Move BF with tilted keystone to tent and remove blades.

    • Characterize all SR-BF blades and choose two similar groups.

    • Rebuild two filters.

  • Etc
    • Move all SFs to cleanbooth and inspect for keystone tilt and/or other issues.

    • Make one set of in-air pico splitter cables (triple and double) for SRM.

    • Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
    • Soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
    • Do buoyancy calculation (see LIGO-T1100616).
    • Set up SR2 Guardian.
    • Install damping filters for SR2.
  • Stuff to have done by other teams
    • Add mushroom top to SRM tank.
    • Put up safety bars.

KAGRA/Subgroups/VIS/TypeB/March2018 (last edited 2018-04-20 15:24:15 by YoshinoriFujii)