Line 14: Line 14:
  * Have 6 wound coils and connectors (one set, for SR3).
  * Might be able to get third set from Akutsu-san.
  * Have 6 wound coils and connectors at Kamioka (one set, for SR3).
  * Have 6 more at Mitaka.
Line 40: Line 40:
  * Move all SFs to cleanbooth and inspect for keystone tilt and/or other issues.
Line 43: Line 44:
  * Do buoyancy calculation.   * Do buoyancy calculation (see LIGO-T1100616).
  * Set up SR2 Guardian.
  * Install damping filters for SR2.

Stuff for Type B to do in March 2018 while waiting for deliveries

  • Build four geophone assemblies (Okutomi-kun has built five):
    • Have most parts:
      • Four sets of canister parts (body, neck, head).
      • Five geophones.
      • Three circuit boards - probably more exist but need to find.
      • 20 x M8*35 (need 4*16=64)
      • 35 x M8*30 (need 4*8=32)
      • 4 x Viton disks (need 4? or 8?)
      • 123 M8 washers (need 4*24=96)
  • Assemble more OSEMs.
    • Have 6 wound coils and connectors at Kamioka (one set, for SR3).
    • Have 6 more at Mitaka.
  • Set up SR3 and SRM racks.
    • Miyakawa-san gave us an empty rack for SR3 => can add boxes and do internal cabling and labels.

    • SR3 rack position is decided (on -X,+Y corner of SR3 cleanbooth) => can do in-air cabling from rack to assembly frame.

    • Miyakawa-san will soon give us an empty rack for SRM and decide position => will be able to do set-up.

  • Disassemble broken top filters
    • Set up heavy table in SRM area (first floor, -X side).
    • Find jig and blade tensioning screw.
    • Remove blades from #3 (in SRM area).
    • Store #3 in box.
    • Remove floor panel in SRM second floor.
    • Crane #1 (in SR3 area) to SRM area.
    • Remove blades from #1.
    • Put test weights on table.
  • BF rebuild.
    • Move BS Test Hang BF to tent and remove blades. (These blades are for BS-BF and will not be used again.)
    • Find SR-BF blades that were removed to free up a BF base for the BS Final Hang.
    • Move BF with tilted keystone to tent and remove blades.
    • Characterize all SR-BF blades and choose two similar groups.
    • Rebuild two filters.
  • Etc
    • Move all SFs to cleanbooth and inspect for keystone tilt and/or other issues.
    • Make one set of in-air pico splitter cables (triple and double) for SRM.
    • Make three in-air stepper splitter cables for SR2, SR3 and SRM.
    • Soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
    • Do buoyancy calculation (see LIGO-T1100616).
    • Set up SR2 Guardian.
    • Install damping filters for SR2.
  • Stuff to have done by other teams
    • Add mushroom top to SRM tank.
    • Put up safety bars