Differences between revisions 1 and 275 (spanning 274 versions)
Revision 1 as of 2016-04-12 15:09:01
Size: 65
Editor: MarkBarton
Comment:
Revision 275 as of 2018-04-06 14:20:35
Size: 2606
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 1: Line 1:
= Scraps of text for incorporation in the Vis Meeting Minutes = = Scraps of text for incorporation in the VIS Meeting Minutes =

[[KAGRA/Subgroups/VIS/MeetingNAOJ]]

=== Type B (Mark) ===
==== Report for week of 4/2 ====

 * Fujii-kun and Yamamoto-kun got the SR3 real time model running.
 * We received the SR3.
 * However Mark and Tanioka-kun found Hirose-san had applied the First Contact patterns on the wrong sides, so we took it to Yamamoto-san's lab and Toyama University and re-applied the FC properly. We also bounced a 1064 nm beam off it to verify that the HR and AR coatings were not also swapped (they were OK).
 * We made magnet-standoff assemblies for both SR3 and SRM, and set up for gluing the prisms and magnets. We will attach the prisms and magnet-standoffs on Monday.
 * Hirata-san did inventory of the SR3/SRM payload parts received last week and started on the inventory of screws.
 * Fujii-kun, Enzo and team finished the preparation, adjustment of the SFs and BFs.
 * They calibrated one SF and BF. (The remaining one SF and BF will take about another day. Also, the FR stops need to be checked.)
 * Enzo and Kozu-kun finished setting up the SR3 and SRM racks. (The SRM rack still lacks a front-end, and power and network connections, but the SR3 is now ready for testing.)
 * Shoda-san worked on getting quotes for the ballast masses, on design of the SRM metal mass, and on splitting the BS model to reduce the load on the front-end computer.

==== Plan for week of 4/9 ====
 * Shoda-san at Mitaka
 * Fujii-san at Mitaka
 * Tanioka-san at Kamioka, but possibly doing PEM stuff.
 * Others at Kamioka
 * --
 * Finish SRM BF and SF calibration
 * Finish IMs and IRMs
 * Glue SR3 mirror

==== Plan for week of 4/16 ====
 * Shoda-san at Mitaka
 * Fujii-san at Mitaka
 * Tanioka-san at Mitaka?
 * Others at Kamioka
 * --
 * Build 1xRM
 * Start SR3 Hang
  * Align assembly frame.

==== Plan for week of 4/23 ====
 * Shoda-san at Mitaka
 * Fujii-san at Mitaka?
 * Mark, Enzo at Kamioka
 * Hirata-san at Mitaka
 * Tanioka-san at Mitaka?
 * --
 * Clean parts (cable clamp bases, etc, etc).
 * Observe KAGRA Phase 1 operations, assist if problems arise.

==== Plan for week of 4/30 ====
  * Golden Week!

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/March2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/April2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]]

==== Vacation Info ====
 * Fabian vacation, 3/26-4/27 (then gone).

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 4/2

  • Fujii-kun and Yamamoto-kun got the SR3 real time model running.
  • We received the SR3.
  • However Mark and Tanioka-kun found Hirose-san had applied the First Contact patterns on the wrong sides, so we took it to Yamamoto-san's lab and Toyama University and re-applied the FC properly. We also bounced a 1064 nm beam off it to verify that the HR and AR coatings were not also swapped (they were OK).
  • We made magnet-standoff assemblies for both SR3 and SRM, and set up for gluing the prisms and magnets. We will attach the prisms and magnet-standoffs on Monday.
  • Hirata-san did inventory of the SR3/SRM payload parts received last week and started on the inventory of screws.
  • Fujii-kun, Enzo and team finished the preparation, adjustment of the SFs and BFs.
  • They calibrated one SF and BF. (The remaining one SF and BF will take about another day. Also, the FR stops need to be checked.)
  • Enzo and Kozu-kun finished setting up the SR3 and SRM racks. (The SRM rack still lacks a front-end, and power and network connections, but the SR3 is now ready for testing.)
  • Shoda-san worked on getting quotes for the ballast masses, on design of the SRM metal mass, and on splitting the BS model to reduce the load on the front-end computer.

Plan for week of 4/9

  • Shoda-san at Mitaka
  • Fujii-san at Mitaka
  • Tanioka-san at Kamioka, but possibly doing PEM stuff.
  • Others at Kamioka
  • --
  • Finish SRM BF and SF calibration
  • Finish IMs and IRMs
  • Glue SR3 mirror

Plan for week of 4/16

  • Shoda-san at Mitaka
  • Fujii-san at Mitaka
  • Tanioka-san at Mitaka?
  • Others at Kamioka
  • --
  • Build 1xRM
  • Start SR3 Hang
    • Align assembly frame.

Plan for week of 4/23

  • Shoda-san at Mitaka
  • Fujii-san at Mitaka?
  • Mark, Enzo at Kamioka
  • Hirata-san at Mitaka
  • Tanioka-san at Mitaka?
  • --
  • Clean parts (cable clamp bases, etc, etc).
  • Observe KAGRA Phase 1 operations, assist if problems arise.

Plan for week of 4/30

  • Golden Week!

To-Do Lists, Schedule

Vacation Info

  • Fabian vacation, 3/26-4/27 (then gone).

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)