Line 5: Line 5:
 * Activity report for week of 12/19
  * Hirata-san made, and Fabian and Mark checked, drawings and parts/fastener lists for the SRM/PRM order and various others: [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5964| D1605964]], [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5965| D1605965]], [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5956| D1605956]], [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5963| D1605963]], [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5977|D1605977]], etc.
  * Fabian designed a simple two-piece hold-down device to immobilize the SRx IMs during the optic and RM hanging. It avoids having to remachine all the IM support bars to allow for hold-down screws. The Type Bp team might also want to use it.
  * Aso-san and Mark discussed the [[KAGRA/Subgroups/VIS/VISMinutes20161216#BFIssue|BF issue]] from last week.
   * It was decided to ask Takahashi-san to take a look at the BF while he's at Kamioka this week.
   * It was decided to have the BS bottom filter moved to Mitaka for tuneup and adjustment as soon as possible in the new year.
  * Raffaele, Aso-san, Mark and Fabian discussed having much smaller/shorter BS and SR stub flags plus longer, coil-only OSEMs.
   * Aso-san volunteered to do the OSEM design.
   * Hirata-san made Pack'n'Go archives of the existing designs as a baseline for Aso-san.
  * Hirata-san searched for missing PR mirror box parts.
  * Miyakawa-san finished recabling the PR2 rack and got the BS real-time model running again. The model still needs lots of work, but it has the OSEM functionality needed for the next test-hang stage, plus Okutomi-san's improvements.
=== Type B (Mark) ===
==== Past week report ====
At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san):

 * Craned in the PI.
 * Assembled the thrust bearing holder that receives the PI-SF rod. (It originally had a burr that prevented the bearing from seating properly, and so required filing and re-cleaning.)
 * Hooked the SF and lowered the jacks under the SF to suspend the SF/... section.
 * The top filter rose when unlocked, and required about 1.8 kg to send it back down. Therefore we may be OK - the top filter seems to have about 8 kg more capacity than as measured by G&M. The hex cable clamp (≈0.25 kg) and the cables between the PI and SF still have to be added, but we can get an extra 3 kg by removing one of the three Cu damper segments (and rearranging the other two).
 * Built and installed three LBB blade units.
 * Kept debugging the SF LVDT. We repaired several broken wires, but it's still not behaving correctly.

==== Plan for coming weeks ====
For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]].

Week of 5/1:
 * No activity (Golden Week).

Week of 5/8:
 * Work from Tuesday.
 * Remove PI temporarily.
 * Add magnets to upper SF damper ring.
 * Reinstall PI with damper ring.
 * Reinstall PI-SF rod, this time with hex cable clamp.
 * Install PI yaw stepper.
 * Wire up PI yaw and vertical steppers.
 * Route cables from SF to PI (may involve removing part of Cu damper).

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san):

  • Craned in the PI.
  • Assembled the thrust bearing holder that receives the PI-SF rod. (It originally had a burr that prevented the bearing from seating properly, and so required filing and re-cleaning.)
  • Hooked the SF and lowered the jacks under the SF to suspend the SF/... section.
  • The top filter rose when unlocked, and required about 1.8 kg to send it back down. Therefore we may be OK - the top filter seems to have about 8 kg more capacity than as measured by G&M. The hex cable clamp (≈0.25 kg) and the cables between the PI and SF still have to be added, but we can get an extra 3 kg by removing one of the three Cu damper segments (and rearranging the other two).

  • Built and installed three LBB blade units.
  • Kept debugging the SF LVDT. We repaired several broken wires, but it's still not behaving correctly.

Plan for coming weeks

For more detail, see KAGRA/Subgroups/VIS/TypeB/ToDo.

Week of 5/1:

  • No activity (Golden Week).

Week of 5/8:

  • Work from Tuesday.
  • Remove PI temporarily.
  • Add magnets to upper SF damper ring.
  • Reinstall PI with damper ring.
  • Reinstall PI-SF rod, this time with hex cable clamp.
  • Install PI yaw stepper.
  • Wire up PI yaw and vertical steppers.
  • Route cables from SF to PI (may involve removing part of Cu damper).