* Activity report for week of 12/19 * Hirata-san made, and Fabian and Mark checked, drawings and parts/fastener lists for the SRM/PRM order and various others: [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5964| D1605964]], [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5965| D1605965]], [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5956| D1605956]], [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5963| D1605963]], [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5977|D1605977]], etc. * Fabian designed a simple two-piece hold-down device to immobilize the SRx IMs during the optic and RM hanging. It avoids having to remachine all the IM support bars to allow for hold-down screws. The Type Bp team might also want to use it. * Aso-san and Mark discussed the [[KAGRA/Subgroups/VIS/VISMinutes20161216#BFIssue|BF issue]] from last week. * It was decided to ask Takahashi-san to take a look at the BF while he's at Kamioka this week. * It was decided to have the BS bottom filter moved to Mitaka for tuneup and adjustment as soon as possible in the new year. * Raffaele, Aso-san, Mark and Fabian discussed having much smaller/shorter BS and SR stub flags plus longer, coil-only OSEMs. * Aso-san volunteered to do the OSEM design. * Hirata-san made Pack'n'Go archives of the existing designs as a baseline for Aso-san. * Hirata-san searched for missing PR mirror box parts. * Miyakawa-san finished recabling the PR2 rack and got the BS real-time model running again. The model still needs lots of work, but it has the OSEM functionality needed for the next test-hang stage, plus Okutomi-san's improvements. |
=== Type B (Mark) === ==== Past week report ==== At Kamioka (Mark, Ohishi-san, Enzo, Yoshioka-kun, Kozu-kun): * We finished installing the RM OSEMs and installed the new Type5-2.2 and 5-2.4 OSEM cables. * We hung the RM and set its pitch. * We doubled-checked the BS and RM pitch, tightened the clamps and removed the winch system. * We installed the bottom section of the security structure to protect the RM/BS. * We lifted the IM/RM/BS section and weighed it. It was about 1.25 kg too heavy for the new BF, so we improvised a lighter set of ballast masses. * We installed the section of the security structure up to the BF ring, and the BF crossbars and jacks of the assembly frame. * We brought in the new BF. * We installed the BF-IRM rods and IRM top plate. * We reinstalled the IM flags and other items that had been taken off to use the winch system. * We hooked the BF-IM rod (with hex cable clamp). (We did not unlock the BF keystone.) * We cabled and tested the IM-PIT, IM-ROL and IM-YAW picos and the BF FR stepper (but not, yet, the BF LVDT). ==== Plan for week of 8/14 ==== Site closure: Mon, Tue<<BR>> Vacation: Fabian (Mon-Fri)<<BR>> Kamioka: Mark (Wed-Fri), Enzo (Wed-Fri), Yoshioka-kun (Wed, Fri), Ohishi (Thu-Fri).<<BR>> * Remove LBB blade units from PI, then remove blades and send for remachining. * Remove LBB rings from chamber and send for recleaning. * Unlock BF, adjust ballast masses on IM/RM/BS to correct pitch/roll/vertical. * Test, calibrate BF LVDT. Mitaka: Hirata-san (Mon-Fri)<<BR>> * SR Stuff ==== Plan for week of 8/21 ==== Vacation: Fabian (Mon)<<BR>> Kamioka: Mark, Ohishi, Fabian (Tue-Fri), Enzo, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun. * Install side panels of IRM and OSEMs. * Route IRM OSEM cables, test/adjust IRM OSEMs. * Add BF cap; cable and test BF-1 and BF-2 picos. * Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass. * Crane in SF. Mitaka: Hirata-san. * SR stuff. ==== Vacation Info ==== Fabian: Fri 8/4 through Mon 8/21 Mark: TBD Mid-Oct |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past week report
At Kamioka (Mark, Ohishi-san, Enzo, Yoshioka-kun, Kozu-kun):
- We finished installing the RM OSEMs and installed the new Type5-2.2 and 5-2.4 OSEM cables.
- We hung the RM and set its pitch.
- We doubled-checked the BS and RM pitch, tightened the clamps and removed the winch system.
- We installed the bottom section of the security structure to protect the RM/BS.
- We lifted the IM/RM/BS section and weighed it. It was about 1.25 kg too heavy for the new BF, so we improvised a lighter set of ballast masses.
- We installed the section of the security structure up to the BF ring, and the BF crossbars and jacks of the assembly frame.
- We brought in the new BF.
- We installed the BF-IRM rods and IRM top plate.
- We reinstalled the IM flags and other items that had been taken off to use the winch system.
- We hooked the BF-IM rod (with hex cable clamp). (We did not unlock the BF keystone.)
- We cabled and tested the IM-PIT, IM-ROL and IM-YAW picos and the BF FR stepper (but not, yet, the BF LVDT).
Plan for week of 8/14
Site closure: Mon, Tue
Vacation: Fabian (Mon-Fri)
Kamioka: Mark (Wed-Fri), Enzo (Wed-Fri), Yoshioka-kun (Wed, Fri), Ohishi (Thu-Fri).
- Remove LBB blade units from PI, then remove blades and send for remachining.
- Remove LBB rings from chamber and send for recleaning.
- Unlock BF, adjust ballast masses on IM/RM/BS to correct pitch/roll/vertical.
- Test, calibrate BF LVDT.
Mitaka: Hirata-san (Mon-Fri)
- SR Stuff
Plan for week of 8/21
Vacation: Fabian (Mon)
Kamioka: Mark, Ohishi, Fabian (Tue-Fri), Enzo, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun.
- Install side panels of IRM and OSEMs.
- Route IRM OSEM cables, test/adjust IRM OSEMs.
- Add BF cap; cable and test BF-1 and BF-2 picos.
- Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass.
- Crane in SF.
Mitaka: Hirata-san.
- SR stuff.
Vacation Info
Fabian: Fri 8/4 through Mon 8/21 Mark: TBD Mid-Oct