* Activity report for week of 12/19 * Hirata-san made (and Fabian and Mark checked) drawings and parts/fastener lists for the SRM/PRM order and various others: [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5964| D1605964]], [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5965| D1605965]], [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5956| D1605956]], [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5963| D1605963]], [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5977|D1605977]], etc. * Fabian designed a simple two-piece hold-down device to immobilize the SRx IMs during the optic and RM hanging. It avoids having to remachine all the IM support bars to allow for hold-down screws. The Type Bp team might also want to use it. * Aso-san and Mark discussed the [[KAGRA/Subgroups/VIS/VISMinutes20161216#BFIssue|BF issue]] from last week. * It was decided to ask Takahashi-san to take a look at the BF while he's at Kamioka this week. * It was decided to have the BS bottom filter moved to Mitaka for tuneup and adjustment as soon as possible in the new year. * Raffaele, Aso-san, Mark and Fabian discussed having much smaller/shorter BS and SR stub flags plus longer, coil-only OSEMs. * Aso-san volunteered to do the OSEM design. * Hirata-san made Pack'n'Go archives of the existing designs as a baseline for Aso-san. * Hirata-san searched for missing PR mirror box parts. * Miyakawa-san finished recabling the PR2 rack and got the BS real-time model running again. The model still needs lots of work, but it has the OSEM functionality needed for the next test-hang stage, plus Okutomi-san's improvements. |
* Hirata-san: * Did drawings of SR damper. * Mark, Fabian, Enzo and Hirata-san (at Kamioka): * Took the end plate off the IM to get access to the pitch/roll picos. * Found the pitch pico was unreliable and replaced it. * Found the springs were not stiff enough, and immobilized 7 turns at the end of each with Cu wire to make them stiffer. * Reassembled and rebalanced the IM. * Reassembled and adjusted the IRM. * Discovered that the transverse offset between IRM and IM could be corrected by adjusting the roll of the BF. * Adjusted IM OSEMs to half-way. * Made and installed a new pair of wires for the BF yaw pico on the IM pico adapter (Hirata-san). * Installed an improved LVDT cable made by Hirata-san. * Made and hung posters for the Elites meeting visitors. |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
- Hirata-san:
- Did drawings of SR damper.
- Mark, Fabian, Enzo and Hirata-san (at Kamioka):
- Took the end plate off the IM to get access to the pitch/roll picos.
- Found the pitch pico was unreliable and replaced it.
- Found the springs were not stiff enough, and immobilized 7 turns at the end of each with Cu wire to make them stiffer.
- Reassembled and rebalanced the IM.
- Reassembled and adjusted the IRM.
- Discovered that the transverse offset between IRM and IM could be corrected by adjusting the roll of the BF.
- Adjusted IM OSEMs to half-way.
- Made and installed a new pair of wires for the BF yaw pico on the IM pico adapter (Hirata-san).
- Installed an improved LVDT cable made by Hirata-san.
- Made and hung posters for the Elites meeting visitors.