1891
Comment:
|
1829
|
Deletions are marked like this. | Additions are marked like this. |
Line 5: | Line 5: |
* Activity report for week of 12/19 * Hirata-san made (and Fabian and Mark checked) drawings and parts/fastener lists for the SRM/PRM order and various others: [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5964| D1605964]], [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5965| D1605965]], [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5956| D1605956]], [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5963| D1605963]], [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5977|D1605977]], etc. * Fabian designed a simple two-piece hold-down device to immobilize the SRx IMs during the optic and RM hanging. It avoids having to remachine all the IM support bars to allow for hold-down screws. The Type Bp team might also want to use it. * Aso-san and Mark discussed the [[KAGRA/Subgroups/VIS/VISMinutes20161216#BFIssue|BF issue]] from last week. * It was decided to ask Takahashi-san to take a look at the BF while he's at Kamioka this week. * It was decided to have the BS bottom filter moved to Mitaka for tuneup and adjustment as soon as possible in the new year. * Raffaele, Aso-san, Mark and Fabian discussed having much smaller/shorter BS and SR stub flags plus longer, coil-only OSEMs. * Aso-san volunteered to do the OSEM design. * Hirata-san made Pack'n'Go archives of the existing designs as a baseline for Aso-san. * Hirata-san searched for missing PR mirror box parts. * Miyakawa-san finished recabling the PR2 rack and got the BS real-time model running again. The model still needs lots of work, but it has the OSEM functionality needed for the next test-hang stage, plus Okutomi-san's improvements. |
=== Type B (Mark) === ==== Report for week of 1/29 ==== * Mark made two sets of in-air pico splitter cables (each with a triple for IM and a double for BF) for SR2 and SR3. * Fabian, Hirata-san and Kozu-kun worked on cabling and testing the IM pitch/roll/yaw picos, the BF FR and the BF LVDT. The LVDT connections were initially unreliable and Hirata-san had to redo the pins on the coil wires. * Fabian installed ballast masses in the BF. * Mark worked on schedule. * Mark did inventory of the stepper motor drivers (many were not accounted for on the wiki and/or JGWDoc and one is missing) and reserved two for SR3. * We emptied out the external cleanroom in preparation for installing SS sheet. ==== Plan for week of 2/13 ==== * No work Monday (建国記念の日の振替休日) * Enzo on vacation * Hirata-san at Mitaka Tue (self-evaluation interview). * Shoda-san at Mitaka. * All others at Kamioka. * - * Build IRM around IM. * Cable/test/adjust IM OSEMs. * Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw. ==== Plan for week of 2/19 ==== * Enzo back from Tuesday. * Shoda-san at Mitaka. * Hirata-san at Mitaka Mon+Tue (to receive and wash parts). * All others at Kamioka. * - * Lift BF/... section and check total mass and balance. * Cable and test BF picos. * Add section of SS up to SF ring. * Bring in SF. * Hook BF/... section. * Route cables up to under SF. * Check/adjust total mass of BF/... section. ==== Plan for week of 2/26 ==== * Shoda-san at Mitaka. * - * Add Cu segments to SF cap. * Lift SF/... section and check total mass and balance. ==== Vacation Info ==== * Enzo 1/30-2/19. * Fabian 4/2-4/27 vacation (then gone). |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 1/29
- Mark made two sets of in-air pico splitter cables (each with a triple for IM and a double for BF) for SR2 and SR3.
- Fabian, Hirata-san and Kozu-kun worked on cabling and testing the IM pitch/roll/yaw picos, the BF FR and the BF LVDT. The LVDT connections were initially unreliable and Hirata-san had to redo the pins on the coil wires.
- Fabian installed ballast masses in the BF.
- Mark worked on schedule.
- Mark did inventory of the stepper motor drivers (many were not accounted for on the wiki and/or JGWDoc and one is missing) and reserved two for SR3.
- We emptied out the external cleanroom in preparation for installing SS sheet.
Plan for week of 2/13
- No work Monday (建国記念の日の振替休日)
- Enzo on vacation
- Hirata-san at Mitaka Tue (self-evaluation interview).
- Shoda-san at Mitaka.
- All others at Kamioka.
- -
- Build IRM around IM.
- Cable/test/adjust IM OSEMs.
- Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw.
Plan for week of 2/19
- Enzo back from Tuesday.
- Shoda-san at Mitaka.
- Hirata-san at Mitaka Mon+Tue (to receive and wash parts).
- All others at Kamioka.
- -
- Lift BF/... section and check total mass and balance.
- Cable and test BF picos.
- Add section of SS up to SF ring.
- Bring in SF.
- Hook BF/... section.
- Route cables up to under SF.
- Check/adjust total mass of BF/... section.
Plan for week of 2/26
- Shoda-san at Mitaka.
- -
- Add Cu segments to SF cap.
- Lift SF/... section and check total mass and balance.
Vacation Info
- Enzo 1/30-2/19.
- Fabian 4/2-4/27 vacation (then gone).