Line 5: Line 5:
 * Activity report for week of 12/19
  * Hirata-san made (and Fabian and Mark checked) drawings and parts/fastener lists for the SRM/PRM order and various others: [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5964| D1605964]], [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5965| D1605965]], [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5956| D1605956]], [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5963| D1605963]], [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5977|D1605977]], etc.
  * Fabian designed a simple two-piece hold-down device to immobilize the SRx IMs during the optic and RM hanging. It avoids having to remachine all the IM support bars to allow for hold-down screws. The Type Bp team might also want to use it.
  * Aso-san and Mark discussed the [[KAGRA/Subgroups/VIS/VISMinutes20161216#BFIssue|BF issue]] from last week.
   * It was decided to ask Takahashi-san to take a look at the BF while he's at Kamioka this week.
   * It was decided to have the BS bottom filter moved to Mitaka for tuneup and adjustment as soon as possible in the new year.
  * Raffaele, Aso-san, Mark and Fabian discussed having much smaller/shorter BS and SR stub flags plus longer, coil-only OSEMs.
   * Aso-san volunteered to do the OSEM design.
   * Hirata-san made Pack'n'Go archives of the existing designs as a baseline for Aso-san.
  * Hirata-san searched for missing PR mirror box parts.
  * Miyakawa-san finished recabling the PR2 rack and got the BS real-time model running again. (The problem had been a new requirement for a safe.snap file to be provided in the burt directory, which was imposed by RCG2.9.7.) The model still needs lots of work, but it has the OSEM functionality needed for the next test-hang stage, plus Okutomi-san's improvements.
=== Type B (Mark) ===
==== Past week report ====
At Kamioka (Mark, Fabian, Hirata-san, Yoshioka-kun):
 * We reconfigured the top of the assembly frame.
 * We cleaned the assembly frame, blowing dust out of the grooves and wiping all surfaces.
 * We recentered the optic table in the bottom of the frame and adjusted the frame until the top was centered over the optic table. We also recentered the trolleys.
 * We re-installed, centered and leveled the IM.
 * We solved two issues with the new wire clamps:
  * Some holes were not properly threaded - Hirata-san retapped them.
  * Some locating pins were loose - we glued them.
 * We mounted the BS mirror box on the trolley and brought it under the IM.
 * We installed the winch system and the 300 µm wires for the BS.
 * We set up the optical lever.
 * Hirata-san finished the new BF. We moved the old BF out of the cleanbooth and the new one in.
 * We suspended the BS and set its height and pitch.

==== Plan for week of 8/7 ====
Site closure: Friday<<BR>>
Vacation: Enzo (Mon), Fabian (Mon-Fri)<<BR>>
Kamioka: Mark (Mon-Thu), Enzo (Tue-Thu), Yoshioka-kun (Tue, Wed), Ohishi (TBD).<<BR>>
 * Adjust RM OSEMs; add new RM cable clamp piece.
 * Hang RM.
 * Run new (longer) OSEM cables.
 * Weigh/trim BS/RM/IM.
 * Suspend BS/RM/IM, add IRM.
 * Lay new in-air OSEM cables.
Mitaka: Hirata-san (Mon-Fri)<<BR>>
 * SR stuff.

==== Plan for week of 8/14 ====
Site closure: Mon, Tue<<BR>>
Vacation: Fabian (Mon-Fri)
Kamioka: Mark (Wed-Fri), Enzo (Wed-Fri), Yoshioka-kun (Wed, Fri), Ohishi (TBD).<<BR>>
 * Bring in BF and hang BS/RM/IM/IRM.
Mitaka: Hirata-san (Mon-Fri)<<BR>>
 * SR Stuff?
Vacation Info:
Enzo: Sat 7/22 through Sun 8/6
Fabian: Fri 8/4 through Mon 8/21
Mark: TBD Mid-Oct

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Fabian, Hirata-san, Yoshioka-kun):

  • We reconfigured the top of the assembly frame.
  • We cleaned the assembly frame, blowing dust out of the grooves and wiping all surfaces.
  • We recentered the optic table in the bottom of the frame and adjusted the frame until the top was centered over the optic table. We also recentered the trolleys.
  • We re-installed, centered and leveled the IM.
  • We solved two issues with the new wire clamps:
    • Some holes were not properly threaded - Hirata-san retapped them.
    • Some locating pins were loose - we glued them.
  • We mounted the BS mirror box on the trolley and brought it under the IM.
  • We installed the winch system and the 300 µm wires for the BS.
  • We set up the optical lever.
  • Hirata-san finished the new BF. We moved the old BF out of the cleanbooth and the new one in.
  • We suspended the BS and set its height and pitch.

Plan for week of 8/7

Site closure: Friday
Vacation: Enzo (Mon), Fabian (Mon-Fri)
Kamioka: Mark (Mon-Thu), Enzo (Tue-Thu), Yoshioka-kun (Tue, Wed), Ohishi (TBD).

  • Adjust RM OSEMs; add new RM cable clamp piece.
  • Hang RM.
  • Run new (longer) OSEM cables.
  • Weigh/trim BS/RM/IM.
  • Suspend BS/RM/IM, add IRM.
  • Lay new in-air OSEM cables.

Mitaka: Hirata-san (Mon-Fri)

  • SR stuff.

Plan for week of 8/14

Site closure: Mon, Tue
Vacation: Fabian (Mon-Fri) Kamioka: Mark (Wed-Fri), Enzo (Wed-Fri), Yoshioka-kun (Wed, Fri), Ohishi (TBD).

  • Bring in BF and hang BS/RM/IM/IRM.

Mitaka: Hirata-san (Mon-Fri)

  • SR Stuff?

Vacation Info: Enzo: Sat 7/22 through Sun 8/6 Fabian: Fri 8/4 through Mon 8/21 Mark: TBD Mid-Oct

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)