* Activity report for week of 12/19 * Hirata-san made (and Fabian and Mark checked) drawings and parts/fastener lists for the SRM/PRM order and various others: [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5964| D1605964]], [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5965| D1605965]], [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5956| D1605956]], [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5963| D1605963]], [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5977|D1605977]], etc. * Fabian designed a simple two-piece hold-down device to immobilize the SRx IMs during the optic and RM hanging. It avoids having to remachine all the IM support bars to allow for hold-down screws. The Type Bp team might also want to use it. * Aso-san and Mark discussed the [[KAGRA/Subgroups/VIS/VISMinutes20161216#BFIssue|BF issue]] from last week. * It was decided to ask Takahashi-san to take a look at the BF while he's at Kamioka this week. * It was decided to have the BS bottom filter moved to Mitaka for tuneup and adjustment as soon as possible in the new year. * Raffaele, Aso-san, Mark and Fabian discussed having much smaller/shorter BS and SR stub flags plus longer, coil-only OSEMs. * Aso-san volunteered to do the OSEM design. * Hirata-san made Pack'n'Go archives of the existing designs as a baseline for Aso-san. * Hirata-san searched for missing PR mirror box parts. * Miyakawa-san finished recabling the PR2 rack and got the BS real-time model running again. (The problem had been a new requirement for a safe.snap file to be provided in the burt directory, which was imposed by version RCG2.9.7 of the real-time software.) The model still needs lots of work, but it has the OSEM functionality needed for the next stage of the BS test hang, plus Okutomi-san's improvements. |
=== Type B (Mark) === ==== Past week report ==== At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun): * ==== Plan for week of 9/4 ==== Mark, Fabian, Enzo (Tue-Fri), Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun (Thu, Fri) * Retrieve PEEK piece from BF. * Crane SF back in. * Suspend BF/IRM/IM/RM/BS. * Test SF FR. * Calibrate SF LVDT. * Install SF cap; route cables. * Lift and weigh SF/BF/IRM/IM/RM/BS. * Adjust SF ballast. ==== Plan for week of 9/13 ==== Mark (except Wed), Fabian (except ASJ), Enzo, Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun * Prepare magnet ring. * Bring in PI. * Route cables. * Suspend SF/..., adjust tilt of SF and total mass. * Adjust damper gap. ==== Vacation Info ==== Mark: 10/16-24 |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past week report
At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):
Plan for week of 9/4
Mark, Fabian, Enzo (Tue-Fri), Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun (Thu, Fri)
- Retrieve PEEK piece from BF.
- Crane SF back in.
- Suspend BF/IRM/IM/RM/BS.
- Test SF FR.
- Calibrate SF LVDT.
- Install SF cap; route cables.
- Lift and weigh SF/BF/IRM/IM/RM/BS.
- Adjust SF ballast.
Plan for week of 9/13
Mark (except Wed), Fabian (except ASJ), Enzo, Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun
- Prepare magnet ring.
- Bring in PI.
- Route cables.
- Suspend SF/..., adjust tilt of SF and total mass.
- Adjust damper gap.
Vacation Info
Mark: 10/16-24