 * Activity report for weeks of 12/26 and 1/2 === Type B (Mark) ===
==== Past week report ====
At Kamioka (Mark, Fabian, Enzo, Hirata-san):
 * We disconnected the in-vacuum and in-air cabling from the feedthroughs.
 * We removed crossbars below BF and SF.
 * We set the SF damper to 4 mm clearance.
 * We adjusted the jacks to nominal height.
 * We removed the geophones and PI yaw stepper for craning.
 * We craned the suspension into the tank, and hooked the LBB Cu ring.
 * We replaced the geophones etc.
 * We unlocked all but the IP and adjusted the jacks until the pendulum was centered in the security structure.
 * We unlocked the IP and adjusted to to center with the jacks and fishing rods.
 * We craned the vacuum tank lid+ring back on, and then removed just the lid (only).
 * We unclamped the LBB damper rings and removed the spacers.
 * We removed the blocks and shims supporting the LBB, inserted the long screw feet and hooked the LBB to the Cu damper ring.
 * We added 2*31.5 kg of ballast to the LBB, which got the blades to the point where firm pressure would depress the tips.
 * We reconnected the in-vacuum cabling. In ≈15 places we opted to omit the Type 1 cable and use a F-F gender bender.
 * We reconnected all but four of the in-air cables.
Line 7: Line 24:
{{{Dear Mark,

I did for Type-B as below,
・modified parts list and screw list for Payload.
・sent lists to i-ject and asked for quotes.
(But we need to send latest list again.)
・made drawings for some jigs and some parts for payload.

For PR
・searched glueing jigs.
・washed and assembled recoilmass base for mirror hanging jigs, and sent them to Kamioka.
・washed additional masses for IM and sent them to Kamioka.

For others
・washed IMMT plate and send them to Kamioka.

Best regards,
Hirata
}}}
{{{Hello,

Succinctly, it is as follows:

1. Mechanical design:

    a. Pull down system to fix the power recycling IM to the EQ stop.
    b. EQ stop for the BS recoil mass.

2. Checked assembly PR/SR drawings. There were few corrections/changes.

3. Checked fastener list. There were few corrections/changes.

4. Checked component list for the manufacture order. There were few corrections/changes.

5. I helped in searching for the PR mirror box missing pieces at Mitaka.

Regards,

Fabian
}}}
==== Plan for week of 6/26 ====
Mark and Enzo at Kamioka:
 * Double-check where gender-benders were used.
 * Finish connecting in-air cabling.
 * Debug all cabling.
 * Work with Simon to set up LSOL.
Fabian at Mitaka:
 * Design final ballast masses for IM, BF and SF assuming no BF rebuild (needs to be adaptable).
 * Check all items for BS flag/prism gluing are available (prisms, flags, jigs, mirror box, glue, scale, mixing tools etc).
Hirata-san at Mitaka:
 * Do new 3D CAD:
  * BS Test Hang build, with top of tank, full suspension, and LBB damper all reversed.
  * Final BS build, as above, but with everything BF down rotated back to original.
   * In-tank version.
   * On-assembly-frame version. (Adjust jack positions if possible, or leave for Mark to do.)
  * SR2 on BS assembly frame. (Adjust jack positions if possible, or leave for Mark to do.)

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Fabian, Enzo, Hirata-san):

  • We disconnected the in-vacuum and in-air cabling from the feedthroughs.
  • We removed crossbars below BF and SF.
  • We set the SF damper to 4 mm clearance.
  • We adjusted the jacks to nominal height.
  • We removed the geophones and PI yaw stepper for craning.
  • We craned the suspension into the tank, and hooked the LBB Cu ring.
  • We replaced the geophones etc.
  • We unlocked all but the IP and adjusted the jacks until the pendulum was centered in the security structure.
  • We unlocked the IP and adjusted to to center with the jacks and fishing rods.
  • We craned the vacuum tank lid+ring back on, and then removed just the lid (only).
  • We unclamped the LBB damper rings and removed the spacers.
  • We removed the blocks and shims supporting the LBB, inserted the long screw feet and hooked the LBB to the Cu damper ring.
  • We added 2*31.5 kg of ballast to the LBB, which got the blades to the point where firm pressure would depress the tips.
  • We reconnected the in-vacuum cabling. In ≈15 places we opted to omit the Type 1 cable and use a F-F gender bender.
  • We reconnected all but four of the in-air cables.

Plan for week of 6/26

Mark and Enzo at Kamioka:

  • Double-check where gender-benders were used.
  • Finish connecting in-air cabling.
  • Debug all cabling.
  • Work with Simon to set up LSOL.

Fabian at Mitaka:

  • Design final ballast masses for IM, BF and SF assuming no BF rebuild (needs to be adaptable).
  • Check all items for BS flag/prism gluing are available (prisms, flags, jigs, mirror box, glue, scale, mixing tools etc).

Hirata-san at Mitaka:

  • Do new 3D CAD:
    • BS Test Hang build, with top of tank, full suspension, and LBB damper all reversed.
    • Final BS build, as above, but with everything BF down rotated back to original.
      • In-tank version.
      • On-assembly-frame version. (Adjust jack positions if possible, or leave for Mark to do.)
    • SR2 on BS assembly frame. (Adjust jack positions if possible, or leave for Mark to do.)