 * Activity report for weeks of 12/26 and 1/2 === Type B (Mark) ===
==== Past week report ====
At Kamioka (Mark, Fabian, Hirata-san, Yoshioka-kun):
 * We reconfigured the top of the assembly frame.
 * We cleaned the assembly frame, blowing dust out of the grooves and wiping all surfaces.
 * We recentered the optic table in the bottom of the frame and adjusted the frame until the top was centered over the optic table. We also recentered the trolleys.
 * We re-installed, centered and leveled the IM.
 * We solved two issues with the new wire clamps:
  * Some holes were not properly threaded - Hirata-san retapped them.
  * Some locating pins were loose - we glued them.
 * We mounted the BS mirror box on the trolley and brought it under the IM.
 * We installed the winch system and the 300 µm wires for the BS.
 * We set up the optical lever.
 * Hirata-san finished the new BF. We moved the old BF out of the cleanbooth and the new one in.
 * We suspended the BS and set its height and pitch.
Line 7: Line 21:
{{{Dear Mark, ==== Plan for week of 8/7 ====
Site closure: Friday<<BR>>
Vacation: Enzo (Mon), Fabian (Mon-Fri)<<BR>>
Kamioka: Mark (Mon-Thu), Enzo (Tue-Thu), Yoshioka-kun (Tue, Wed), Ohishi (TBD).<<BR>>
 * Adjust RM OSEMs; add new RM cable clamp piece.
 * Hang RM.
 * Run new (longer) OSEM cables.
 * Weigh/trim BS/RM/IM.
 * Suspend BS/RM/IM, add IRM.
 * Lay new in-air OSEM cables.
Mitaka: Hirata-san (Mon-Fri)<<BR>>
 * SR stuff.
Line 9: Line 34:
I did for Type-B as below,
・modified parts list and screw list for Payload.
・sent lists to i-ject and asked for quotes.
(But we need to send latest list again.)
・made drawings for some jigs and some parts for payload.

For PR
・searched glueing jigs.
・washed and assembled recoilmass base for mirror hanging jigs, and sent them to Kamioka.
・washed additional masses for IM and sent them to Kamioka.

For others
・washed IMMT plate and send them to Kamioka.

Best regards,
Hirata
}}}
{{{Hello,

Succinctly, it is as follows:

1. Mechanical design:

    a. Pull down system to fix the power recycling IM to the EQ stop.
    b. EQ stop for the BS recoil mass.

2. Checked assembly PR/SR drawings. There were few corrections/changes.

3. Checked fastener list. There were few corrections/changes.

4. Checked component list for the manufacture order. There were few corrections/changes.

5. I helped in searching for the PR mirror box missing pieces at Mitaka.

Regards,

Fabian
}}}
==== Plan for week of 8/14 ====
Site closure: Mon, Tue<<BR>>
Vacation: Fabian (Mon-Fri)
Kamioka: Mark (Wed-Fri), Enzo (Wed-Fri), Yoshioka-kun (Wed, Fri), Ohishi (TBD).<<BR>>
 * Bring in BF and hang BS/RM/IM/IRM.
Mitaka: Hirata-san (Mon-Fri)<<BR>>
 * SR Stuff?
Vacation Info:
Enzo: Sat 7/22 through Sun 8/6
Fabian: Fri 8/4 through Mon 8/21
Mark: TBD Mid-Oct

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Fabian, Hirata-san, Yoshioka-kun):

  • We reconfigured the top of the assembly frame.
  • We cleaned the assembly frame, blowing dust out of the grooves and wiping all surfaces.
  • We recentered the optic table in the bottom of the frame and adjusted the frame until the top was centered over the optic table. We also recentered the trolleys.
  • We re-installed, centered and leveled the IM.
  • We solved two issues with the new wire clamps:
    • Some holes were not properly threaded - Hirata-san retapped them.
    • Some locating pins were loose - we glued them.
  • We mounted the BS mirror box on the trolley and brought it under the IM.
  • We installed the winch system and the 300 µm wires for the BS.
  • We set up the optical lever.
  • Hirata-san finished the new BF. We moved the old BF out of the cleanbooth and the new one in.
  • We suspended the BS and set its height and pitch.

Plan for week of 8/7

Site closure: Friday
Vacation: Enzo (Mon), Fabian (Mon-Fri)
Kamioka: Mark (Mon-Thu), Enzo (Tue-Thu), Yoshioka-kun (Tue, Wed), Ohishi (TBD).

  • Adjust RM OSEMs; add new RM cable clamp piece.
  • Hang RM.
  • Run new (longer) OSEM cables.
  • Weigh/trim BS/RM/IM.
  • Suspend BS/RM/IM, add IRM.
  • Lay new in-air OSEM cables.

Mitaka: Hirata-san (Mon-Fri)

  • SR stuff.

Plan for week of 8/14

Site closure: Mon, Tue
Vacation: Fabian (Mon-Fri) Kamioka: Mark (Wed-Fri), Enzo (Wed-Fri), Yoshioka-kun (Wed, Fri), Ohishi (TBD).

  • Bring in BF and hang BS/RM/IM/IRM.

Mitaka: Hirata-san (Mon-Fri)

  • SR Stuff?

Vacation Info: Enzo: Sat 7/22 through Sun 8/6 Fabian: Fri 8/4 through Mon 8/21 Mark: TBD Mid-Oct