Deletions are marked like this. | Additions are marked like this. |
Line 5: | Line 5: |
* Activity report for weeks of 12/26 and 1/2 | === Type B (Mark) === ==== Past week report ==== |
Line 7: | Line 8: |
{{{Dear Mark, | * Mark worked on SR2 planning. * Mark thought through what would be required to swap an optic (e.g., SRM) in situ (JGW-T1707436). * Hirata-san tried removing disks from IM flags (so we could reuse them in flag bases and make a complete set for SR2) but only got 1 of 4 out. * Hirata-san ordered more disks for IM flags. * Hirata-san asked for quotes on SF LBB blades. * Hirata-san got a reduced quote for the LBB damper rings. * Hirata-san received and cleaned suspension wires for the SR. * Fabian worked on the SR mass budget. * Fabian worked out the COM of the SR2 optic, and Mark used it to derive the proper prism positions. * Enzo and Kozu-kun worked on control filter design and installation. |
Line 9: | Line 19: |
I did for Type-B as below, ・modified parts list and screw list for Payload. ・sent lists to i-ject and asked for quotes. (But we need to send latest list again.) ・made drawings for some jigs and some parts for payload. |
==== Plan for week of 11/27 ==== * Fabian at commissioning workshop * Hirata-san at Kamioka Tue-Fri to work with Mirapro on SRM LBB installation. * All others (Mark, Enzo, Shoda-san, Kozu-kun) at Kamioka to start SR2 assembly. * Mark from Mon lunchtime. * Kozu-kun from Mon lunchtime through Wed. * Mirror gluing. * SR2 rack setup. |
Line 15: | Line 28: |
For PR ・searched glueing jigs. ・washed and assembled recoilmass base for mirror hanging jigs, and sent them to Kamioka. ・washed additional masses for IM and sent them to Kamioka. |
==== Plan for week of 12/4 ==== * All at Kamioka * IM assembly and pico test. * Assembly frame alignment and optical table centering. * OL setup. |
Line 20: | Line 34: |
For others ・washed IMMT plate and send them to Kamioka. Best regards, Hirata }}} {{{Hello, Succinctly, it is as follows: 1. Mechanical design: a. Pull down system to fix the power recycling IM to the EQ stop. b. EQ stop for the BS recoil mass. 2. Checked assembly PR/SR drawings. There were few corrections/changes. 3. Checked fastener list. There were few corrections/changes. 4. Checked component list for the manufacture order. There were few corrections/changes. 5. I helped in searching for the PR mirror box missing pieces at Mitaka. Regards, Fabian }}} |
==== Vacation Info ==== * Mark 12/22-1/3 * Enzo TBD, probably 12/22-1/3 * Fabian 12/22-1/5 * Hirata-san 12/21-22 (conference) |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past week report
- Mark worked on SR2 planning.
- Mark thought through what would be required to swap an optic (e.g., SRM) in situ (JGW-T1707436).
- Hirata-san tried removing disks from IM flags (so we could reuse them in flag bases and make a complete set for SR2) but only got 1 of 4 out.
- Hirata-san ordered more disks for IM flags.
- Hirata-san asked for quotes on SF LBB blades.
- Hirata-san got a reduced quote for the LBB damper rings.
- Hirata-san received and cleaned suspension wires for the SR.
- Fabian worked on the SR mass budget.
- Fabian worked out the COM of the SR2 optic, and Mark used it to derive the proper prism positions.
- Enzo and Kozu-kun worked on control filter design and installation.
Plan for week of 11/27
- Fabian at commissioning workshop
- Hirata-san at Kamioka Tue-Fri to work with Mirapro on SRM LBB installation.
- All others (Mark, Enzo, Shoda-san, Kozu-kun) at Kamioka to start SR2 assembly.
- Mark from Mon lunchtime.
- Kozu-kun from Mon lunchtime through Wed.
- Mirror gluing.
- SR2 rack setup.
Plan for week of 12/4
- All at Kamioka
- IM assembly and pico test.
- Assembly frame alignment and optical table centering.
- OL setup.