Line 5: Line 5:
 * Activity report for weeks of 12/26 and 1/2 === Type B (Mark) ===
==== Past week report ====
At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san):
Line 7: Line 9:
{{{
Dear Mark,
 * Realized that the SF/BF/... section doesn't need 6 kg added, it needs 6 kg ''removed'', but none to remove. The 20 kg extra in the BF to match the SF GAS filter makes the whole chain overload the PI GAS filter.
 * Lifted the SF/BF/... section to check for net weight and balance. Was 307 kg (cf. G&M's measurement of 301 kf in 2012 for the F0). Can be balanced with only 63 g extra.
 * Went to build up the LBB blade units but discovered that the holes in the base of the blades are two small (are Ø11 mm; should be Ø12 MM). 3D CAD was correct - error was in the 2D drawing. Shipped the blades away for modification.
 * Tested the SF LVDT actuation and worked on debugging it. Still not working.
 * Prepared the PI for being lifted, and the top of the assembly frame for receiving it.
 * Searched for and found the old PI-SF rod.
 * Did safety improvements after Enzo hit his head on a flange bolt: reversed all the bolts on the ±X sides of the BS and put caution tape on them.
 * Debugged Kokeyama-san's changes to the real-time model for the DIO, and started on TFs to check the output filter compensation is working.
Line 10: Line 18:
I did for Type-B as below,
・modified parts list and screw list for Payload.
・sent lists to i-ject and asked for quotes.
(But we need to send latest list again.)
・made drawings for some jigs and some parts for payload.
==== Plan for coming weeks ====
For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]].
Line 16: Line 21:
For PR
・searched glueing jigs.
・washed and assembled recoilmass base for mirror hanging jigs, and sent them to Kamioka.
・washed additional masses for IM and sent them to Kamioka.
Week of 4/24 (four-day week):
 * Crane in PI.
 * Connect SF/BF... section and see if we're indeed overweight and by exactly how much.
 * Finish debugging SF LVDT actuation.
Line 21: Line 26:
For others
・washed IMMT plate and send them to Kamioka.

Best regards,
Hirata
}}}
{{{
Hello,

Succinctly, it is as follows:

1. Mechanical design:

    a. Pull down system to fix the power recycling IM to the EQ stop.
    b. EQ stop for the BS recoil mass.

2. Checked assembly PR/SR drawings. There were few corrections/changes.

3. Checked fastener list. There were few corrections/changes.

4. Checked component list for the manufacture order. There were few corrections/changes.

5. I helped in searching for the PR mirror box missing pieces at Mitaka.

Regards,

Fabian
}}}
Week of 5/1:
 * No activity (Golden Week).

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san):

  • Realized that the SF/BF/... section doesn't need 6 kg added, it needs 6 kg removed, but none to remove. The 20 kg extra in the BF to match the SF GAS filter makes the whole chain overload the PI GAS filter.

  • Lifted the SF/BF/... section to check for net weight and balance. Was 307 kg (cf. G&M's measurement of 301 kf in 2012 for the F0). Can be balanced with only 63 g extra.

  • Went to build up the LBB blade units but discovered that the holes in the base of the blades are two small (are Ø11 mm; should be Ø12 MM). 3D CAD was correct - error was in the 2D drawing. Shipped the blades away for modification.
  • Tested the SF LVDT actuation and worked on debugging it. Still not working.
  • Prepared the PI for being lifted, and the top of the assembly frame for receiving it.
  • Searched for and found the old PI-SF rod.
  • Did safety improvements after Enzo hit his head on a flange bolt: reversed all the bolts on the ±X sides of the BS and put caution tape on them.
  • Debugged Kokeyama-san's changes to the real-time model for the DIO, and started on TFs to check the output filter compensation is working.

Plan for coming weeks

For more detail, see KAGRA/Subgroups/VIS/TypeB/ToDo.

Week of 4/24 (four-day week):

  • Crane in PI.
  • Connect SF/BF... section and see if we're indeed overweight and by exactly how much.
  • Finish debugging SF LVDT actuation.

Week of 5/1:

  • No activity (Golden Week).