1206
Comment:
|
1581
|
Deletions are marked like this. | Additions are marked like this. |
Line 5: | Line 5: |
* Activity report for weeks of 12/26 and 1/2 | === Type B (Mark) === ==== Past two weeks report ==== Kamioka (Mark, Enzo, Kozu-kun): * Supported IA team. * Replaced LPCDs for IM OSEMs with HPCDs for increased pitch/yaw range. * Re-zeroed OL after significant change of beam position during IA. * Re-laid-out OL to improve focus of lens to LEN QPD. * Offloaded the pitch/yaw actuation at the IM OSEMs using the IM pitch/yaw picos. * Enzo worked on design of control loops using the OL. * Kozu-kun worked on diagonalizing the OL. |
Line 7: | Line 16: |
{{{ Dear Mark, |
Mitaka (Fabian, Hirata-san): * Fabian did mechanical design: * F0 FR * Cable clamps for the SR IP base. * New SR recoil ballast masses. * LBB ballast. * Update of BS 3D CAD with the as-built ballast. * Hirata-san * made and updated inventory list for SR. * made order list and asked some quotes. * Ordered some parts. * Talked with mirapro about SRM optical bench. * Made some drawings for SR preparation. |
Line 10: | Line 30: |
I did for Type-B as below, ・modified parts list and screw list for Payload. ・sent lists to i-ject and asked for quotes. (But we need to send latest list again.) ・made drawings for some jigs and some parts for payload. |
==== Plan for week of 11/13 ==== |
Line 16: | Line 32: |
For PR ・searched glueing jigs. ・washed and assembled recoilmass base for mirror hanging jigs, and sent them to Kamioka. ・washed additional masses for IM and sent them to Kamioka. |
Enzo and Kozu-kun at Mitaka * Servos * Diagonalization of OL * TFs of BF * Documentation |
Line 21: | Line 38: |
For others ・washed IMMT plate and send them to Kamioka. |
Mark and Fabian at Kamioka. * Mark attends commissioning workshop at U Toyama. * Support BF characterization work. * Prepare for mirror gluing. * Prepare for IM assembly. |
Line 24: | Line 44: |
Best regards, Hirata }}} {{{ Hello, |
Hirata-san at Mitaka * SR procurement. * Get BS prism-gluing jigs reworked for use with PR/SR mirror box. |
Line 30: | Line 48: |
Succinctly, it is as follows: 1. Mechanical design: a. Pull down system to fix the power recycling IM to the EQ stop. b. EQ stop for the BS recoil mass. 2. Checked assembly PR/SR drawings. There were few corrections/changes. 3. Checked fastener list. There were few corrections/changes. 4. Checked component list for the manufacture order. There were few corrections/changes. 5. I helped in searching for the PR mirror box missing pieces at Mitaka. Regards, Fabian }}} |
==== Plan for week of 11/20 ==== * Holiday on Thu 3/23 * Fabian at commissioning workshop * |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past two weeks report
Kamioka (Mark, Enzo, Kozu-kun):
- Supported IA team.
- Replaced LPCDs for IM OSEMs with HPCDs for increased pitch/yaw range.
- Re-zeroed OL after significant change of beam position during IA.
- Re-laid-out OL to improve focus of lens to LEN QPD.
- Offloaded the pitch/yaw actuation at the IM OSEMs using the IM pitch/yaw picos.
- Enzo worked on design of control loops using the OL.
- Kozu-kun worked on diagonalizing the OL.
Mitaka (Fabian, Hirata-san):
- Fabian did mechanical design:
- F0 FR
- Cable clamps for the SR IP base.
- New SR recoil ballast masses.
- LBB ballast.
- Update of BS 3D CAD with the as-built ballast.
- Hirata-san
- made and updated inventory list for SR.
- made order list and asked some quotes.
- Ordered some parts.
- Talked with mirapro about SRM optical bench.
- Made some drawings for SR preparation.
Plan for week of 11/13
Enzo and Kozu-kun at Mitaka
- Servos
- Diagonalization of OL
- TFs of BF
- Documentation
Mark and Fabian at Kamioka.
- Mark attends commissioning workshop at U Toyama.
- Support BF characterization work.
- Prepare for mirror gluing.
- Prepare for IM assembly.
Hirata-san at Mitaka
- SR procurement.
- Get BS prism-gluing jigs reworked for use with PR/SR mirror box.
Plan for week of 11/20
- Holiday on Thu 3/23
- Fabian at commissioning workshop