Size: 1206
Comment:
|
Size: 1653
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 5: | Line 5: |
* Activity report for weeks of 12/26 and 1/2 | === Type B (Mark) === ==== Report for week of 3/26 ==== |
Line 7: | Line 8: |
{{{ Dear Mark, |
|
Line 10: | Line 9: |
I did for Type-B as below, ・modified parts list and screw list for Payload. ・sent lists to i-ject and asked for quotes. (But we need to send latest list again.) ・made drawings for some jigs and some parts for payload. |
* We finished tuning of BF No. 1. * We wired the LVDT, Picomotor and StepperMotor of BF No. 1. |
Line 16: | Line 13: |
For PR ・searched glueing jigs. ・washed and assembled recoilmass base for mirror hanging jigs, and sent them to Kamioka. ・washed additional masses for IM and sent them to Kamioka. |
* We finished tuning of BF No. 7. * We wired the LVDT, Picomotor and StepperMotor of BF No. 7. |
Line 21: | Line 16: |
For others ・washed IMMT plate and send them to Kamioka. |
|
Line 24: | Line 17: |
Best regards, Hirata }}} {{{ Hello, |
|
Line 30: | Line 18: |
Succinctly, it is as follows: | * SF check (Hirata-san++). * We checked the load capacity with and without the cap. * We checked fit of caps. For the SF No. * Add cable clamps to bases. * Add cable clamps and Cu segments to caps (only if they fit well). * Cable LVDTs and steppers. |
Line 32: | Line 25: |
1. Mechanical design: | * We finished the SR3 in-air cabling. |
Line 34: | Line 27: |
a. Pull down system to fix the power recycling IM to the EQ stop. b. EQ stop for the BS recoil mass. |
==== Plan for week of 4/2 ==== * Mark at Mitaka Mon, Kamioka from Tue. * Shoda-san at Mitaka * Others at Kamioka * -- * Glue SR3 (if available) * Build 2xIM, 2xIRM (if parts available - due 3/30) |
Line 37: | Line 35: |
2. Checked assembly PR/SR drawings. There were few corrections/changes. | ==== Plan for week of 4/9 ==== * Shoda-san at Mitaka * Others at Kamioka * -- * Finish IMs and IRMs * Build 1xRM |
Line 39: | Line 42: |
3. Checked fastener list. There were few corrections/changes. | ==== Plan for week of 4/16 ==== * Start SR3 Hang? |
Line 41: | Line 45: |
4. Checked component list for the manufacture order. There were few corrections/changes. | ==== Plan for week of 4/23 ==== * F0 blade prototype test |
Line 43: | Line 48: |
5. I helped in searching for the PR mirror box missing pieces at Mitaka. | ==== Plan for week of 4/30 ==== * Golden Week! |
Line 45: | Line 51: |
Regards, | ==== To-Do Lists, Schedule ==== * [[KAGRA/Subgroups/VIS/TypeB/March2018]] * [[KAGRA/Subgroups/VIS/TypeB/April2018]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]] |
Line 47: | Line 58: |
Fabian }}} |
==== Vacation Info ==== * Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun) * Fabian vacation, 3/26-4/27 (then gone). |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 3/26
- We finished tuning of BF No. 1.
We wired the LVDT, Picomotor and StepperMotor of BF No. 1.
- We finished tuning of BF No. 7.
We wired the LVDT, Picomotor and StepperMotor of BF No. 7.
- SF check (Hirata-san++).
- We checked the load capacity with and without the cap.
- We checked fit of caps. For the SF No.
- Add cable clamps to bases.
- Add cable clamps and Cu segments to caps (only if they fit well).
- Cable LVDTs and steppers.
- We finished the SR3 in-air cabling.
Plan for week of 4/2
- Mark at Mitaka Mon, Kamioka from Tue.
- Shoda-san at Mitaka
- Others at Kamioka
- --
- Glue SR3 (if available)
- Build 2xIM, 2xIRM (if parts available - due 3/30)
Plan for week of 4/9
- Shoda-san at Mitaka
- Others at Kamioka
- --
- Finish IMs and IRMs
- Build 1xRM
Plan for week of 4/16
- Start SR3 Hang?
Plan for week of 4/23
- F0 blade prototype test
Plan for week of 4/30
- Golden Week!
To-Do Lists, Schedule
Vacation Info
- Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
- Fabian vacation, 3/26-4/27 (then gone).