Differences between revisions 116 and 143 (spanning 27 versions)
Revision 116 as of 2017-01-06 13:19:19
Size: 1856
Editor: MarkBarton
Comment:
Revision 143 as of 2017-05-18 18:34:50
Size: 3401
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Activity report for weeks of 12/26 and 1/2 === Type B (Mark) ===
==== Past week report ====
At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san):
Line 7: Line 9:
  * Hirata-san:
   * Modified parts list and screw list for payload.
   * Sent lists to i-ject and asked for preliminary quotes.
   * Made drawings for some jigs (PR hold-down jig) and some parts for payload (PR/SR wire clamps with disposable jaw pieces - improved version with disposable pieces in both primary and secondary clamps).
   * For Type Bp:
    * Searched for PR gluing jigs.
    * Washed and assembled recoilmass base for mirror hanging jigs, and sent them to Kamioka.
    * Washed additional masses for IM and sent them to Kamioka.
   * For others:
    * Washed IMMT plate and sent them to Kamioka.
  * Fabian
   * Designed a pull down system to fix the PR IM to the EQ stop (similar to the SR one).
   * Worked on design of the SR assembly frame. As hoped, the SR version can be almost identical to the BS version.
   * Worked on design of additional trim mass (≈18 kg) for the BS BF.
   * Checked assembly PR/SR drawings. There were a few corrections/changes.
   * Checked fastener list. There were few corrections/changes.
   * Checked component list for the manufacture order. There were few corrections/changes.
   * Helped in searching for the PR gluing jigs.
  * Mark
   * Started design of SR assembly frame (but then passed it to Fabian).
   * Worked on task lists and schedule.
 * Plan for 1/10-13
  * Mark and Fabian at Kamioka:
   * Finish rebalance of IM
   * Reinstall IRM, adjust OSEMs
   * Replace broken Type 3 cable.
   * Do TFs from IRM OSEMs to IRM and IM OSEMs.
   * Cable up and test BF LVDT and fishing rod (time permitting).
   * Disconnect BF and ship back to Mitaka (time permitting).
  * Hirata-san:
   * More SR procurement.
 * We cleared space for the PR2 team to remove a bellows from their tank.
 * We installed safety bars on the pillars near the assembly frame at about waist height for someone on the tall ladder. We reinforced the clamps with cable ties.
 * We bridged a gap in the second floor on the -X side of the SF2 tank with spare floor panels.
 * We removed the PI from the assembly frame.
 * We encountered a problem with the PI-SF rod jamming in the SF. We finally got it out by clamping a pair of vice grips to the rod and hammering. We found that the receptacle part was the right size (7.0 mm) but had been deformed around the edge. Hirata-san used a knife and sandpaper to lean up the edge and then ultrasonically cleaned it.
 * We removed the LLB blade units from the PI, removed the blades from the clamps and sent the blades away for more rework to fix the length problem. Fortunately the tab section at the tip is fairly long, so we can just add a second hole further from the end.
 * We tested the SR fishing rod again, but it would only go up, not down. We found that reseting the driver fixed it, but we also moved the driver boxes into the cleanbooth to reduce the length of the motor cables. (Instead, we had to run some long DC and LAN cables.)
 * We adjusted the limit nut on the SF fishing rod to increase the range.
 * We debugged an issue with the SF keystone sitting lower than previously and found we had accidentally left two eyebolts on top of the BF. We retrimmed the BF/... section to reset the keystone to nominal (65.5 mm) with the fishing rod at mid-range.
 * We removed one segment of the Cu ring on the SF cap and reconfigured the other two to be symmetrical.
 * Fabian designed a layout for the SF damper ring magnets that would work with the modified Cu ring, and placed the magnets with the template. The poles of the magnets were not on the expected faces so we had to stand the magnets up, with the 12x12 faces sideways and the 10x12 mm pole faces up/down. We will need to raise the magnet ring by 2 mm to allow for the extra height.
 * Hirata-san made a cable for the PI v vertical LVDT. We identified the coils by their resistances which were similar to BF/SF: Primary 193Ω, Secondary 75Ω, Actuation 112Ω.
 * We added the remaining cable clamps to the PI (some places had not been accessible with the PI on the frame).
 * We placed the geophones but discovered we didn't have some mounting brackets called out in the 3D CAD.
 * Enzo made a PI yaw/vertical stepper adapter cable and a trial geophone descrambler cable (one of three).
 * We found that part of the problem with the SF LVDT was that the actuation had not been enabled for SF or F0 in the real-time model. We fixed the model and are now able to drive the LVDT actuator and see input at the LVDT sensor.

==== Plan for coming weeks ====
For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]].

Week of 5/22:
 * Reinstall PI, this time with rods and damper ring.
 * Reinstall PI-SF rod, this time with hex cable clamp.
 * Prepare for PR2 bellows removal on 5/15 (move table with tools).
 * Cable/test PI horizontal LVDTs and steppers.
 * Install/cable/test geophones.
 

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san):

  • We cleared space for the PR2 team to remove a bellows from their tank.
  • We installed safety bars on the pillars near the assembly frame at about waist height for someone on the tall ladder. We reinforced the clamps with cable ties.
  • We bridged a gap in the second floor on the -X side of the SF2 tank with spare floor panels.
  • We removed the PI from the assembly frame.
  • We encountered a problem with the PI-SF rod jamming in the SF. We finally got it out by clamping a pair of vice grips to the rod and hammering. We found that the receptacle part was the right size (7.0 mm) but had been deformed around the edge. Hirata-san used a knife and sandpaper to lean up the edge and then ultrasonically cleaned it.
  • We removed the LLB blade units from the PI, removed the blades from the clamps and sent the blades away for more rework to fix the length problem. Fortunately the tab section at the tip is fairly long, so we can just add a second hole further from the end.
  • We tested the SR fishing rod again, but it would only go up, not down. We found that reseting the driver fixed it, but we also moved the driver boxes into the cleanbooth to reduce the length of the motor cables. (Instead, we had to run some long DC and LAN cables.)
  • We adjusted the limit nut on the SF fishing rod to increase the range.
  • We debugged an issue with the SF keystone sitting lower than previously and found we had accidentally left two eyebolts on top of the BF. We retrimmed the BF/... section to reset the keystone to nominal (65.5 mm) with the fishing rod at mid-range.
  • We removed one segment of the Cu ring on the SF cap and reconfigured the other two to be symmetrical.
  • Fabian designed a layout for the SF damper ring magnets that would work with the modified Cu ring, and placed the magnets with the template. The poles of the magnets were not on the expected faces so we had to stand the magnets up, with the 12x12 faces sideways and the 10x12 mm pole faces up/down. We will need to raise the magnet ring by 2 mm to allow for the extra height.
  • Hirata-san made a cable for the PI v vertical LVDT. We identified the coils by their resistances which were similar to BF/SF: Primary 193Ω, Secondary 75Ω, Actuation 112Ω.
  • We added the remaining cable clamps to the PI (some places had not been accessible with the PI on the frame).
  • We placed the geophones but discovered we didn't have some mounting brackets called out in the 3D CAD.
  • Enzo made a PI yaw/vertical stepper adapter cable and a trial geophone descrambler cable (one of three).
  • We found that part of the problem with the SF LVDT was that the actuation had not been enabled for SF or F0 in the real-time model. We fixed the model and are now able to drive the LVDT actuator and see input at the LVDT sensor.

Plan for coming weeks

For more detail, see KAGRA/Subgroups/VIS/TypeB/ToDo.

Week of 5/22:

  • Reinstall PI, this time with rods and damper ring.
  • Reinstall PI-SF rod, this time with hex cable clamp.
  • Prepare for PR2 bellows removal on 5/15 (move table with tools).
  • Cable/test PI horizontal LVDTs and steppers.
  • Install/cable/test geophones.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)