 * Activity report for weeks of 12/26 and 1/2 === Type B (Mark) ===
==== Past week report ====
At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun):
 * We moved or covered stuff in the BS cleanbooth to prepare for the SR2 crane slot cutting and BS-> SR2 assembly frame move.
 * We put the service port covers back on at the BF level of the BS tank.
 * We used the PI jacks to center the bottom of the security structure around the RM.
 * We debugged a mechanical issue where the #2 IP LVDT had too narrow a gap between the moving and fixed parts, so that there was interference with only a very small clockwise yaw of the IP. We fixed it by moving the bottom baseplate (taking advantage of the fact that it was held by screws in oversize holes for this purpose).
 * We used the IP FRs to center the IP.
 * We set the gains on the IP LVDT driver.
 
Line 7: Line 16:
  * Hirata-san:
   * Modified parts list and screw list for payload.
   * Sent lists to i-ject and asked for preliminary quotes.
   * Made drawings for some jigs (PR hold-down jig) and some parts for payload (PR/SR wire clamps with disposable jaw pieces - improved version with disposable pieces in both primary and secondary clamps).
   * For Type Bp:
    * Searched for PR gluing jigs.
    * Washed and assembled recoilmass base for mirror hanging jigs, and sent them to Kamioka.
    * Washed additional masses for IM and sent them to Kamioka.
   * For others:
    * Washed IMMT plate and sent them to Kamioka.
  * Fabian
   * Designed a pull down system to fix the PR IM to the EQ stop (similar to the SR one).
   * Worked on design of the SR assembly frame. As hoped, the SR version can be almost identical to the BS version.
   * Worked on design of additional trim mass (≈18 kg) for the BS BF.
   * Checked assembly PR/SR drawings. There were a few corrections/changes.
   * Checked fastener list. There were few corrections/changes.
   * Checked component list for the manufacture order. There were few corrections/changes.
   * Helped in searching for the PR gluing jigs.
  * Mark
   * Started design of SR assembly frame (but then passed it to Fabian).
   * Worked on task lists and schedule.
 * Plan for 1/10-13
  * Mark and Fabian at Kamioka:
   * Finish rebalance of IM
   * Reinstall IRM, adjust OSEMs
   * Replace broken Type 3 cable.
   * Do TFs from IRM OSEMs to IRM and IM OSEMs.
   * Cable up and test BF LVDT and fishing rod (time permitting).
   * Disconnect BF and ship back to Mitaka (time permitting).
  * Hirata-san:
   * More SR procurement.
==== Plan for week of 10/2 ====
Kamioka: Mark, Enzo (Tue-Fri), Ohishi-san, Kozu-kun.
 * Finish preparation for SR2 work.
 * Debug electronics, especially actuation.
 * Tune IP, do LVDT/stepper calibration.
 * Remove First Contact, try OL.
Mitaka: Fabian, Hirata-san
 * Design ballast for LBB.
 * Design improved PI yaw adjustment.
 * SR procurement.

==== Plan for week of 10/10 ====
Holiday Mon 10/9, Open Day prep Fri 10/13.<<BR>>
 * TFs, final preparation for alignment in week of 10/16.

==== Plan for week of 10/16 ====
Kamioka: all but Mark
 * Work with alignment team.

==== Vacation Info ====
Mark: 10/16-24

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun):

  • We moved or covered stuff in the BS cleanbooth to prepare for the SR2 crane slot cutting and BS-> SR2 assembly frame move.

  • We put the service port covers back on at the BF level of the BS tank.
  • We used the PI jacks to center the bottom of the security structure around the RM.
  • We debugged a mechanical issue where the #2 IP LVDT had too narrow a gap between the moving and fixed parts, so that there was interference with only a very small clockwise yaw of the IP. We fixed it by moving the bottom baseplate (taking advantage of the fact that it was held by screws in oversize holes for this purpose).
  • We used the IP FRs to center the IP.
  • We set the gains on the IP LVDT driver.

Plan for week of 10/2

Kamioka: Mark, Enzo (Tue-Fri), Ohishi-san, Kozu-kun.

  • Finish preparation for SR2 work.
  • Debug electronics, especially actuation.
  • Tune IP, do LVDT/stepper calibration.
  • Remove First Contact, try OL.

Mitaka: Fabian, Hirata-san

  • Design ballast for LBB.
  • Design improved PI yaw adjustment.
  • SR procurement.

Plan for week of 10/10

Holiday Mon 10/9, Open Day prep Fri 10/13.

  • TFs, final preparation for alignment in week of 10/16.

Plan for week of 10/16

Kamioka: all but Mark

  • Work with alignment team.

Vacation Info