* Activity report for weeks of 12/26 and 1/2 | === Type B (Mark) === ==== Past two weeks report ==== At Kamioka (Mark, Enzo, Kozu-kun): * Supported IA team. * Replaced LPCDs for IM OSEMs with HPCDs for increased pitch/yaw range. * Re-zeroed OL after significant change of beam position during IA. * Re-laid-out OL to improve focus of lens to LEN QPD. * Offloaded the pitch/yaw actuation at the IM OSEMs using the IM pitch/yaw picos. * Enzo worked on design of control loops using the OL. * Kozu-kun worked on diagonalizing the OL. |
Line 7: | Line 16: |
* Hirata-san: * Modified parts list and screw list for payload. * Sent lists to i-ject and asked for preliminary quotes. * Made drawings for some jigs (PR hold-down jig) and some parts for payload (PR/SR wire clamps with disposable jaw pieces - improved version with disposable pieces in both primary and secondary clamps). * For Type Bp: * Searched for PR gluing jigs. * Washed and assembled recoilmass base for mirror hanging jigs, and sent them to Kamioka. * Washed additional masses for IM and sent them to Kamioka. * For others: * Washed IMMT plate and sent them to Kamioka. * Fabian * Designed a pull down system to fix the PR IM to the EQ stop (similar to the SR one). * Worked on design of the SR assembly frame. As hoped, the SR version can be almost identical to the BS version. * Worked on design of additional trim mass (≈18 kg) for the BS BF. * Checked assembly PR/SR drawings. There were a few corrections/changes. * Checked fastener list. There were few corrections/changes. * Checked component list for the manufacture order. There were few corrections/changes. * Helped in searching for the PR gluing jigs. * Mark * Started design of SR assembly frame (but then passed it to Fabian). * Worked on task lists and schedule. * Plan for 1/10-13 * Mark and Fabian at Kamioka: * Finish rebalance of IM * Reinstall IRM, adjust OSEMs * Replace broken Type 3 cable. * Do TFs from IRM OSEMs to IRM and IM OSEMs. * Cable up and test BF LVDT and fishing rod (time permitting). * Disconnect BF and ship back to Mitaka (time permitting). * Hirata-san: * More SR procurement. |
Mitaka (Fabian, Hirata-san): * Hirata-san published his inventory of SR parts on Dropbox. ==== Plan for week of 11/13 ==== Kamioka: Mark * Attend commissioning workshop at U Toyama. * Be person-on-site for BF work. * Set up for mirror gluing. Mitaka: Fabian and Hirata-san * SR procurement. * New PI GAS FR design. * BS LBB ballast mass design. * SR cable lamp design. Mitaka: Enzo and Kozu-kun (Wed, Thu) * Servos * TFs of BF * Documentation |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past two weeks report
At Kamioka (Mark, Enzo, Kozu-kun):
- Supported IA team.
- Replaced LPCDs for IM OSEMs with HPCDs for increased pitch/yaw range.
- Re-zeroed OL after significant change of beam position during IA.
- Re-laid-out OL to improve focus of lens to LEN QPD.
- Offloaded the pitch/yaw actuation at the IM OSEMs using the IM pitch/yaw picos.
- Enzo worked on design of control loops using the OL.
- Kozu-kun worked on diagonalizing the OL.
Mitaka (Fabian, Hirata-san):
- Hirata-san published his inventory of SR parts on Dropbox.
Plan for week of 11/13
Kamioka: Mark
- Attend commissioning workshop at U Toyama.
- Be person-on-site for BF work.
- Set up for mirror gluing.
Mitaka: Fabian and Hirata-san
- SR procurement.
- New PI GAS FR design.
- BS LBB ballast mass design.
- SR cable lamp design.
Mitaka: Enzo and Kozu-kun (Wed, Thu)
- Servos
- TFs of BF
- Documentation