* Activity report for weeks of 12/26 and 1/2 | === Type B (Mark) === ==== Past week report ==== |
Line 7: | Line 8: |
* Hirata-san: * Modified parts list and screw list for payload. * Sent lists to i-ject and asked for preliminary quotes. * Made drawings for some jigs (PR hold-down jig) and some parts for payload (PR/SR wire clamps with disposable jaw pieces - improved version with disposable pieces in both primary and secondary clamps). * For Type Bp: * Searched for PR gluing jigs. * Washed and assembled recoilmass base for mirror hanging jigs, and sent them to Kamioka. * Washed additional masses for IM and sent them to Kamioka. * For others: * Washed IMMT plate and sent them to Kamioka. * Fabian * Designed a pull down system to fix the PR IM to the EQ stop (similar to the SR one). * Worked on design of the SR assembly frame. As hoped, the SR version can be almost identical to the BS version. * Worked on design of additional trim mass (≈18 kg) for the BS BF. * Checked assembly PR/SR drawings. There were a few corrections/changes. * Checked fastener list. There were few corrections/changes. * Checked component list for the manufacture order. There were few corrections/changes. * Helped in searching for the PR gluing jigs. * Mark * Started design of SR assembly frame (but then passed it to Fabian). * Worked on task lists and schedule. * Plan for 1/10-13 * Mark and Fabian at Kamioka: * Finish rebalance of IM * Reinstall IRM, adjust OSEMs * Replace broken Type 3 cable. * Do TFs from IRM OSEMs to IRM and IM OSEMs. * Cable up and test BF LVDT and fishing rod (time permitting). * Disconnect BF and ship back to Mitaka (time permitting). * Hirata-san: * More SR procurement. |
* We brought the SR2 optic into the tunnel and moved it into the good mirror box. The spare mirror was moved into the not-so-good mirror box. * Enzo assembled the SR2 rack and laid all the long cables from the rack into the cleanbooth. (Hayakawa-san can now proceed with the rebuilding of the changing cleanbooth.) * Mark and Shoda-san took data for calibrating and diagonalizing the OL. (Due to the odd angle of the first steering mirror, the beam pattern is rotated by 62° at the QPD.) * Enzo found nearly all in-vacuum cables. * Enzo and Shoda-san got several more loops closed on the BS. * Mark found three geophone pods and two feedthrough adapters for SR2 (now have 3 FAs but need 4). * Mark took out S-numbers for anonymous boxes in the SR2 and put yellow stickers supplied by Tomura-san on them. * Hirata-san worked on SR procurement. * Hirata-san worked with Mirapro to get the SRM LBB installed in the tank. ==== Plan for week of 12/4 ==== * Mark at Kamioka. * Fabian at f2f satellite meeting Mon, then Kamioka. * Enzo at f2f then Mitaka. * Hirata-san at Kamioka Mon-Thu, Mitaka Fri. * Kozu-kun Thu only. * Mirror gluing. * IM assembly and pico test. ==== Plan for week of 12/11 * Mark, Fabian, Enzo, Hirata-san, Shoda-san at Kamioka. * Kozu-kun Mon-Thu only. * Assembly frame alignment and optical table centering. * Move trolley system from SR3. * OL setup. ==== Plan for week of 12/18 ==== * Shoda-san vacation * Mark, Fabian, Enzo, Kozu-kun at Kamioka Mon-Wed. ==== Vacation Info ==== * Mark 12/22-1/3 * Enzo TBD, probably 12/22-1/3 * Fabian 12/22-1/5 * Hirata-san 12/21-22 (conference) * Shoda-san 12/18-21 |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past week report
- We brought the SR2 optic into the tunnel and moved it into the good mirror box. The spare mirror was moved into the not-so-good mirror box.
- Enzo assembled the SR2 rack and laid all the long cables from the rack into the cleanbooth. (Hayakawa-san can now proceed with the rebuilding of the changing cleanbooth.)
- Mark and Shoda-san took data for calibrating and diagonalizing the OL. (Due to the odd angle of the first steering mirror, the beam pattern is rotated by 62° at the QPD.)
- Enzo found nearly all in-vacuum cables.
- Enzo and Shoda-san got several more loops closed on the BS.
- Mark found three geophone pods and two feedthrough adapters for SR2 (now have 3 FAs but need 4).
- Mark took out S-numbers for anonymous boxes in the SR2 and put yellow stickers supplied by Tomura-san on them.
- Hirata-san worked on SR procurement.
- Hirata-san worked with Mirapro to get the SRM LBB installed in the tank.
Plan for week of 12/4
- Mark at Kamioka.
- Fabian at f2f satellite meeting Mon, then Kamioka.
- Enzo at f2f then Mitaka.
- Hirata-san at Kamioka Mon-Thu, Mitaka Fri.
- Kozu-kun Thu only.
- Mirror gluing.
- IM assembly and pico test.
==== Plan for week of 12/11
- Mark, Fabian, Enzo, Hirata-san, Shoda-san at Kamioka.
- Kozu-kun Mon-Thu only.
- Assembly frame alignment and optical table centering.
- Move trolley system from SR3.
- OL setup.
Plan for week of 12/18
- Shoda-san vacation
- Mark, Fabian, Enzo, Kozu-kun at Kamioka Mon-Wed.
Vacation Info
- Mark 12/22-1/3
- Enzo TBD, probably 12/22-1/3
- Fabian 12/22-1/5
- Hirata-san 12/21-22 (conference)
- Shoda-san 12/18-21