 * Hirata-san:
  * Updated the 3D assembly model for BS (among other issues, it turned out that parts were not correctly mated near where the suspension sits on the hydraulic jacks in the tank).
  * Liaised with IJECT.
  * Made an inventory for Type B (BS and SR).
  * Packed and shipped second winch to Kamioka.
  * Packed some jigs for adjusting BF blades.
  * Attended NINS information security seminar.
  * Attended the public hearing for the Opt-IR Research Division Chief Election.
 * Mark and Fabian at Kamioka (plus Enzo for 2 days):
  * Finished rebalance of IM
  * Reinstalled IRM, adjusted OSEMs
  * Replaced broken Type 3 cable on IM-H1 OSEM.
  * Fixed issues with k1visbs real-time model.
  * Started TFs from IRM OSEMs to IRM and IM OSEMs.
 * Mark, Fabian and Enzo
  *
=== Type B (Mark) ===
==== Report for week of 3/26 ====

BFs:

 * BF No. 1:
  * Fujii-san finished tuning. Optimal load: 52.15[kg]. Resonance frequency: 0.36[Hz]. Optimal height: 64.7[mm].
  * We wired the LVDT, Picomotor and Steppermotor.
  * We measured the keystone tilt at 4 different points and it was at 65.5, 65.5, 65.5 and 65.5.
    So with the differences of 0.1 mm we think we can tolarate this differences.
  * We added cable clamps to the base.

 * BF No.7:
  * Fujii-san replaced the blades corresponding to the BS and for the SR type blades.
  * The yoke position was corrected.
  * The fishing rod was assembled.
  * Compression tuning is ongoing.

SFs:

 * Hirata-san and Tanioka-san set up the frame to check the SFs.

 * SF (B2-5):
  * Hirata-san, Fujii-san and Tanioka-san checked the optimal load with and without cap. The optimal load changes about 250[g].
  * We measured the keystone tilt at different points, and the diferences are within 0.1[mm]

 * SF (B2-6):
  * Hirata-san, Fujii-san and Tanioka-san checked the optimal load with and without cap (On going?).
  * We measured the keystone tilt at different points, and the diferences are within 0.3[mm]

SR3/SRM:

 * Kozu-kun and Enzo finished the SR3 in-air cabling.

 * Enzo prepared the SR3 and SRM rack in parallel (On going).

BS:

 * Kozu-kun and Enzo helped Enomoto-san troubleshooting the BS Oplev issue (On going).


Others:

 * We finished tuning of BF No. 1.
  * We wired the LVDT, Picomotor and StepperMotor of BF No. 1.
  

 * We finished tuning of BF No. 7.
  * We wired the LVDT, Picomotor and StepperMotor of BF No. 7.



 * SF check (Hirata-san++).
  * We checked the load capacity with and without the cap.
  * We checked fit of caps. For the SF No.
  * Add cable clamps to bases.
  * Add cable clamps and Cu segments to caps (only if they fit well).
  * Cable LVDTs and steppers.

 * We finished the SR3 in-air cabling.

==== Plan for week of 4/2 ====
 * Mark at Mitaka Mon, Kamioka from Tue.
 * Shoda-san at Mitaka
 * Others at Kamioka
 * --
 * Glue SR3 (if available)
 * Build 2xIM, 2xIRM (if parts available - due 3/30)

==== Plan for week of 4/9 ====
 * Shoda-san at Mitaka
 * Others at Kamioka
 * --
 * Finish IMs and IRMs
 * Build 1xRM

==== Plan for week of 4/16 ====
 * Start SR3 Hang?

==== Plan for week of 4/23 ====
 * F0 blade prototype test

==== Plan for week of 4/30 ====
  * Golden Week!

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/March2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/April2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]]

==== Vacation Info ====
 * Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
 * Fabian vacation, 3/26-4/27 (then gone).

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 3/26

BFs:

  • BF No. 1:
    • Fujii-san finished tuning. Optimal load: 52.15[kg]. Resonance frequency: 0.36[Hz]. Optimal height: 64.7[mm].
    • We wired the LVDT, Picomotor and Steppermotor.
    • We measured the keystone tilt at 4 different points and it was at 65.5, 65.5, 65.5 and 65.5.
      • So with the differences of 0.1 mm we think we can tolarate this differences.
    • We added cable clamps to the base.
  • BF No.7:
    • Fujii-san replaced the blades corresponding to the BS and for the SR type blades.
    • The yoke position was corrected.
    • The fishing rod was assembled.
    • Compression tuning is ongoing.

SFs:

  • Hirata-san and Tanioka-san set up the frame to check the SFs.
  • SF (B2-5):
    • Hirata-san, Fujii-san and Tanioka-san checked the optimal load with and without cap. The optimal load changes about 250[g].
    • We measured the keystone tilt at different points, and the diferences are within 0.1[mm]
  • SF (B2-6):
    • Hirata-san, Fujii-san and Tanioka-san checked the optimal load with and without cap (On going?).
    • We measured the keystone tilt at different points, and the diferences are within 0.3[mm]

SR3/SRM:

  • Kozu-kun and Enzo finished the SR3 in-air cabling.
  • Enzo prepared the SR3 and SRM rack in parallel (On going).

BS:

  • Kozu-kun and Enzo helped Enomoto-san troubleshooting the BS Oplev issue (On going).

Others:

  • We finished tuning of BF No. 1.
  • We finished tuning of BF No. 7.
  • SF check (Hirata-san++).
    • We checked the load capacity with and without the cap.
    • We checked fit of caps. For the SF No.
    • Add cable clamps to bases.
    • Add cable clamps and Cu segments to caps (only if they fit well).
    • Cable LVDTs and steppers.
  • We finished the SR3 in-air cabling.

Plan for week of 4/2

  • Mark at Mitaka Mon, Kamioka from Tue.
  • Shoda-san at Mitaka
  • Others at Kamioka
  • --
  • Glue SR3 (if available)
  • Build 2xIM, 2xIRM (if parts available - due 3/30)

Plan for week of 4/9

  • Shoda-san at Mitaka
  • Others at Kamioka
  • --
  • Finish IMs and IRMs
  • Build 1xRM

Plan for week of 4/16

  • Start SR3 Hang?

Plan for week of 4/23

  • F0 blade prototype test

Plan for week of 4/30

  • Golden Week!

To-Do Lists, Schedule

Vacation Info

  • Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
  • Fabian vacation, 3/26-4/27 (then gone).