* Hirata-san: * Received many parts from i-ject for BFRM (took pictures and took them into ATC cleanroom). * got quotes for PRM/SRM payload from i-ject. * Checked quotes and asked for some modifications.) * Washed parts (parts for type-A, small hexagons, screws, etc\) * Wiped 9 piano wires and sent to Kamioka for PR. * pdated Fabian's EQstop parts for BS recoilmass and updated EQstop assy drawings. * Fabian * Worked out geometry for blade adjustment. * Designed additional ballast masses for BS BF (and SR). * Mark and Enzo (at Kamioka) * Did two rounds of adjustment of the blades with help from Takahashi-san (one for position, one for frequency) * Surveyed the position of the rod using the vertical mode of the bubble level. * Got apparent improvement as judged at the IRM-IM EQ stops (but still not perfect). * Did one more round of blade adjustments (without Takahashi-san) * Got good agreement with IRM-IM EQ stops, so put BF cap on and raised the whole system to check for balance. * Found balance still fairly bad: about the same on the -X,+Y diagonal and about half on the +X,+Y diagonal (70 and 30 mm worth of motion of a single trim mass respectively; previous a bit over 70 mm each). * From the imbalance torques, calculated the offset of rod as 2.3 mm in the direction 22 degrees to the +X side of -Y. * Calculated the blade adjustments required: {-0.325194, -1.79175, 2.11695} mm * Prepared to apply adjustments (removed cap etc). |
=== Type B (Mark) === ==== Past week report ==== At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun): * We craned out the SF temporarily and retrieved the lost PEEK cable clamp collet from the BF. * We installed the BF. * We routed cables from the BF via the hex cable clamp to the SF level. * We adjusted the BF trim mass for pitch, roll and vertical, and got the IRM hanging symmetrically around the IM. * We adjusted all the IRM OSEMs laterally and in/out. * We calibrated the SF LVDT and tested the SF FR stepper. * We suspended the SF/... section and weighed it but found the old 7-mm maraging rod adapter did not hold it at the center, so we chad to lift it with slings and could not accurately trim it for pitch/roll. * We craned in the PI with the SF damper ring hanging from it. * We suspended the SF successfully from the PI and unlocked the F0 keystone to check the mass budget. We needed about 1.5 kg extra, which is about right. * However we had to leave out the F0-SF hex cable clamp because of a bad thread on the inside of the cap. Hirata-san will make a new cap by enlarging the 7-mm hole in an old cap to 8 mm. ==== Plan for week of 9/4 ==== Mark, Fabian, Enzo (Tue-Fri), Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun (Thu, Fri) * Retrieve PEEK piece from BF. * Crane SF back in. * Suspend BF/IRM/IM/RM/BS. * Test SF FR. * Calibrate SF LVDT. * Install SF cap; route cables. * Lift and weigh SF/BF/IRM/IM/RM/BS. * Adjust SF ballast. ==== Plan for week of 9/13 ==== Mark (except Wed), Fabian (except ASJ), Enzo, Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun * Prepare magnet ring. * Bring in PI. * Route cables. * Suspend SF/..., adjust tilt of SF and total mass. * Adjust damper gap. ==== Vacation Info ==== Mark: 10/16-24 |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past week report
At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):
- We craned out the SF temporarily and retrieved the lost PEEK cable clamp collet from the BF.
- We installed the BF.
- We routed cables from the BF via the hex cable clamp to the SF level.
- We adjusted the BF trim mass for pitch, roll and vertical, and got the IRM hanging symmetrically around the IM.
- We adjusted all the IRM OSEMs laterally and in/out.
- We calibrated the SF LVDT and tested the SF FR stepper.
- We suspended the SF/... section and weighed it but found the old 7-mm maraging rod adapter did not hold it at the center, so we chad to lift it with slings and could not accurately trim it for pitch/roll.
- We craned in the PI with the SF damper ring hanging from it.
- We suspended the SF successfully from the PI and unlocked the F0 keystone to check the mass budget. We needed about 1.5 kg extra, which is about right.
- However we had to leave out the F0-SF hex cable clamp because of a bad thread on the inside of the cap. Hirata-san will make a new cap by enlarging the 7-mm hole in an old cap to 8 mm.
Plan for week of 9/4
Mark, Fabian, Enzo (Tue-Fri), Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun (Thu, Fri)
- Retrieve PEEK piece from BF.
- Crane SF back in.
- Suspend BF/IRM/IM/RM/BS.
- Test SF FR.
- Calibrate SF LVDT.
- Install SF cap; route cables.
- Lift and weigh SF/BF/IRM/IM/RM/BS.
- Adjust SF ballast.
Plan for week of 9/13
Mark (except Wed), Fabian (except ASJ), Enzo, Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun
- Prepare magnet ring.
- Bring in PI.
- Route cables.
- Suspend SF/..., adjust tilt of SF and total mass.
- Adjust damper gap.
Vacation Info