Differences between revisions 120 and 257 (spanning 137 versions)
Revision 120 as of 2017-01-27 13:28:23
Size: 1613
Editor: MarkBarton
Comment:
Revision 257 as of 2018-03-23 12:10:14
Size: 1923
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Hirata-san:
  * Received many parts from i-ject for BFRM (took pictures and took them into ATC cleanroom).
  * got quotes for PRM/SRM payload from i-ject.
  * Checked quotes and asked for some modifications.)
  * Washed parts (parts for type-A, small hexagons, screws, etc\)
  * Wiped 9 piano wires and sent to Kamioka for PR.
  * pdated Fabian's EQstop parts for BS recoilmass and updated EQstop assy drawings.
 * Fabian
  * Worked out geometry for blade adjustment.
  * Designed additional ballast masses for BS BF (and SR).
 * Mark and Enzo (at Kamioka)
  * Did two rounds of adjustment of the blades with help from Takahashi-san (one for position, one for frequency)
  * Surveyed the position of the rod using the vertical mode of the bubble level.
  * Got apparent improvement as judged at the IRM-IM EQ stops (but still not perfect).
  * Did one more round of blade adjustments (without Takahashi-san)
  * Got good agreement with IRM-IM EQ stops, so put BF cap on and raised the whole system to check for balance.
  * Found balance still fairly bad: about the same on the -X,+Y diagonal and about half on the +X,+Y diagonal (70 and 30 mm worth of motion of a single trim mass respectively; previous a bit over 70 mm each).
  * From the imbalance torques, calculated the offset of rod as 2.3 mm in the direction 22 degrees to the +X side of -Y.
  * Calculated the blade adjustments required: {-0.325194, -1.79175, 2.11695} mm
  * Prepared to apply adjustments (removed cap etc).
=== Type B (Mark) ===
==== Report for week of 3/19 ====
 * Fujii-kun successfully assembled and tested a geophone pod (klogs 4492, 4508).
 * Hirata-san set up the dummy BS to soak off the sapphire prisms (ongoing).
 * Shoda-san, Hirata-san and Enzo finished the assembly of 12 OSEMs. We still need to measure the maximum output (ongoing).
 * We will send the OSEMs to Kamioka today.
 * Enzo made 2 in-air picomotor cable.


==== Plan for week of 3/26 ====
 * Tanioka-kun joins.
 * Mark vacation.
 * Shoda-san at Mitaka
 * Others at Kamioka
 * --
 * Lay SR3 in-air cabling (Enzo++).
 * Finish tuning of BFs (Hirata-san++).
 * SF check (Hirata-san++).
  * Check load capacity.
  * Check fit of caps.
  * Add cable clamps to bases.
  * Add cable clamps and Cu segments to caps (only if they fit well).
  * Cable LVDTs and steppers.

==== Plan for week of 4/2 ====
 * Mark at Mitaka Mon, Kamioka from Tue.
 * Shoda-san at Mitaka
 * Others at Kamioka
 * --
 * Glue SR3 (if available)
 * Build 2xIM, 2xIRM (if parts available - due 3/30)

==== Plan for week of 4/9 ====
 * Shoda-san at Mitaka
 * Others at Kamioka
 * --
 * Finish IMs and IRMs
 * Build 1xRM

==== Plan for week of 4/16 ====
 * Start SR3 Hang?

==== Plan for week of 4/23 ====
 * F0 blade prototype test

==== Plan for week of 4/30 ====
  * Golden Week!

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/March2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/April2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]]

==== Vacation Info ====
 * Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
 * Fabian vacation, 3/26-4/27 (then gone).

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 3/19

  • Fujii-kun successfully assembled and tested a geophone pod (klogs 4492, 4508).
  • Hirata-san set up the dummy BS to soak off the sapphire prisms (ongoing).
  • Shoda-san, Hirata-san and Enzo finished the assembly of 12 OSEMs. We still need to measure the maximum output (ongoing).
  • We will send the OSEMs to Kamioka today.
  • Enzo made 2 in-air picomotor cable.

Plan for week of 3/26

  • Tanioka-kun joins.
  • Mark vacation.
  • Shoda-san at Mitaka
  • Others at Kamioka
  • --
  • Lay SR3 in-air cabling (Enzo++).
  • Finish tuning of BFs (Hirata-san++).
  • SF check (Hirata-san++).
    • Check load capacity.
    • Check fit of caps.
    • Add cable clamps to bases.
    • Add cable clamps and Cu segments to caps (only if they fit well).
    • Cable LVDTs and steppers.

Plan for week of 4/2

  • Mark at Mitaka Mon, Kamioka from Tue.
  • Shoda-san at Mitaka
  • Others at Kamioka
  • --
  • Glue SR3 (if available)
  • Build 2xIM, 2xIRM (if parts available - due 3/30)

Plan for week of 4/9

  • Shoda-san at Mitaka
  • Others at Kamioka
  • --
  • Finish IMs and IRMs
  • Build 1xRM

Plan for week of 4/16

  • Start SR3 Hang?

Plan for week of 4/23

  • F0 blade prototype test

Plan for week of 4/30

  • Golden Week!

To-Do Lists, Schedule

Vacation Info

  • Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
  • Fabian vacation, 3/26-4/27 (then gone).

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)