 * Hirata-san:
  * Made BS disposable wire clamp 3Dmodel and drawings.
  * Made ballast mass drawings for BS Bottomfilter and Standardfilter.
  * Made parts list and screw list for disposable wire clamp and ballast mass.
  * Sent drawings and lists to i-ject for quotation.
  * Start to make drawings for SR big parts (optical bench,damper rings,sus wires,cable clamps) - ongoing.
 * Mark, Fabian and Enzo (at Kamioka):
  * Realized that some of the imbalance in the BF was from the fishing rod and calculated a new set of blade offsets to center the rod but leave the torque from the FR to be cancelled by the trim mass for now.
  * Applied the blade offsets and checked that the BF hung as expected.
  * Found that the yoke was rubbing again and corrected it by putting it at an angle matching the keystone.
  * Found that the cables were adding too much stiffness and friction and rerouted them.
  * Found that the GAS was unstable and reduced the compression symmetrically to get 0.37 Hz.
  * Rebalanced the IM to set the right pitch, yaw and height.
  * Tested the IM picos. Unfortunately the pitch pico stuck near or at one end of its range and we will need to take the end plate off the IM to find out what is wrong.
=== Type B (Mark) ===
==== Report for week of 1/29 ====
 * We moved the top filter intended for SR2 (#1) into the SR3 cleanbooth.
 * Unfortunately we noticed one of the blades had many small X-shaped stress fractures on the top surface (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=4058|4058]]).
 * We moved the top filter entered for SR3 (#3) into the SRM cleanbooth and inspected the blades. Two had one smallish stress fracture each and one had a huge fracture and looks close to failing (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=4061|4061]]).
 * We referred the BS OL.
 * We removed the BS tank lid and inspected the BS top filter blades. They seemed fine (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=4073|4073]]).
 * Hirata-san received and washed some ferromagnetic disks for IM flags and other small parts.
 * Hirata-san moved the BF with the tilted keystone (#1) out of the cleanbooth in preparation for rebuilding.
 * Hirata-san placed the second order for payload parts, and an order for remachining of nuts for cable clamps on rods.
 * Fabian measured the gain of the ADC system (homework from the Commissioning Workshop).
 
==== Plan for week of 2/5 ====
Enzo on vacation; all others at Kamioka.
 * Make in-air pico adapter cables.
 * Calibrate LVDT.
 * Test IM picos and BF yaw pico.
 * Test FR.
 * Install ballast mass in BF.
 * Build IRM around IM.
 * Cable/test/adjust IM OSEMs.
 * Time permitting, do TFs from IM OSEMs to themselves and to optical sensor.

==== Plan for week of 2/13 ====
 * No work Monday (建国記念の日の振替休日)<<BR>>
 * Enzo on vacation
 * Hirata-san at Mitaka Tue, Wed (to receive and wash parts).
 * All others at Kamioka.
 * -
 * Lift BF/IM/IRM/RM/TM and check total mass and balance.
 * Test BF picos.
 *

==== Vacation Info ====
 * Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30)
 * Kozu-kun 1/29-2/2

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 1/29

  • We moved the top filter intended for SR2 (#1) into the SR3 cleanbooth.
  • Unfortunately we noticed one of the blades had many small X-shaped stress fractures on the top surface (klog 4058).

  • We moved the top filter entered for SR3 (#3) into the SRM cleanbooth and inspected the blades. Two had one smallish stress fracture each and one had a huge fracture and looks close to failing (klog 4061).

  • We referred the BS OL.
  • We removed the BS tank lid and inspected the BS top filter blades. They seemed fine (klog 4073).

  • Hirata-san received and washed some ferromagnetic disks for IM flags and other small parts.
  • Hirata-san moved the BF with the tilted keystone (#1) out of the cleanbooth in preparation for rebuilding.
  • Hirata-san placed the second order for payload parts, and an order for remachining of nuts for cable clamps on rods.
  • Fabian measured the gain of the ADC system (homework from the Commissioning Workshop).

Plan for week of 2/5

Enzo on vacation; all others at Kamioka.

  • Make in-air pico adapter cables.
  • Calibrate LVDT.
  • Test IM picos and BF yaw pico.
  • Test FR.
  • Install ballast mass in BF.
  • Build IRM around IM.
  • Cable/test/adjust IM OSEMs.
  • Time permitting, do TFs from IM OSEMs to themselves and to optical sensor.

Plan for week of 2/13

  • No work Monday (建国記念の日の振替休日)

  • Enzo on vacation
  • Hirata-san at Mitaka Tue, Wed (to receive and wash parts).
  • All others at Kamioka.
  • -
  • Lift BF/IM/IRM/RM/TM and check total mass and balance.
  • Test BF picos.

Vacation Info

  • Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30)
  • Kozu-kun 1/29-2/2