 * Hirata-san:
  * Worked on the PR optic removal jig.
  * Worked on getting modified quotes for PR/SR/BS parts.
 * Enzo-san
  * Worked on getting his drivers license.
  * Worked on getting familiar with the Type B circuit diagram.
 * Mark, Fabian (at Kamioka):
  * Tried different strategies for getting the IRM-IM EQ stops and IRM OSEMs to line up simultaneously.
  * Realized that the main problem was that the pitch of the BS had changed relative to the IM (presumably due to slight slippage of the wires) so the IM had to be pitched up by 16 mrad to get the BS pitched slightly down (4.7 mrad).
  * Took the sides off the IRM to get access to the clamps and tightened them to prevent further slips.
  * Rebalanced the IM to be level in pitch (and roll).
  * Reassembled the IRM and aligned the IRM-IM EQ stops - this time it was easy.
  * Adjusted the IRM and RM OSEMs to mid-range.
  * Got Kokeyama's new real-time model working and started TFs.
At Kamioka (Enzo):
 * Enzo (with help from Miyo-kun) fixed the broken actuation coil on PI LVDT #0.
 * Enzo worked on the final cabling plan for BS and SRx.
 * Enzo replaced the LVDT driver again to have one with no dead channels (and free up the partly non-working cards for servicing).

At Mitaka and Kashiwa (Mark, Hirata-san, Fabian, Enzo):
 * We glued magnets into their holders.
 * We did a walk-through of the gluing procedure at Mitaka and discovered that the secondary prisms were missing.
 * We took the mirror box and gluing tools to Kashiwa to do as much of the gluing as possible.
 * Hirose-san applied First Contact to the BS and he and Kieran moved it into the mirror box.
 * We practiced putting sapphire prisms on the BS but didn't apply glue.
 * We tried the magnet gluing jigs designed by Aso-san and found two major issues: the overall length was about 25 mm too long, and there was no adjustment to allow for the wedge.
 * We designed a simple modification to the jigs that hopefully would be trivial for the ATC to do: the jigs will be cut in half and the bottom section will be mounted with adhesive on an 11 mm rod that slides in the central hole of the top section. Thus the top half can be screwed into the existing recess, and the bottom half with the magnets and glue can be allowed to drop about 3 mm onto the face of the optic. Hirata-san worked with ATC to get this done and it should be ready today (Friday 7/7).
 * Hirata-san also got ATC to make some jigs to hold the old 5-mm prisms so that they can be ground down to 3 mm to replace the missing ones. Hirata-san will do the grinding himself today (Friday 7/7/).
 * We decided to continue the gluing work at Kamioka, so we brought the BS back to Mitaka and will ship it on to Kamioka next Tuesday.
 * Hirata-san did a version of the 3D CAD with the as-built BS Test Hang configuration.

==== Plan for weeks of 7/10, 7/17 ====
Mark, Enzo mostly at Kamioka.
 * More TFs.
 * Receive BS at Kamioka, do gluing if possible.
 * Learn how Miyo-kun's pico driver software works and make fixes/improvements.
 * Test picos and steppers more fully.
 * Finish tidying rack and labeling cables.
 
Line 22: Line 33:
==== Plan for coming weeks ====
 * Mark and Enzo come to Kamioka and work on rack and cabling.
 * Fabian works on design, including SR assembly frame.
 * Hirata-san works on procurement.
Fabian, Hirata-san at Mitaka.
 * Do new 3D CAD (Hirata-san):
  * SR2 on BS assembly frame. (Adjust jack positions if possible, or leave for Fabian/Mark to do.)
  * Final BS build, SS/PI/SF as for Test Hang but with BF/IRM/IM/BS/RM down rotated back to original direction.
   * On-assembly-frame version. (Adjust jack positions if possible, or leave for Mark to do.)
   * In-tank version.
 * Solve arc weight versus magic wand problem.
 * Do mass budget for LBB - design ballast masses (Fabian)
 * Run TFs, make improvements to real-time model (Mark, Enzo).
 * Design SR assembly frame.
 * Inventory for SR.
==== Plan for week of 7/10 ====
Mark and Enzo at Kamioka:
Fabian and Hirata-san at Mitaka.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Enzo):

  • Enzo (with help from Miyo-kun) fixed the broken actuation coil on PI LVDT #0.
  • Enzo worked on the final cabling plan for BS and SRx.
  • Enzo replaced the LVDT driver again to have one with no dead channels (and free up the partly non-working cards for servicing).

At Mitaka and Kashiwa (Mark, Hirata-san, Fabian, Enzo):

  • We glued magnets into their holders.
  • We did a walk-through of the gluing procedure at Mitaka and discovered that the secondary prisms were missing.
  • We took the mirror box and gluing tools to Kashiwa to do as much of the gluing as possible.
  • Hirose-san applied First Contact to the BS and he and Kieran moved it into the mirror box.
  • We practiced putting sapphire prisms on the BS but didn't apply glue.
  • We tried the magnet gluing jigs designed by Aso-san and found two major issues: the overall length was about 25 mm too long, and there was no adjustment to allow for the wedge.
  • We designed a simple modification to the jigs that hopefully would be trivial for the ATC to do: the jigs will be cut in half and the bottom section will be mounted with adhesive on an 11 mm rod that slides in the central hole of the top section. Thus the top half can be screwed into the existing recess, and the bottom half with the magnets and glue can be allowed to drop about 3 mm onto the face of the optic. Hirata-san worked with ATC to get this done and it should be ready today (Friday 7/7).
  • Hirata-san also got ATC to make some jigs to hold the old 5-mm prisms so that they can be ground down to 3 mm to replace the missing ones. Hirata-san will do the grinding himself today (Friday 7/7/).
  • We decided to continue the gluing work at Kamioka, so we brought the BS back to Mitaka and will ship it on to Kamioka next Tuesday.
  • Hirata-san did a version of the 3D CAD with the as-built BS Test Hang configuration.

Plan for weeks of 7/10, 7/17

Mark, Enzo mostly at Kamioka.

  • More TFs.
  • Receive BS at Kamioka, do gluing if possible.
  • Learn how Miyo-kun's pico driver software works and make fixes/improvements.
  • Test picos and steppers more fully.
  • Finish tidying rack and labeling cables.

Fabian, Hirata-san at Mitaka.

  • Do new 3D CAD (Hirata-san):
    • SR2 on BS assembly frame. (Adjust jack positions if possible, or leave for Fabian/Mark to do.)
    • Final BS build, SS/PI/SF as for Test Hang but with BF/IRM/IM/BS/RM down rotated back to original direction.
      • On-assembly-frame version. (Adjust jack positions if possible, or leave for Mark to do.)
      • In-tank version.
  • Solve arc weight versus magic wand problem.
  • Do mass budget for LBB - design ballast masses (Fabian)
  • Run TFs, make improvements to real-time model (Mark, Enzo).
  • Design SR assembly frame.
  • Inventory for SR.

Plan for week of 7/10

Mark and Enzo at Kamioka: Fabian and Hirata-san at Mitaka.