 * Hirata-san:
  * Worked on the PR optic removal jig.
  * Worked on getting modified quotes for PR/SR/BS parts.
 * Enzo-san
  * Worked on getting his drivers license.
  * Worked on getting familiar with the Type B circuit diagram.
 * Mark, Fabian (at Kamioka):
  * Tried different strategies for getting the IRM-IM EQ stops and IRM OSEMs to line up simultaneously.
  * Realized that the main problem was that the pitch of the BS had changed relative to the IM (presumably due to slight slippage of the wires) so the IM had to be pitched up by 16 mrad to get the BS pitched slightly down (4.7 mrad).
  * Took the sides off the IRM to get access to the clamps and tightened them to prevent further slips.
  * Rebalanced the IM to be level in pitch (and roll).
  * Reassembled the IRM and aligned the IRM-IM EQ stops - this time it was easy.
  * Adjusted the IRM and RM OSEMs to mid-range.
  * Got Kokeyama's new real-time model working and started TFs.

 * Mark analyzed the QPD data from Friday 12/1 and derived matrices to diagonalize the QPD, and calibrate output in µrad. In the process an error in the IM OSEM diagonalization was discovered: the P and Y gains were low by a factor 2.
 * Mark re-zeroed the QPD after noting the micrometer readings so we can do TFs over the weekend.
 * We prepared for the SR2 gluing:
  * We aligned the SR2 in the box with the wedge on the correct side.
  * We checked that the remachined BS prism holders fit on the PR2 mirror box.
  * We checked that with Tatsumi-san's support ring, the prisms would go on at the right height.
  * We checked the new magnet jigs.
 * We glued ferromagnetic disks in a large number of IM flag tips and flag bases, and in the SR magnet jigs.
 * We also glued SR magnets in the magnet bases.

==== Plan for week of 12/11
 * Mark, Fabian, Enzo, Kozu-kun (Mon-Thu only), Hirata-san, Shoda-san at Kamioka.
 * Mirror gluing.
 * IM assembly and pico test.
 * Assembly frame alignment and optical table centering.
 * Move trolley system from SR3.
 * OL setup.

==== Plan for week of 12/18 ====
 * Shoda-san vacation
 * Mark, Fabian, Enzo, Kozu-kun at Kamioka Mon-Wed.

==== Vacation Info ====
 * Mark 12/22-1/3
 * Enzo, 12/21-12/27 (but ''not'' 12/28)
 * Fabian 12/22-1/5
 * Hirata-san 12/21-22 (conference)
 * Shoda-san 12/18-21
Line 22: Line 37:
==== Plan for coming weeks ====
 * Mark and Enzo come to Kamioka and work on rack and cabling.
 * Fabian works on design, including SR assembly frame.
 * Hirata-san works on procurement.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

  • Mark analyzed the QPD data from Friday 12/1 and derived matrices to diagonalize the QPD, and calibrate output in µrad. In the process an error in the IM OSEM diagonalization was discovered: the P and Y gains were low by a factor 2.
  • Mark re-zeroed the QPD after noting the micrometer readings so we can do TFs over the weekend.
  • We prepared for the SR2 gluing:
    • We aligned the SR2 in the box with the wedge on the correct side.
    • We checked that the remachined BS prism holders fit on the PR2 mirror box.
    • We checked that with Tatsumi-san's support ring, the prisms would go on at the right height.
    • We checked the new magnet jigs.
  • We glued ferromagnetic disks in a large number of IM flag tips and flag bases, and in the SR magnet jigs.
  • We also glued SR magnets in the magnet bases.

==== Plan for week of 12/11

  • Mark, Fabian, Enzo, Kozu-kun (Mon-Thu only), Hirata-san, Shoda-san at Kamioka.
  • Mirror gluing.
  • IM assembly and pico test.
  • Assembly frame alignment and optical table centering.
  • Move trolley system from SR3.
  • OL setup.

Plan for week of 12/18

  • Shoda-san vacation
  • Mark, Fabian, Enzo, Kozu-kun at Kamioka Mon-Wed.

Vacation Info

  • Mark 12/22-1/3
  • Enzo, 12/21-12/27 (but not 12/28)

  • Fabian 12/22-1/5
  • Hirata-san 12/21-22 (conference)
  • Shoda-san 12/18-21