Differences between revisions 127 and 251 (spanning 124 versions)
Revision 127 as of 2017-02-24 13:38:24
Size: 1844
Editor: MarkBarton
Comment:
Revision 251 as of 2018-03-22 01:02:47
Size: 1671
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 6: Line 6:
==== Past week report ====
At Kamioka (Mark, Fabian, Enzo, Hirata-san):
 * We improvised a solution for ballast mass on the BF, using some heavy dog clamps meant for pedestals, washed and wrapped in foil. We we use them for the duration of the BS Test Hang and then swap them out for custom masses.
 * We put back the original BF jacks (replacing the cantilevered jacks that had been borrowed from the SF level to allow access to the BF blade screws).
 * We rearranged the BS rack, closing the gaps between boxes (per request of Miyakawa-san. We also renumbered some boxes, connectors and cables so as to use zero-based numbering (#0, #1, #2,...) throughout.
 * We routed the OSEM cables into the external cable rack (rather than through the PR2 area).
 * We connected up the BF LVDT, and BF fishing rod stepper motor.
 * We installed a signal generator for the LVDT.
 * We connected the super motor driver box to the Internet and attempted to set it up, but with no success so far.
 * We found the final picomotor driver (we have been using the one from TAMA in the clean booth).
 * We found many items that we will need soon, including the copper ring for the SF.
 * We found issues with the digital system (the computer driving the rack had been changed from k1pr2 to k1bs, which causes problems) and worked with DGS to fix them. It now mostly works but the real-time model crashes from time to time.
 
==== Plan for coming weeks ====
Next week:
 * Everyone (Mark, Fabian, Enzo, Hirata-san) at Kamioka, Monday-Thursday.
 * Work on electronics, possibly suspend and weigh BF.
Week after next:
 * Everyone (Mark, Fabian, Enzo, Hirata-san) at Kamioka, Monday-Friday.
 * Add SF and suspend BF.
==== Report for week of 3/19 ====
 * Fujii-kun successfully assembled and tested a geophone pod (klogs 4492, 4508).


==== Plan for week of 3/19 ====
 * Fujii-kun joins.
 * Mark at LVC meeting
 * Fujii-kun at Kamioka (including Wed 3/21)
 * Kozu-kun at Kamioka Mon-Tue.
 * All others at Mitaka
 * --
 * SR2 TFs and control loop development (Shoda-san and Enzo).
 * Assemble four geophone pods (Fujii-kun and Kozu-kun at Kamioka).
 * Make two sets of IM OSEMs (Shoda-san and Enzo)
 * Make last in-air pico adapter cable (Enzo).
 * Make three in-air stepper splitter cables for SR2, SR3 and SRM (Enzo).
 * Set up dummy BS prism removal (Hirata-san).

==== Plan for week of 3/26 ====
 * Tanioka-kun joins.
 * Mark vacation.
 * Shoda-san at Mitaka
 * Others at Kamioka
 * --
 * Lay SR3 in-air cabling (Enzo++).
 * Finish tuning of BFs (Hirata-san++).
 * SF check (Hirata-san++).
  * Check load capacity.
  * Check fit of caps.
  * Add cable clamps to bases.
  * Add cable clamps and Cu segments to caps (only if they fit well).
  * Cable LVDTs and steppers.

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/March2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/April2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]]

==== Vacation Info ====
 * Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
 * Fabian vacation, 3/26-4/27 (then gone).

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 3/19

  • Fujii-kun successfully assembled and tested a geophone pod (klogs 4492, 4508).

Plan for week of 3/19

  • Fujii-kun joins.
  • Mark at LVC meeting
  • Fujii-kun at Kamioka (including Wed 3/21)
  • Kozu-kun at Kamioka Mon-Tue.
  • All others at Mitaka
  • --
  • SR2 TFs and control loop development (Shoda-san and Enzo).
  • Assemble four geophone pods (Fujii-kun and Kozu-kun at Kamioka).
  • Make two sets of IM OSEMs (Shoda-san and Enzo)
  • Make last in-air pico adapter cable (Enzo).
  • Make three in-air stepper splitter cables for SR2, SR3 and SRM (Enzo).
  • Set up dummy BS prism removal (Hirata-san).

Plan for week of 3/26

  • Tanioka-kun joins.
  • Mark vacation.
  • Shoda-san at Mitaka
  • Others at Kamioka
  • --
  • Lay SR3 in-air cabling (Enzo++).
  • Finish tuning of BFs (Hirata-san++).
  • SF check (Hirata-san++).
    • Check load capacity.
    • Check fit of caps.
    • Add cable clamps to bases.
    • Add cable clamps and Cu segments to caps (only if they fit well).
    • Cable LVDTs and steppers.

To-Do Lists, Schedule

Vacation Info

  • Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
  • Fabian vacation, 3/26-4/27 (then gone).

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)