* We set things up again after the floor coating work. * We moved the PI into the second floor of the cleanbooth: * We cleared a path for the forklift (moving the portable cleanroom, worktable, power cables, vacuum pumps and other obstacles). * We got Saito-sensei to move the PI to the +Y side of the cleanbooth. * We washed and cling-wrapped a pallet. * We got Miyoki-san to disconnect the cables and curtain blocking the crane slot (and reconnect them afterwards). * We added some temporary crossbars in the top of the assembly frame and stored the SF cap on them to get it out of the way. * We craned in the pallet and set it up to bridge three floor joists. * We craned in the PI using Saito-san's adapter. * We couldn't find the original screws for the three PI transport plates so we substituted some others - fortunately there was no galling. * We had to connect the adapter to the crane with a sling because the ring for the hook was slightly too small). * We did a lot of cabling work: * We routed all the BF cables over the BF cap, up through the cable clamp on the SF-BF rod and up to the SF. (We had to redo a few because the Type 3 cable was at the flange end instead of the Type 1.) * We connected up the SF LVDT and FR stepper. * We started on rebalancing the BF (which had been perturbed by the weight and tension of all the cables). We got it rather better, but it needs more work. * We made another batch of anti-feedthrough adapters. |
* Realized that the SF/BF/... section doesn't need 6 kg added, it needs 6 kg ''removed'', but none to remove. The 20 kg extra in the BF to match the SF GAS filter makes the whole chain overload the PI GAS filter. * Lifted the SF/BF/... section to check for net weight and balance. Was 307 kg (cf. G&M's measurement of 301 kf in 2012 for the F0). Can be balanced with only 63 g extra. * Went to build up the LBB blade units but discovered that the holes in the base of the blades are two small (are Ø11 mm; should be Ø12 MM). 3D CAD was correct - error was in the 2D drawing. Shipped the blades away for modification. * Tested the SF LVDT actuation and worked on debugging it. Still not working. * Prepared the PI for being lifted, and the top of the assembly frame for receiving it. * Searched for and found the old PI-SF rod. * Did safety improvements after Enzo hit his head on a flange bolt: reversed all the bolts on the ±X sides of the BS and put caution tape on them. * Debugged Kokeyama-san's changes to the real-time model for the DIO, and started on TFs to check the output filter compensation is working. |
Line 28: | Line 21: |
Week of 4/10: * Hirata-san does scissor lift training 4/10. * Perry in Tokyo 4/10. * Debug/fix dead OSEM channel, TM-H4. * Debug BF/SF LVDTs. * Adjust BF pitch/roll. * Do TF from SF LVDT actuation. * Install temporary ballast mass in SF. * Lift SF/BF/... section and check total weight and SF balance. * Continue swap of PI LVDT connectors (female->male) * Start preparing LBB spring units. * Install pico drivers in rack, create MEDM interface (with Miyo-kun), and undo temporary connection of picos to old controller and joystick. Week of 4/17: |
Week of 4/24 (four-day week): |
Line 42: | Line 23: |
* Connect SF/BF... section. * Temporarily remove PI and adjust SF ballast if necessary. |
* Connect SF/BF... section and see if we're indeed overweight and by exactly how much. * Finish debugging SF LVDT actuation. Week of 5/1: * No activity (Golden Week). |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past week report
At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san):
Realized that the SF/BF/... section doesn't need 6 kg added, it needs 6 kg removed, but none to remove. The 20 kg extra in the BF to match the SF GAS filter makes the whole chain overload the PI GAS filter.
Lifted the SF/BF/... section to check for net weight and balance. Was 307 kg (cf. G&M's measurement of 301 kf in 2012 for the F0). Can be balanced with only 63 g extra.
- Went to build up the LBB blade units but discovered that the holes in the base of the blades are two small (are Ø11 mm; should be Ø12 MM). 3D CAD was correct - error was in the 2D drawing. Shipped the blades away for modification.
- Tested the SF LVDT actuation and worked on debugging it. Still not working.
- Prepared the PI for being lifted, and the top of the assembly frame for receiving it.
- Searched for and found the old PI-SF rod.
- Did safety improvements after Enzo hit his head on a flange bolt: reversed all the bolts on the ±X sides of the BS and put caution tape on them.
- Debugged Kokeyama-san's changes to the real-time model for the DIO, and started on TFs to check the output filter compensation is working.
Plan for coming weeks
For more detail, see KAGRA/Subgroups/VIS/TypeB/ToDo.
Week of 4/24 (four-day week):
- Crane in PI.
- Connect SF/BF... section and see if we're indeed overweight and by exactly how much.
- Finish debugging SF LVDT actuation.
Week of 5/1:
- No activity (Golden Week).