==== Past week report ====
At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san):
 * We set things up again after the floor coating work.
 * We moved the PI into the second floor of the cleanbooth:
  * We cleared a path for the forklift (moving the portable cleanroom, worktable, power cables, vacuum pumps and other obstacles).
  * We got Saito-sensei to move the PI to the +Y side of the cleanbooth.
  * We washed and cling-wrapped a pallet.
  * We got Miyoki-san to disconnect the cables and curtain blocking the crane slot (and reconnect them afterwards).
  * We added some temporary crossbars in the top of the assembly frame and stored the SF cap on them to get it out of the way.
  * We craned in the pallet and set it up to bridge three floor joists.
  * We craned in the PI using Saito-san's adapter.
   * We couldn't find the original screws for the three PI transport plates so we substituted some others - fortunately there was no galling.
   * We had to connect the adapter to the crane with a sling because the ring for the hook was slightly too small).
 * We did a lot of cabling work:
  * We routed all the BF cables over the BF cap, up through the cable clamp on the SF-BF rod and up to the SF. (We had to redo a few because the Type 3 cable was at the flange end instead of the Type 1.)
  * We connected up the SF LVDT and FR stepper.
  * We started on rebalancing the BF (which had been perturbed by the weight and tension of all the cables). We got it rather better, but it needs more work.
  * We made another batch of anti-feedthrough adapters.
==== Past two weeks report ====
At Kamioka (Mark, Enzo, Kozu-kun):
 * Supported IA team.
 * Replaced LPCDs for IM OSEMs with HPCDs for increased pitch/yaw range.
 * Re-zeroed OL after significant change of beam position during IA.
 * Re-laid-out OL to improve focus of lens to LEN QPD.
 * Offloaded the pitch/yaw actuation at the IM OSEMs using the IM pitch/yaw picos.
 * Enzo worked on design of control loops using the OL.
 * Kozu-kun worked on diagonalizing the OL.
Line 25: Line 16:
==== Plan for coming weeks ====
For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]].
Mitaka (Fabian, Hirata-san):
 * Hirata-san published his inventory of SR parts on Dropbox.
Line 28: Line 19:
Week of 4/10:
 * Hirata-san does scissor lift training 4/10.
 * Perry in Tokyo 4/10.
 * Debug/fix dead OSEM channel, TM-H4.
 * Debug BF/SF LVDTs.
 * Adjust BF pitch/roll.
 * Do TF from SF LVDT actuation.
 * Install temporary ballast mass in SF.
 * Lift SF/BF/... section and check total weight and SF balance.
 * Continue swap of PI LVDT connectors (female->male)
 * Start preparing LBB spring units.
 * Install pico drivers in rack, create MEDM interface (with Miyo-kun), and undo temporary connection of picos to old controller and joystick.
Week of 4/17:
 * Crane in PI.
 * Connect SF/BF... section.
 * Temporarily remove PI and adjust SF ballast if necessary.
 
==== Plan for week of 11/13 ====

Kamioka: Mark
 * Attend commissioning workshop at U Toyama.
 * Be person-on-site for BF work.
 * Set up for mirror gluing.

Mitaka: Fabian and Hirata-san
 * SR procurement.
 * New PI GAS FR design.
 * BS LBB ballast mass design.
 * SR cable lamp design.

Mitaka: Enzo and Kozu-kun (Wed, Thu)
 * Servos
 * TFs of BF
 * Documentation

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past two weeks report

At Kamioka (Mark, Enzo, Kozu-kun):

  • Supported IA team.
  • Replaced LPCDs for IM OSEMs with HPCDs for increased pitch/yaw range.
  • Re-zeroed OL after significant change of beam position during IA.
  • Re-laid-out OL to improve focus of lens to LEN QPD.
  • Offloaded the pitch/yaw actuation at the IM OSEMs using the IM pitch/yaw picos.
  • Enzo worked on design of control loops using the OL.
  • Kozu-kun worked on diagonalizing the OL.

Mitaka (Fabian, Hirata-san):

  • Hirata-san published his inventory of SR parts on Dropbox.

Plan for week of 11/13

Kamioka: Mark

  • Attend commissioning workshop at U Toyama.
  • Be person-on-site for BF work.
  • Set up for mirror gluing.

Mitaka: Fabian and Hirata-san

  • SR procurement.
  • New PI GAS FR design.
  • BS LBB ballast mass design.
  • SR cable lamp design.

Mitaka: Enzo and Kozu-kun (Wed, Thu)

  • Servos
  • TFs of BF
  • Documentation