Line 7: Line 7:
At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san):
 * We set things up again after the floor coating work.
 * We moved the PI into the second floor of the cleanbooth:
  * We cleared a path for the forklift (moving the portable cleanroom, worktable, power cables, vacuum pumps and other obstacles).
  * We got Saito-sensei to move the PI to the +Y side of the cleanbooth.
  * We washed and cling-wrapped a pallet.
  * We got Miyoki-san to disconnect the cables and curtain blocking the crane slot (and reconnect them afterwards).
  * We added some temporary crossbars in the top of the assembly frame and stored the SF cap on them to get it out of the way.
  * We craned in the pallet and set it up to bridge three floor joists.
  * We craned in the PI using Saito-san's adapter.
   * We couldn't find the original screws for the three PI transport plates so we substituted some others - fortunately there was no galling.
   * We had to connect the adapter to the crane with a sling because the ring for the hook was slightly too small).
 * We did a lot of cabling work:
  * We routed all the BF cables over the BF cap, up through the cable clamp on the SF-BF rod and up to the SF. (We had to redo a few because the Type 3 cable was at the flange end instead of the Type 1.)
  * We connected up the SF LVDT and FR stepper.
  * We started on rebalancing the BF (which had been perturbed by the weight and tension of all the cables). We got it rather better, but it needs more work.
  * We made another batch of anti-feedthrough adapters.
Line 25: Line 8:
==== Plan for coming weeks ====
For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]].
 * Mark and Fabian did a huge cleanup of the SR2 area and prepared a workspace for assembling the IM.
 * Fabian did a stocktake of the screws for the SR.
  * We have all we need for the IM, except one type that can be added after the rest of the IP is assembled.
  * We have most of what we need for the rest of the payload, and Hirata-san has ordered the others.
 * Hirata-san worked on SR procurement:
  * Suspension wire
  * SR additional parts (compensation masses, clamps etc)
  * Regular, SDC and BUMAX screws.
  * Additional machining on the BS sapphire prism jig to allow it to be used on the PR/SR mirror box.
  * LBB blade design.
 * Enzo and Kozu-kun (with help from Fujii-kun) worked on export from SUMCON to Matlab, and on filter design).
Line 28: Line 20:
Week of 4/10:
 * Hirata-san does scissor lift training 4/10.
 * Perry in Tokyo 4/10.
 * Debug/fix dead OSEM channel, TM-H4.
 * Debug BF/SF LVDTs.
 * Adjust BF pitch/roll.
 * Do TF from SF LVDT actuation.
 * Install temporary ballast mass in SF.
 * Lift SF/BF/... section and check total weight and SF balance.
 * Continue swap of PI LVDT connectors (female->male)
 * Start preparing LBB spring units.
 * Install pico drivers in rack, create MEDM interface (with Miyo-kun), and undo temporary connection of picos to old controller and joystick.
Week of 4/17:
 * Crane in PI.
 * Connect SF/BF... section.
 * Temporarily remove PI and adjust SF ballast if necessary.
 
==== Plan for week of 11/20 ====
 * Holiday on Thu 3/23
 * All at Mitaka.
 * SR procurement, planning (Mark, Hirata-san)
 * SR mass budget (Fabian)
 * BS modeling filter design (Enzo, Kozu-kun)


==== Plan for week of 11/27 ====
 * Fabian at commissioning workshop
 *

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

  • Mark and Fabian did a huge cleanup of the SR2 area and prepared a workspace for assembling the IM.
  • Fabian did a stocktake of the screws for the SR.
    • We have all we need for the IM, except one type that can be added after the rest of the IP is assembled.
    • We have most of what we need for the rest of the payload, and Hirata-san has ordered the others.
  • Hirata-san worked on SR procurement:
    • Suspension wire
    • SR additional parts (compensation masses, clamps etc)
    • Regular, SDC and BUMAX screws.
    • Additional machining on the BS sapphire prism jig to allow it to be used on the PR/SR mirror box.
    • LBB blade design.
  • Enzo and Kozu-kun (with help from Fujii-kun) worked on export from SUMCON to Matlab, and on filter design).

Plan for week of 11/20

  • Holiday on Thu 3/23
  • All at Mitaka.
  • SR procurement, planning (Mark, Hirata-san)
  • SR mass budget (Fabian)
  • BS modeling filter design (Enzo, Kozu-kun)

Plan for week of 11/27

  • Fabian at commissioning workshop