Size: 2491
Comment:
|
Size: 1204
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 7: | Line 7: |
At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san): * We set things up again after the floor coating work. * We moved the PI into the second floor of the cleanbooth: * We cleared a path for the forklift (moving the portable cleanroom, worktable, power cables, vacuum pumps and other obstacles). * We got Saito-sensei to move the PI to the +Y side of the cleanbooth. * We washed and cling-wrapped a pallet. * We got Miyoki-san to disconnect the cables and curtain blocking the crane slot (and reconnect them afterwards). * We added some temporary crossbars in the top of the assembly frame and stored the SF cap on them to get it out of the way. * We craned in the pallet and set it up to bridge three floor joists. * We craned in the PI using Saito-san's adapter. * We couldn't find the original screws for the three PI transport plates so we substituted some others - fortunately there was no galling. * We had to connect the adapter to the crane with a sling because the ring for the hook was slightly too small). * We did a lot of cabling work: * We routed all the BF cables over the BF cap, up through the cable clamp on the SF-BF rod and up to the SF. (We had to redo a few because the Type 3 cable was at the flange end instead of the Type 1.) * We connected up the SF LVDT and FR stepper. * We started on rebalancing the BF (which had been perturbed by the weight and tension of all the cables). We got it rather better, but it needs more work. * We made another batch of anti-feedthrough adapters. |
|
Line 25: | Line 8: |
==== Plan for coming weeks ==== For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]]. |
* Mark and Fabian did a huge cleanup of the SR2 area and prepared a workspace for assembling the IM. * Fabian did a stocktake of the screws for the SR. * We have all we need for the IM, except one type that can be added after the rest of the IP is assembled. * We have most of what we need for the rest of the payload, and Hirata-san has ordered the others. * Hirata-san worked on SR procurement: * Suspension wire * SR additional parts (compensation masses, clamps etc) * Regular, SDC and BUMAX screws. * Additional machining on the BS sapphire prism jig to allow it to be used on the PR/SR mirror box. * LBB blade design. * Enzo and Kozu-kun (with help from Fujii-kun) worked on export from SUMCON to Matlab, and on filter design). |
Line 28: | Line 20: |
Week of 4/10: * Hirata-san does scissor lift training 4/10. * Perry in Tokyo 4/10. * Debug/fix dead OSEM channel, TM-H4. * Debug BF/SF LVDTs. * Adjust BF pitch/roll. * Do TF from SF LVDT actuation. * Install temporary ballast mass in SF. * Lift SF/BF/... section and check total weight and SF balance. * Continue swap of PI LVDT connectors (female->male) * Start preparing LBB spring units. * Install pico drivers in rack, create MEDM interface (with Miyo-kun), and undo temporary connection of picos to old controller and joystick. Week of 4/17: * Crane in PI. * Connect SF/BF... section. * Temporarily remove PI and adjust SF ballast if necessary. |
==== Plan for week of 11/20 ==== * Holiday on Thu 3/23 * All at Mitaka. * SR procurement, planning (Mark, Hirata-san) * SR mass budget (Fabian) * BS modeling filter design (Enzo, Kozu-kun) ==== Plan for week of 11/27 ==== * Fabian at commissioning workshop * |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past week report
- Mark and Fabian did a huge cleanup of the SR2 area and prepared a workspace for assembling the IM.
- Fabian did a stocktake of the screws for the SR.
- We have all we need for the IM, except one type that can be added after the rest of the IP is assembled.
- We have most of what we need for the rest of the payload, and Hirata-san has ordered the others.
- Hirata-san worked on SR procurement:
- Suspension wire
- SR additional parts (compensation masses, clamps etc)
- Regular, SDC and BUMAX screws.
- Additional machining on the BS sapphire prism jig to allow it to be used on the PR/SR mirror box.
- LBB blade design.
- Enzo and Kozu-kun (with help from Fujii-kun) worked on export from SUMCON to Matlab, and on filter design).
Plan for week of 11/20
- Holiday on Thu 3/23
- All at Mitaka.
- SR procurement, planning (Mark, Hirata-san)
- SR mass budget (Fabian)
- BS modeling filter design (Enzo, Kozu-kun)
Plan for week of 11/27
- Fabian at commissioning workshop