Line 7: Line 7:
At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san):
 * We set things up again after the floor coating work.
 * We moved the PI into the second floor of the cleanbooth:
  * We cleared a path for the forklift (moving the portable cleanroom, worktable, power cables, vacuum pumps and other obstacles).
  * We got Saito-sensei to move the PI to the +Y side of the cleanbooth.
  * We washed and cling-wrapped a pallet.
  * We got Miyoki-san to disconnect the cables and curtain blocking the crane slot (and reconnect them afterwards).
  * We added some temporary crossbars in the top of the assembly frame and stored the SF cap on them to get it out of the way.
  * We craned in the pallet and set it up to bridge three floor joists.
  * We craned in the PI using Saito-san's adapter.
   * We couldn't find the original screws for the three PI transport plates so we substituted some others - fortunately there was no galling.
   * We had to connect the adapter to the crane with a sling because the ring for the hook was slightly too small).
 * We did a lot of cabling work:
  * We routed all the BF cables over the BF cap, up through the cable clamp on the SF-BF rod and up to the SF. (We had to redo a few because the Type 3 cable was at the flange end instead of the Type 1.)
  * We connected up the SF LVDT and FR stepper.
  * We started on rebalancing the BF (which had been perturbed by the weight and tension of all the cables). We got it rather better, but it needs more work.
  * We made another batch of anti-feedthrough adapters.
Line 25: Line 8:
==== Plan for coming weeks ====
For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]].
 * Mark worked on SR2 planning.
 * Mark thought through what would be required to swap an optic (e.g., SRM) in situ (JGW-T1707436).
 * Hirata-san tried removing disks from IM flags (so we could reuse them in flag bases and make a complete set for SR2) but only got 1 of 4 out.
 * Hirata-san ordered more disks for IM flags.
 * Hirata-san asked for quotes on SF LBB blades.
 * Hirata-san got a reduced quote for the LBB damper rings.
 * Hirata-san received and cleaned suspension wires for the SR.
 * Fabian worked on the SR mass budget.
 * Fabian worked out the COM of the SR2 optic, and Mark used it to derive the proper prism positions.
 * Enzo and Kozu-kun worked on control filter design and installation.
Line 28: Line 19:
Week of 4/10:
 * Hirata-san does scissor lift training 4/10.
 * Perry in Tokyo 4/10.
 * Debug/fix dead OSEM channel, TM-H4.
 * Debug BF/SF LVDTs.
 * Adjust BF pitch/roll.
 * Do TF from SF LVDT actuation.
 * Install temporary ballast mass in SF.
 * Lift SF/BF/... section and check total weight and SF balance.
 * Continue swap of PI LVDT connectors (female->male)
 * Start preparing LBB spring units.
 * Install pico drivers in rack, create MEDM interface (with Miyo-kun), and undo temporary connection of picos to old controller and joystick.
Week of 4/17:
 * Crane in PI.
 * Connect SF/BF... section.
 * Temporarily remove PI and adjust SF ballast if necessary.
 
==== Plan for week of 11/27 ====
 * Fabian at commissioning workshop
 * Hirata-san at Kamioka Tue-Fri to work with Mirapro on SRM LBB installation.
 * All others (Mark, Enzo, Shoda-san, Kozu-kun) at Kamioka to start SR2 assembly.
  * Mark from Mon lunchtime.
  * Kozu-kun from Mon lunchtime through Wed.
  * Mirror gluing.
  * SR2 rack setup.

==== Plan for week of 12/4 ====
 * All at Kamioka
  * IM assembly and pico test.
  * Assembly frame alignment and optical table centering.
  * OL setup.
  

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

  • Mark worked on SR2 planning.
  • Mark thought through what would be required to swap an optic (e.g., SRM) in situ (JGW-T1707436).
  • Hirata-san tried removing disks from IM flags (so we could reuse them in flag bases and make a complete set for SR2) but only got 1 of 4 out.
  • Hirata-san ordered more disks for IM flags.
  • Hirata-san asked for quotes on SF LBB blades.
  • Hirata-san got a reduced quote for the LBB damper rings.
  • Hirata-san received and cleaned suspension wires for the SR.
  • Fabian worked on the SR mass budget.
  • Fabian worked out the COM of the SR2 optic, and Mark used it to derive the proper prism positions.
  • Enzo and Kozu-kun worked on control filter design and installation.

Plan for week of 11/27

  • Fabian at commissioning workshop
  • Hirata-san at Kamioka Tue-Fri to work with Mirapro on SRM LBB installation.
  • All others (Mark, Enzo, Shoda-san, Kozu-kun) at Kamioka to start SR2 assembly.
    • Mark from Mon lunchtime.
    • Kozu-kun from Mon lunchtime through Wed.
    • Mirror gluing.
    • SR2 rack setup.

Plan for week of 12/4

  • All at Kamioka
    • IM assembly and pico test.
    • Assembly frame alignment and optical table centering.
    • OL setup.