Size: 2491
Comment:
|
Size: 2458
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 6: | Line 6: |
==== Past week report ==== At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san): * We set things up again after the floor coating work. * We moved the PI into the second floor of the cleanbooth: * We cleared a path for the forklift (moving the portable cleanroom, worktable, power cables, vacuum pumps and other obstacles). * We got Saito-sensei to move the PI to the +Y side of the cleanbooth. * We washed and cling-wrapped a pallet. * We got Miyoki-san to disconnect the cables and curtain blocking the crane slot (and reconnect them afterwards). * We added some temporary crossbars in the top of the assembly frame and stored the SF cap on them to get it out of the way. * We craned in the pallet and set it up to bridge three floor joists. * We craned in the PI using Saito-san's adapter. * We couldn't find the original screws for the three PI transport plates so we substituted some others - fortunately there was no galling. * We had to connect the adapter to the crane with a sling because the ring for the hook was slightly too small). * We did a lot of cabling work: * We routed all the BF cables over the BF cap, up through the cable clamp on the SF-BF rod and up to the SF. (We had to redo a few because the Type 3 cable was at the flange end instead of the Type 1.) * We connected up the SF LVDT and FR stepper. * We started on rebalancing the BF (which had been perturbed by the weight and tension of all the cables). We got it rather better, but it needs more work. * We made another batch of anti-feedthrough adapters. |
==== Report for week of 2/26 ==== * We routed all the cables from the BF level up via the flying saucer to the SF. * Hirata-san tried filing the SF cap to improve the fit, but without much success. * Hirata-san installed the Cu segments and cable clamps on the SF cap and the SF LVDT and FR cables. * We cabled and tested the BF cap picos and the SF LVDT and FR. (The LVDT still needs a full calibration.) * We worked on recovering the IM OSEM alignment. |
Line 25: | Line 13: |
==== Plan for coming weeks ==== For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]]. |
==== Plan for week of 3/5 ==== * Shoda-san at Mitaka. * Hirata-san vacation Mon 3/5, then Kamioka * Others at Kamioka. * - * '''Remove LBB temporary ballast masses from BS chamber.''' * Finish recovering IM OSEM alignment. * Calibrate SF LVDT. * Lift SF/... section and check total mass and balance. * Get SRM tank mushroom section installed (Hirata-san, Kimura-san) * Set up for rebuilding of two BFs. |
Line 28: | Line 25: |
Week of 4/10: * Hirata-san does scissor lift training 4/10. * Perry in Tokyo 4/10. * Debug/fix dead OSEM channel, TM-H4. * Debug BF/SF LVDTs. * Adjust BF pitch/roll. * Do TF from SF LVDT actuation. * Install temporary ballast mass in SF. * Lift SF/BF/... section and check total weight and SF balance. * Continue swap of PI LVDT connectors (female->male) * Start preparing LBB spring units. * Install pico drivers in rack, create MEDM interface (with Miyo-kun), and undo temporary connection of picos to old controller and joystick. Week of 4/17: * Crane in PI. * Connect SF/BF... section. * Temporarily remove PI and adjust SF ballast if necessary. |
==== Plan for week of 3/12 ==== * Shoda-san at Mitaka. * Mark at ASJ (Chiba) Fri, then Mitaka. * Hirata-san vacation Mon 3/5; Kamioka Tue-Thu; Mitaka Fri * Others Kamioka Mon-Thu * Install boxes in SR3 and SRM racks. * Lay SR3 in-air cabling. * Continue rebuild of BFs. ==== Plan for week of 3/19 ==== * Mark at LVC meeting * All others at Mitaka * Make two sets of IM OSEMs * Make last in-air pico adapter cable * Make three in-air stepper splitter cables for SR2, SR3 and SRM. * Set up Dummy BS prism removal. ==== Plan for week of 3/26 ==== * Mark vacation. * Shoda-san at Mitaka * Others at Kamioka * -- * F0 Prototype Blade Test * Characterize blades. * Choose best set of three. * Remove cracked blades from filter in SRM area. * Set up test weights in SRM area, first floor. * Remove floor panel in SRM area, second floor. * Install chosen blades. * Measure load capacity. ==== To-Do Lists, Schedule ==== * [[KAGRA/Subgroups/VIS/TypeB/March2018]] * [[KAGRA/Subgroups/VIS/TypeB/April2018]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]] ==== Vacation Info ==== * Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun) * Hirata-san vacation, Mon 3/5. * Fabian vacation, 3/26-4/27 (then gone). |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 2/26
- We routed all the cables from the BF level up via the flying saucer to the SF.
- Hirata-san tried filing the SF cap to improve the fit, but without much success.
- Hirata-san installed the Cu segments and cable clamps on the SF cap and the SF LVDT and FR cables.
- We cabled and tested the BF cap picos and the SF LVDT and FR. (The LVDT still needs a full calibration.)
- We worked on recovering the IM OSEM alignment.
Plan for week of 3/5
- Shoda-san at Mitaka.
- Hirata-san vacation Mon 3/5, then Kamioka
- Others at Kamioka.
- -
Remove LBB temporary ballast masses from BS chamber.
- Finish recovering IM OSEM alignment.
- Calibrate SF LVDT.
- Lift SF/... section and check total mass and balance.
- Get SRM tank mushroom section installed (Hirata-san, Kimura-san)
- Set up for rebuilding of two BFs.
Plan for week of 3/12
- Shoda-san at Mitaka.
- Mark at ASJ (Chiba) Fri, then Mitaka.
- Hirata-san vacation Mon 3/5; Kamioka Tue-Thu; Mitaka Fri
- Others Kamioka Mon-Thu
- Install boxes in SR3 and SRM racks.
- Lay SR3 in-air cabling.
- Continue rebuild of BFs.
Plan for week of 3/19
- Mark at LVC meeting
- All others at Mitaka
- Make two sets of IM OSEMs
- Make last in-air pico adapter cable
- Make three in-air stepper splitter cables for SR2, SR3 and SRM.
- Set up Dummy BS prism removal.
Plan for week of 3/26
- Mark vacation.
- Shoda-san at Mitaka
- Others at Kamioka
- --
- F0 Prototype Blade Test
- Characterize blades.
- Choose best set of three.
- Remove cracked blades from filter in SRM area.
- Set up test weights in SRM area, first floor.
- Remove floor panel in SRM area, second floor.
- Install chosen blades.
- Measure load capacity.
To-Do Lists, Schedule
Vacation Info
- Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
- Hirata-san vacation, Mon 3/5.
- Fabian vacation, 3/26-4/27 (then gone).