Line 7: Line 7:
At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san):

 * Realized that the SF/BF/... section doesn't need 6 kg added, it needs 6 kg ''removed'', but none to remove. The 20 kg extra in the BF to match the SF GAS filter makes the whole chain overload the PI GAS filter.
 * Lifted the SF/BF/... section to check for net weight and balance. Was 307 kg (cf. G&M's measurement of 301 kf in 2012 for the F0). Can be balanced with only 63 g extra.
 * Went to build up the LBB blade units but discovered that the holes in the base of the blades are two small (are Ø11 mm; should be Ø12 MM). 3D CAD was correct - error was in the 2D drawing. Shipped the blades away for modification.
 * Tested the SF LVDT actuation and worked on debugging it. Still not working.
 * Prepared the PI for being lifted, and the top of the assembly frame for receiving it.
 * Searched for and found the old PI-SF rod.
 * Did safety improvements after Enzo hit his head on a flange bolt: reversed all the bolts on the ±X sides of the BS and put caution tape on them.
 * Debugged Kokeyama-san's changes to the real-time model for the DIO, and started on TFs to check the output filter compensation is working.
At Kamioka (Mark, Fabian, Enzo, Hirata-san):
 * Hirata-san and Mark reversed the support ring for the LBB damper to match the reversed suspension.
 * Hirata-san did a trial assembly of the magnet ring for the LLB damper and placed magnets on it with the template.
 * Hirata-san and Mark put the base pieces for the Cu ring in the chamber. However it turns out that the holes for attaching the joint pieces are incompletely threaded and we will have to run a tap through them.
 * We tested the geophones. At first one didn't work at all. This turned out to be a broken wire in one of the in-vacuum adapter cables. For the test we replaced the adapter with an old-style one (and removed the matching descrambler). A second geophone mostly works but saturates at a suspiciously low number of counts at the ADC (2000 instead of 20000).
 * We tested the PI horizontal LVDTs. The #1 (H2) one works but cable swaps showed that #0 and #2 have issues both at the tank end and at the card.
 * We decided on a final location for the stepper and pico drivers on the second floor. We moved the cables for the stepper drivers (using the outside cable trays) and laid new LAN and AC cables for the picos.
Line 21: Line 18:
Week of 4/24 (four-day week):
 * Crane in PI.
 * Connect SF/BF... section and see if we're indeed overweight and by exactly how much.
 * Finish debugging SF LVDT actuation.

Week of 5/1:
 * No activity (Golden Week).
Week of 6/12:
 * Cabling:
  * Debug/fix PI vertical LVDTs #0 and #2.
  * Calibrate PI vertical LVDT.
  * Debug/fix geophone #1.
  * Set yoke on PI vertical LVDT (if necessary).
  * Cable and test PI yaw stepper.
  * Cable and test PI vertical stepper.
  * Cable and test PI horizontal steppers.
  * Cable and test PI horizontal LVDTs.
  * Calibrate PI horizontal LVDTs.
 * Prepare LBB.
  * Attach LBB outriggers and rod receptacles.
 * Prepare LBB Cu ring.
  * Remove from tank, fix incompletely threaded holes, reinstall in tank.
  * Lay down spacers to protect magnets (in next step).
 * Prepare LBB magnet ring.
  * Disassemble.
  * Pass pieces into tank.
  * Reassemble on top of Cu ring.
 * Install LBB damper.
  * Bind LBB damper rings together with slings.
  * Remove vacuum tank lid and ring.
  * Crane rings up to install height, hook LBB magnet ring and support LBB Cu ring by TBD method.
 * Crane suspension into tank.
 * Hook LBB Cu ring.
 * Hook LBB.
 * Crane vacuum tank lid+ring black on.
 * Remove vacuum tank lid (only).
 * Remove port covers where feedthroughs will go, move feedthroughs from assembly frame and install on vacuum tank ring.
 * Reconnect in-air cables.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Fabian, Enzo, Hirata-san):

  • Hirata-san and Mark reversed the support ring for the LBB damper to match the reversed suspension.
  • Hirata-san did a trial assembly of the magnet ring for the LLB damper and placed magnets on it with the template.
  • Hirata-san and Mark put the base pieces for the Cu ring in the chamber. However it turns out that the holes for attaching the joint pieces are incompletely threaded and we will have to run a tap through them.
  • We tested the geophones. At first one didn't work at all. This turned out to be a broken wire in one of the in-vacuum adapter cables. For the test we replaced the adapter with an old-style one (and removed the matching descrambler). A second geophone mostly works but saturates at a suspiciously low number of counts at the ADC (2000 instead of 20000).
  • We tested the PI horizontal LVDTs. The #1 (H2) one works but cable swaps showed that #0 and #2 have issues both at the tank end and at the card.
  • We decided on a final location for the stepper and pico drivers on the second floor. We moved the cables for the stepper drivers (using the outside cable trays) and laid new LAN and AC cables for the picos.

Plan for coming weeks

For more detail, see KAGRA/Subgroups/VIS/TypeB/ToDo.

Week of 6/12:

  • Cabling:
    • Debug/fix PI vertical LVDTs #0 and #2.
    • Calibrate PI vertical LVDT.
    • Debug/fix geophone #1.
    • Set yoke on PI vertical LVDT (if necessary).
    • Cable and test PI yaw stepper.
    • Cable and test PI vertical stepper.
    • Cable and test PI horizontal steppers.
    • Cable and test PI horizontal LVDTs.
    • Calibrate PI horizontal LVDTs.
  • Prepare LBB.
    • Attach LBB outriggers and rod receptacles.
  • Prepare LBB Cu ring.
    • Remove from tank, fix incompletely threaded holes, reinstall in tank.
    • Lay down spacers to protect magnets (in next step).
  • Prepare LBB magnet ring.
    • Disassemble.
    • Pass pieces into tank.
    • Reassemble on top of Cu ring.
  • Install LBB damper.
    • Bind LBB damper rings together with slings.
    • Remove vacuum tank lid and ring.
    • Crane rings up to install height, hook LBB magnet ring and support LBB Cu ring by TBD method.
  • Crane suspension into tank.
  • Hook LBB Cu ring.
  • Hook LBB.
  • Crane vacuum tank lid+ring black on.
  • Remove vacuum tank lid (only).
  • Remove port covers where feedthroughs will go, move feedthroughs from assembly frame and install on vacuum tank ring.
  • Reconnect in-air cables.