Line 7: Line 7:
At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san): At Kamioka (Mark, Fabian, Enzo, Hirata-san):
 * Hirata-san did an inventory of SR and other parts at Kamioka.
 * Mark and Enzo finalized the geometry matrices for the IP, entered them in MEDM and updated the safe.snap.
 * Mark, Enzo and Fabian worked with Izumi-san et al. to align the BS. We got the +Y beam fairly close to aligned (to the second gate valve, near IY).
Line 9: Line 12:
 * Realized that the SF/BF/... section doesn't need 6 kg added, it needs 6 kg ''removed'', but none to remove. The 20 kg extra in the BF to match the SF GAS filter makes the whole chain overload the PI GAS filter.
 * Lifted the SF/BF/... section to check for net weight and balance. Was 307 kg (cf. G&M's measurement of 301 kf in 2012 for the F0). Can be balanced with only 63 g extra.
 * Went to build up the LBB blade units but discovered that the holes in the base of the blades are two small (are Ø11 mm; should be Ø12 MM). 3D CAD was correct - error was in the 2D drawing. Shipped the blades away for modification.
 * Tested the SF LVDT actuation and worked on debugging it. Still not working.
 * Prepared the PI for being lifted, and the top of the assembly frame for receiving it.
 * Searched for and found the old PI-SF rod.
 * Did safety improvements after Enzo hit his head on a flange bolt: reversed all the bolts on the ±X sides of the BS and put caution tape on them.
 * Debugged Kokeyama-san's changes to the real-time model for the DIO, and started on TFs to check the output filter compensation is working.
==== Plan for week of 10/30 ====
Line 18: Line 14:
==== Plan for coming weeks ====
For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]].
Kamioka: Mark and Enzo
 * Continue alignment of BS.
 * Realign OL.
 * Work on servos.
Line 21: Line 19:
Week of 4/24 (four-day week):
 * Crane in PI.
 * Connect SF/BF... section and see if we're indeed overweight and by exactly how much.
 * Finish debugging SF LVDT actuation.

Week of 5/1:
 * No activity (Golden Week).
Mitaka: Fabian and Hirata-san
 * SR procurement.
 * New PI GAS FR design.
 * BS LBB ballast mass design.
 * SR cable lamp design.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Fabian, Enzo, Hirata-san):

  • Hirata-san did an inventory of SR and other parts at Kamioka.
  • Mark and Enzo finalized the geometry matrices for the IP, entered them in MEDM and updated the safe.snap.
  • Mark, Enzo and Fabian worked with Izumi-san et al. to align the BS. We got the +Y beam fairly close to aligned (to the second gate valve, near IY).

Plan for week of 10/30

Kamioka: Mark and Enzo

  • Continue alignment of BS.
  • Realign OL.
  • Work on servos.

Mitaka: Fabian and Hirata-san

  • SR procurement.
  • New PI GAS FR design.
  • BS LBB ballast mass design.
  • SR cable lamp design.