At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san):
Line 9: Line 8:
 * Realized that the SF/BF/... section doesn't need 6 kg added, it needs 6 kg ''removed'', but none to remove. The 20 kg extra in the BF to match the SF GAS filter makes the whole chain overload the PI GAS filter.
 * Lifted the SF/BF/... section to check for net weight and balance. Was 307 kg (cf. G&M's measurement of 301 kf in 2012 for the F0). Can be balanced with only 63 g extra.
 * Went to build up the LBB blade units but discovered that the holes in the base of the blades are two small (are Ø11 mm; should be Ø12 MM). 3D CAD was correct - error was in the 2D drawing. Shipped the blades away for modification.
 * Tested the SF LVDT actuation and worked on debugging it. Still not working.
 * Prepared the PI for being lifted, and the top of the assembly frame for receiving it.
 * Searched for and found the old PI-SF rod.
 * Did safety improvements after Enzo hit his head on a flange bolt: reversed all the bolts on the ±X sides of the BS and put caution tape on them.
 * Debugged Kokeyama-san's changes to the real-time model for the DIO, and started on TFs to check the output filter compensation is working.
 * Mark worked on SR2 planning.
 * Mark thought through what would be required to swap an optic (e.g., SRM) in situ (JGW-T1707436).
 * Hirata-san tried removing disks from IM flags (so we could reuse them in flag bases and make a complete set for SR2) but only got 1 of 4 out.
 * Hirata-san ordered more disks for IM flags.
 * Hirata-san asked for quotes on SF LBB blades.
 * Hirata-san got a reduced quote for the LBB damper rings.
 * Hirata-san received and cleaned suspension wires for the SR.
 * Fabian worked on the SR mass budget.
 * Fabian worked out the COM of the SR2 optic, and Mark used it to derive the proper prism positions.
 * Enzo and Kozu-kun worked on control filter design and installation.
Line 18: Line 19:
==== Plan for coming weeks ====
For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]].
==== Plan for week of 11/27 ====
 * Fabian at commissioning workshop
 * Hirata-san at Kamioka Tue-Fri to work with Mirapro on SRM LBB installation.
 * All others (Mark, Enzo, Shoda-san, Kozu-kun) at Kamioka to start SR2 assembly.
  * Mark from Mon lunchtime.
  * Kozu-kun from Mon lunchtime through Wed.
  * Mirror gluing.
  * SR2 rack setup.
Line 21: Line 28:
Week of 4/24 (four-day week):
 * Crane in PI.
 * Connect SF/BF... section and see if we're indeed overweight and by exactly how much.
 * Finish debugging SF LVDT actuation.
==== Plan for week of 12/4 ====
 * All at Kamioka
  * IM assembly and pico test.
  * Assembly frame alignment and optical table centering.
  * OL setup.
Line 26: Line 34:
Week of 5/1:
 * No activity (Golden Week).
==== Vacation Info ====
 * Mark 12/22-1/3
 * Enzo TBD, probably 12/22-1/3
 * Fabian 12/22-1/5
 * Hirata-san 12/21-22 (conference)
  

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

  • Mark worked on SR2 planning.
  • Mark thought through what would be required to swap an optic (e.g., SRM) in situ (JGW-T1707436).
  • Hirata-san tried removing disks from IM flags (so we could reuse them in flag bases and make a complete set for SR2) but only got 1 of 4 out.
  • Hirata-san ordered more disks for IM flags.
  • Hirata-san asked for quotes on SF LBB blades.
  • Hirata-san got a reduced quote for the LBB damper rings.
  • Hirata-san received and cleaned suspension wires for the SR.
  • Fabian worked on the SR mass budget.
  • Fabian worked out the COM of the SR2 optic, and Mark used it to derive the proper prism positions.
  • Enzo and Kozu-kun worked on control filter design and installation.

Plan for week of 11/27

  • Fabian at commissioning workshop
  • Hirata-san at Kamioka Tue-Fri to work with Mirapro on SRM LBB installation.
  • All others (Mark, Enzo, Shoda-san, Kozu-kun) at Kamioka to start SR2 assembly.
    • Mark from Mon lunchtime.
    • Kozu-kun from Mon lunchtime through Wed.
    • Mirror gluing.
    • SR2 rack setup.

Plan for week of 12/4

  • All at Kamioka
    • IM assembly and pico test.
    • Assembly frame alignment and optical table centering.
    • OL setup.

Vacation Info

  • Mark 12/22-1/3
  • Enzo TBD, probably 12/22-1/3
  • Fabian 12/22-1/5
  • Hirata-san 12/21-22 (conference)

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)