Differences between revisions 139 and 168 (spanning 29 versions)
Revision 139 as of 2017-04-27 15:53:11
Size: 1534
Editor: MarkBarton
Comment:
Revision 168 as of 2017-07-21 14:12:00
Size: 1551
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 7: Line 7:
At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san): At Kamioka (Mark, Enzo, Hirata-san, Yoshioka-kun):
 * We lubricated the stuck screw at the top of the security structure with stuck and were able to remove it.
 * Enzo disconnected and removed or coiled many in-vac cables at the PI level to free it.
 * We craned the PI. There was a minor safety incident - see below.
 * Hirata-san set up the filter service area, and we moved in a BF intended for one of the SRs (BF#3).
 * Fabian and Hirata-san worked out a method for characterizing a single spring, and Fabian finished characterizing the first one.
 * We did a big tidy-up and clean-up of the area, especially the corner where we intended to do the gluing.
 * We set up the BS gluing jigs and applied the glue. We will check the results on Monday.
Line 9: Line 16:
 * Craned in the PI.
 * Assembled the thrust bearing holder that receives the PI-SF rod. (It originally had a burr that prevented the bearing from seating properly, and so required filing and re-cleaning.)
 * Hooked the SF and lowered the jacks under the SF to suspend the SF/... section.
 * The top filter rose when unlocked, and required about 1.8 kg to send it back down. Therefore we may be OK - the top filter seems to have about 8 kg more capacity than as measured by G&M. The hex cable clamp (≈0.25 kg) and the cables between the PI and SF still have to be added, but we can get an extra 3 kg by removing one of the three Cu damper segments (and rearranging the other two).
 * Built and installed three LBB blade units.
 * Kept debugging the SF LVDT. We repaired several broken wires, but it's still not behaving correctly.
==== Plan for week of 7/24 ====
Full team at Kamioka from Mon-Fri, except Hirata-san (Tue-Fri) and Enzo (vacation).
 * Check results of gluing.
 * Finish disassembly.
 * Finish BF rebuild.
 * Remove LBB rings.
 * Recheck alignment of assembly frame and centering of optical table.
 * Install IM, suspend BS and RM.
Line 16: Line 25:
==== Plan for coming weeks ====
For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]].
==== Plan for week of 7/31 ====
Full team at Kamioka from Mon-Fri, except Fabian (Mon-Thu) and Enzo (vacation).
 * Weigh/trim BS/RM/IM.
 * Bring in rebuilt BF.
Line 19: Line 30:
Week of 5/1:
 * No activity (Golden Week).

Week of 5/8:
 * Work from Tuesday.
 * Remove PI temporarily.
 * Add magnets to upper SF damper ring.
 * Reinstall PI with damper ring.
 * Reinstall PI-SF rod, this time with hex cable clamp.
 * Install PI yaw stepper.
 * Wire up PI yaw and vertical steppers.
 * Route cables from SF to PI (may involve removing part of Cu damper).
Vacation Info:
Hirata-san: Thu 7/20 through Mon 7/24
Enzo: Sat 7/22 through Sun 8/6
Fabian: Fri 8/4 through Mon 8/21
Mark: TBD Mid-Oct

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Enzo, Hirata-san, Yoshioka-kun):

  • We lubricated the stuck screw at the top of the security structure with stuck and were able to remove it.
  • Enzo disconnected and removed or coiled many in-vac cables at the PI level to free it.
  • We craned the PI. There was a minor safety incident - see below.
  • Hirata-san set up the filter service area, and we moved in a BF intended for one of the SRs (BF#3).
  • Fabian and Hirata-san worked out a method for characterizing a single spring, and Fabian finished characterizing the first one.
  • We did a big tidy-up and clean-up of the area, especially the corner where we intended to do the gluing.
  • We set up the BS gluing jigs and applied the glue. We will check the results on Monday.

Plan for week of 7/24

Full team at Kamioka from Mon-Fri, except Hirata-san (Tue-Fri) and Enzo (vacation).

  • Check results of gluing.
  • Finish disassembly.
  • Finish BF rebuild.
  • Remove LBB rings.
  • Recheck alignment of assembly frame and centering of optical table.
  • Install IM, suspend BS and RM.

Plan for week of 7/31

Full team at Kamioka from Mon-Fri, except Fabian (Mon-Thu) and Enzo (vacation).

  • Weigh/trim BS/RM/IM.
  • Bring in rebuilt BF.

Vacation Info: Hirata-san: Thu 7/20 through Mon 7/24 Enzo: Sat 7/22 through Sun 8/6 Fabian: Fri 8/4 through Mon 8/21 Mark: TBD Mid-Oct

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)