Differences between revisions 139 and 187 (spanning 48 versions)
Revision 139 as of 2017-04-27 15:53:11
Size: 1534
Editor: MarkBarton
Comment:
Revision 187 as of 2017-09-08 13:41:35
Size: 1973
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 7: Line 7:
At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san): At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):
 * We craned out the SF temporarily and retrieved the lost PEEK cable clamp collet from the BF.
 * We installed the BF.
 * We routed cables from the BF via the hex cable clamp to the SF level.
 * We adjusted the BF trim mass for pitch, roll and vertical, and got the IRM hanging symmetrically around the IM.
 * We adjusted all the IRM OSEMs laterally and in/out.
 * We calibrated the SF LVDT and tested the SF FR stepper.
 * We suspended the SF/... section and weighed it but found the old 7-mm maraging rod adapter did not hold it at the center, so we chad to lift it with slings and could not accurately trim it for pitch/roll.
 * We craned in the PI with the SF damper ring hanging from it.
 * We suspended the SF successfully from the PI and unlocked the F0 keystone to check the mass budget. We needed about 1.5 kg extra, which is about right.
 * However we had to leave out the F0-SF hex cable clamp because of a bad thread on the inside of the cap. Hirata-san will make a new cap by enlarging the 7-mm hole in an old cap to 8 mm.
Line 9: Line 19:
 * Craned in the PI.
 * Assembled the thrust bearing holder that receives the PI-SF rod. (It originally had a burr that prevented the bearing from seating properly, and so required filing and re-cleaning.)
 * Hooked the SF and lowered the jacks under the SF to suspend the SF/... section.
 * The top filter rose when unlocked, and required about 1.8 kg to send it back down. Therefore we may be OK - the top filter seems to have about 8 kg more capacity than as measured by G&M. The hex cable clamp (≈0.25 kg) and the cables between the PI and SF still have to be added, but we can get an extra 3 kg by removing one of the three Cu damper segments (and rearranging the other two).
 * Built and installed three LBB blade units.
 * Kept debugging the SF LVDT. We repaired several broken wires, but it's still not behaving correctly.
==== Plan for week of 9/4 ====
Mark, Fabian, Enzo (Tue-Fri), Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun (Thu, Fri)
 * Retrieve PEEK piece from BF.
 * Crane SF back in.
 * Suspend BF/IRM/IM/RM/BS.
 * Test SF FR.
 * Calibrate SF LVDT.
 * Install SF cap; route cables.
 * Lift and weigh SF/BF/IRM/IM/RM/BS.
 * Adjust SF ballast.
Line 16: Line 30:
==== Plan for coming weeks ====
For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]].
==== Plan for week of 9/13 ====
Mark (except Wed), Fabian (except ASJ), Enzo, Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun
 * Prepare magnet ring.
 * Bring in PI.
 * Route cables.
 * Suspend SF/..., adjust tilt of SF and total mass.
 * Adjust damper gap.
  
Line 19: Line 39:
Week of 5/1:
 * No activity (Golden Week).

Week of 5/8:
 * Work from Tuesday.
 * Remove PI temporarily.
 * Add magnets to upper SF damper ring.
 * Reinstall PI with damper ring.
 * Reinstall PI-SF rod, this time with hex cable clamp.
 * Install PI yaw stepper.
 * Wire up PI yaw and vertical steppers.
 * Route cables from SF to PI (may involve removing part of Cu damper).
==== Vacation Info ====
Mark: 10/16-24

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):

  • We craned out the SF temporarily and retrieved the lost PEEK cable clamp collet from the BF.
  • We installed the BF.
  • We routed cables from the BF via the hex cable clamp to the SF level.
  • We adjusted the BF trim mass for pitch, roll and vertical, and got the IRM hanging symmetrically around the IM.
  • We adjusted all the IRM OSEMs laterally and in/out.
  • We calibrated the SF LVDT and tested the SF FR stepper.
  • We suspended the SF/... section and weighed it but found the old 7-mm maraging rod adapter did not hold it at the center, so we chad to lift it with slings and could not accurately trim it for pitch/roll.
  • We craned in the PI with the SF damper ring hanging from it.
  • We suspended the SF successfully from the PI and unlocked the F0 keystone to check the mass budget. We needed about 1.5 kg extra, which is about right.
  • However we had to leave out the F0-SF hex cable clamp because of a bad thread on the inside of the cap. Hirata-san will make a new cap by enlarging the 7-mm hole in an old cap to 8 mm.

Plan for week of 9/4

Mark, Fabian, Enzo (Tue-Fri), Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun (Thu, Fri)

  • Retrieve PEEK piece from BF.
  • Crane SF back in.
  • Suspend BF/IRM/IM/RM/BS.
  • Test SF FR.
  • Calibrate SF LVDT.
  • Install SF cap; route cables.
  • Lift and weigh SF/BF/IRM/IM/RM/BS.
  • Adjust SF ballast.

Plan for week of 9/13

Mark (except Wed), Fabian (except ASJ), Enzo, Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun

  • Prepare magnet ring.
  • Bring in PI.
  • Route cables.
  • Suspend SF/..., adjust tilt of SF and total mass.
  • Adjust damper gap.

Vacation Info

Mark: 10/16-24

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)