At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san):
Line 9: Line 8:
 * Craned in the PI.
 * Assembled the thrust bearing holder that receives the PI-SF rod. (It originally had a burr that prevented the bearing from seating properly, and so required filing and re-cleaning.)
 * Hooked the SF and lowered the jacks under the SF to suspend the SF/... section.
 * The top filter rose when unlocked, and required about 1.8 kg to send it back down. Therefore we may be OK - the top filter seems to have about 8 kg more capacity than as measured by G&M. The hex cable clamp (≈0.25 kg) and the cables between the PI and SF still have to be added, but we can get an extra 3 kg by removing one of the three Cu damper segments (and rearranging the other two).
 * Built and installed three LBB blade units.
 * Kept debugging the SF LVDT. We repaired several broken wires, but it's still not behaving correctly.
 * Mark analyzed the QPD data from Friday 12/1 and derived matrices to diagonalize the QPD, and calibrate output in µrad. In the process an error in the IM OSEM diagonalization was discovered: the P and Y gains were low by a factor 2.
 * Mark re-zeroed the QPD after noting the micrometer readings so we can do TFs over the weekend.
 * We prepared for the SR2 gluing:
  * We aligned the SR2 in the box with the wedge on the correct side.
  * We checked that the remachined BS prism holders fit on the PR2 mirror box.
  * We checked that with Tatsumi-san's support ring, the prisms would go on at the right height.
  * We checked the new magnet jigs.
 * We glued ferromagnetic disks in a large number of IM flag tips and flag bases, and in the SR magnet jigs.
 * We also glued SR magnets in the magnet bases.
Line 16: Line 18:
==== Plan for coming weeks ====
For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]].
==== Plan for week of 12/11
 * Mark, Fabian, Enzo, Kozu-kun (Mon-Thu only), Hirata-san, Shoda-san at Kamioka.
 * Mirror gluing.
 * IM assembly and pico test.
 * Assembly frame alignment and optical table centering.
 * Move trolley system from SR3.
 * OL setup.
Line 19: Line 26:
Week of 5/1:
 * No activity (Golden Week).
==== Plan for week of 12/18 ====
 * Shoda-san vacation
 * Mark, Fabian, Enzo, Kozu-kun at Kamioka Mon-Wed.
Line 22: Line 30:
Week of 5/8:
 * Work from Tuesday.
 * Remove PI temporarily.
 * Add magnets to upper SF damper ring.
 * Reinstall PI with damper ring.
 * Reinstall PI-SF rod, this time with hex cable clamp.
 * Install PI yaw stepper.
 * Wire up PI yaw and vertical steppers.
 * Route cables from SF to PI (may involve removing part of Cu damper).
==== Vacation Info ====
 * Mark 12/22-1/3
 * Enzo, 12/21-12/27 (but ''not'' 12/28)
 * Fabian 12/22-1/5
 * Hirata-san 12/21-22 (conference)
 * Shoda-san 12/18-21
  

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

  • Mark analyzed the QPD data from Friday 12/1 and derived matrices to diagonalize the QPD, and calibrate output in µrad. In the process an error in the IM OSEM diagonalization was discovered: the P and Y gains were low by a factor 2.
  • Mark re-zeroed the QPD after noting the micrometer readings so we can do TFs over the weekend.
  • We prepared for the SR2 gluing:
    • We aligned the SR2 in the box with the wedge on the correct side.
    • We checked that the remachined BS prism holders fit on the PR2 mirror box.
    • We checked that with Tatsumi-san's support ring, the prisms would go on at the right height.
    • We checked the new magnet jigs.
  • We glued ferromagnetic disks in a large number of IM flag tips and flag bases, and in the SR magnet jigs.
  • We also glued SR magnets in the magnet bases.

==== Plan for week of 12/11

  • Mark, Fabian, Enzo, Kozu-kun (Mon-Thu only), Hirata-san, Shoda-san at Kamioka.
  • Mirror gluing.
  • IM assembly and pico test.
  • Assembly frame alignment and optical table centering.
  • Move trolley system from SR3.
  • OL setup.

Plan for week of 12/18

  • Shoda-san vacation
  • Mark, Fabian, Enzo, Kozu-kun at Kamioka Mon-Wed.

Vacation Info

  • Mark 12/22-1/3
  • Enzo, 12/21-12/27 (but not 12/28)

  • Fabian 12/22-1/5
  • Hirata-san 12/21-22 (conference)
  • Shoda-san 12/18-21