Size: 1534
Comment:
|
Size: 2774
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 6: | Line 6: |
==== Past week report ==== At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san): |
==== Report for week of 2/26 ==== * We routed all the cables from the BF level up via the flying saucer to the SF. * Hirata-san tried filing the SF cap to improve the fit, but without much success. * Hirata-san installed the Cu segments and cable clamps on the SF cap and the SF LVDT and FR cables. * We cabled and tested the BF cap picos and the SF LVDT and FR. (The LVDT still needs a full calibration.) * We worked on recovering the IM OSEM alignment. |
Line 9: | Line 13: |
* Craned in the PI. * Assembled the thrust bearing holder that receives the PI-SF rod. (It originally had a burr that prevented the bearing from seating properly, and so required filing and re-cleaning.) * Hooked the SF and lowered the jacks under the SF to suspend the SF/... section. * The top filter rose when unlocked, and required about 1.8 kg to send it back down. Therefore we may be OK - the top filter seems to have about 8 kg more capacity than as measured by G&M. The hex cable clamp (≈0.25 kg) and the cables between the PI and SF still have to be added, but we can get an extra 3 kg by removing one of the three Cu damper segments (and rearranging the other two). * Built and installed three LBB blade units. * Kept debugging the SF LVDT. We repaired several broken wires, but it's still not behaving correctly. |
==== Plan for week of 2/26 ==== * Shoda-san at Mitaka. * - * Enzo at Mitaka Mon 2/26. * '''Remove LBB temporary ballast masses from BS chamber.''' * Route cables up to under SF. * Check/adjust total mass and balance of BF/... section, especially IM OSEMs. * Cable and calibrate SF LVDT. * Add Cu segments to SF cap. * Install cap. * Lift SF/... section and check total mass and balance. |
Line 16: | Line 25: |
==== Plan for coming weeks ==== For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]]. |
==== Plan for week of 3/5 ==== * Shoda-san at Mitaka. * Hirata-san vacation Mon 3/5, then Kamioka * Others at Kamioka. * - * Finish recovering IM OSEM alignment. * Calibrate SF LVDT. * Weigh SF/... section. * Get SRM tank mushroom section installed (Hirata-san, Kimura-san) * Set up for rebuilding of two BFs. |
Line 19: | Line 36: |
Week of 5/1: * No activity (Golden Week). |
==== Plan for week of 3/12 ==== * Shoda-san at Mitaka. * Mark at ASJ (Chiba) Fri, then Mitaka. * Hirata-san vacation Mon 3/5; Kamioka Tue-Thu; Mitaka Fri * Others Kamioka Mon-Thu * Install boxes in SR3 and SRM racks. * Lay SR3 in-air cabling. * Continue rebuild of BFs. |
Line 22: | Line 45: |
Week of 5/8: * Work from Tuesday. * Remove PI temporarily. * Add magnets to upper SF damper ring. * Reinstall PI with damper ring. * Reinstall PI-SF rod, this time with hex cable clamp. * Install PI yaw stepper. * Wire up PI yaw and vertical steppers. * Route cables from SF to PI (may involve removing part of Cu damper). |
==== Plan for week of 3/19 ==== * Mark at LVC meeting * All others at Mitaka * Make two sets of IM OSEMs * Make last in-air pico adapter cable * Make three in-air stepper splitter cables for SR2, SR3 and SRM. * Set up Dummy BS prism removal. ==== Plan for week of 3/26 ==== * Mark vacation. * Shoda-san at Mitaka * Others at Kamioka * -- * F0 Prototype Blade Test * Characterize blades. * Choose best set of three. * Remove cracked blades from filter in SRM area. * Set up test weights in SRM area, first floor. * Remove floor panel in SRM area, second floor. * Install chosen blades. * Measure load capacity. ==== To-Do Lists, Schedule ==== * [[KAGRA/Subgroups/VIS/TypeB/March2018]] * [[KAGRA/Subgroups/VIS/TypeB/April2018]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]] ==== Vacation Info ==== * Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun) * Hirata-san vacation, Mon 3/5. * Fabian vacation, 3/26-4/27 (then gone). |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 2/26
- We routed all the cables from the BF level up via the flying saucer to the SF.
- Hirata-san tried filing the SF cap to improve the fit, but without much success.
- Hirata-san installed the Cu segments and cable clamps on the SF cap and the SF LVDT and FR cables.
- We cabled and tested the BF cap picos and the SF LVDT and FR. (The LVDT still needs a full calibration.)
- We worked on recovering the IM OSEM alignment.
Plan for week of 2/26
- Shoda-san at Mitaka.
- -
- Enzo at Mitaka Mon 2/26.
Remove LBB temporary ballast masses from BS chamber.
- Route cables up to under SF.
- Check/adjust total mass and balance of BF/... section, especially IM OSEMs.
- Cable and calibrate SF LVDT.
- Add Cu segments to SF cap.
- Install cap.
- Lift SF/... section and check total mass and balance.
Plan for week of 3/5
- Shoda-san at Mitaka.
- Hirata-san vacation Mon 3/5, then Kamioka
- Others at Kamioka.
- -
- Finish recovering IM OSEM alignment.
- Calibrate SF LVDT.
- Weigh SF/... section.
- Get SRM tank mushroom section installed (Hirata-san, Kimura-san)
- Set up for rebuilding of two BFs.
Plan for week of 3/12
- Shoda-san at Mitaka.
- Mark at ASJ (Chiba) Fri, then Mitaka.
- Hirata-san vacation Mon 3/5; Kamioka Tue-Thu; Mitaka Fri
- Others Kamioka Mon-Thu
- Install boxes in SR3 and SRM racks.
- Lay SR3 in-air cabling.
- Continue rebuild of BFs.
Plan for week of 3/19
- Mark at LVC meeting
- All others at Mitaka
- Make two sets of IM OSEMs
- Make last in-air pico adapter cable
- Make three in-air stepper splitter cables for SR2, SR3 and SRM.
- Set up Dummy BS prism removal.
Plan for week of 3/26
- Mark vacation.
- Shoda-san at Mitaka
- Others at Kamioka
- --
- F0 Prototype Blade Test
- Characterize blades.
- Choose best set of three.
- Remove cracked blades from filter in SRM area.
- Set up test weights in SRM area, first floor.
- Remove floor panel in SRM area, second floor.
- Install chosen blades.
- Measure load capacity.
To-Do Lists, Schedule
Vacation Info
- Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
- Hirata-san vacation, Mon 3/5.
- Fabian vacation, 3/26-4/27 (then gone).