 * Type B Past Week Summary
  * Flags and metal prisms ordered; expected 5/31.
  * New assembly drawing [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5179| D1605179]] focussing on items not part of main chain (and associated screws):
   * Crane adapter
   * Lower breadboard blade module (with cable clamps)
   * IM-RM safety bar ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5127| D1605127]] from last week now obsolete)
  * 3D assembly changed to have geophones instead of accelerometers (but SRx will probably be per original design - need to revisit circuit diagram)
  * Concept for load gauge adapter decided (reuse crane adapter plate and jacks from below PI; add Misumi crossbars, cleanroom-compatible chain hoist)
  * Concept for second floor of clean booth decided (remove all floor panels; add bridge panels at right angles: [[attachment:BS Cleanbooth.pdf]])
  * Modified drawings for main assembly frame and drawings for most small parts (jack adapters etc) received from Mirapro.
  * Wire sizes decided: 300 µm piano wire and 500 µm tungsten (will revisit this later).
  * Lots of work on [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4817| E1604817]] (Fabian) and [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]] (Mark)
=== Type B (Mark) ===
==== Report for week of 3/5 ====
 * Mark finished -v2 of the schedule ([[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779| L1807779]]).
 * We removed the non-vacuum-compatible ballast mass from the BS tank.
 * We secured all the PR2 feedthrough connections with screws.
 * We grabbed an extra empty rack for SRM and set it up next to the one for SR3 (we will add boxes next week).
 * We calibrated the SR2 SF LVDT sensing and actuation, and the FR.
 * We measured the bounce frequencies of the SF with and without the cap, and the bounce frequency of the BF.
 * We put the SF cap on and lifted and weighed the SF/... section.
 * However we were unhappy with how the cap had to be forced on and off and how it lowered the load capacity (≈-433 g) and resonance frequency (0.271 Hz-> 0.23 Hz).
 * We tried the cap left over from B2-3 used in one of the PRs, which was slightly better but still not great.
 * We measured diameter of the original cap (B2-2) and the new one (B2-3). The original cap was almost exactly 700 mm in internal diameter, and the new one was about 0.2 mm wider.
 * We moved the filter building bench and tools into the SRM area and started the rebuild of the two remaining BFs (the one from the BS Test Hang and the one with the tilted keystone).
 * Mark worked on slides for the ASJ and LVC meetings.
 * The SRM mushroom work was postponed due to other demands on the time of Sawada-san-tachi and Mirapro.

==== Plan for week of 3/12 ====
 * Shoda-san at Mitaka.
 * Mark at ASJ (Chiba) Fri, then Mitaka.
 * Others Kamioka Mon-Thu
 * F2F VIS Meeting and Farewell Party for Fabian at Mitaka on Friday.
 * --
 * Install boxes in SR3 and SRM racks.
 * Lay SR3 in-air cabling.
 * Continue rebuild of BFs.
 * Ship dummy BS to Mitaka.

==== Plan for week of 3/19 ====
 * Fujii-kun and Tanioka-kun join.
 * Mark at LVC meeting
 * Fujii-kun at Kamioka
 * All others at Mitaka
 * --
 * Put four geophones in pods.
 * Make two sets of IM OSEMs
 * Make last in-air pico adapter cable
 * Make three in-air stepper splitter cables for SR2, SR3 and SRM.
 * Set up Dummy BS prism removal.


==== Plan for week of 3/26 ====
 * Mark vacation.
 * Shoda-san at Mitaka
 * Others at Kamioka
 * --
 * SF Check
  * Check load capacity.
  * Check fit of caps.
  * Add cable clamps to bases.
  * Add cable clamps and Cu segments to caps (only if they fit well).
  * Cable LVDTs and steppers.

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/March2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/April2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]]

==== Vacation Info ====
 * Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
 * Hirata-san vacation, Mon 3/5.
 * Fabian vacation, 3/26-4/27 (then gone).

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 3/5

  • Mark finished -v2 of the schedule (L1807779).

  • We removed the non-vacuum-compatible ballast mass from the BS tank.
  • We secured all the PR2 feedthrough connections with screws.
  • We grabbed an extra empty rack for SRM and set it up next to the one for SR3 (we will add boxes next week).
  • We calibrated the SR2 SF LVDT sensing and actuation, and the FR.
  • We measured the bounce frequencies of the SF with and without the cap, and the bounce frequency of the BF.
  • We put the SF cap on and lifted and weighed the SF/... section.
  • However we were unhappy with how the cap had to be forced on and off and how it lowered the load capacity (≈-433 g) and resonance frequency (0.271 Hz-> 0.23 Hz).

  • We tried the cap left over from B2-3 used in one of the PRs, which was slightly better but still not great.
  • We measured diameter of the original cap (B2-2) and the new one (B2-3). The original cap was almost exactly 700 mm in internal diameter, and the new one was about 0.2 mm wider.
  • We moved the filter building bench and tools into the SRM area and started the rebuild of the two remaining BFs (the one from the BS Test Hang and the one with the tilted keystone).
  • Mark worked on slides for the ASJ and LVC meetings.
  • The SRM mushroom work was postponed due to other demands on the time of Sawada-san-tachi and Mirapro.

Plan for week of 3/12

  • Shoda-san at Mitaka.
  • Mark at ASJ (Chiba) Fri, then Mitaka.
  • Others Kamioka Mon-Thu
  • F2F VIS Meeting and Farewell Party for Fabian at Mitaka on Friday.
  • --
  • Install boxes in SR3 and SRM racks.
  • Lay SR3 in-air cabling.
  • Continue rebuild of BFs.
  • Ship dummy BS to Mitaka.

Plan for week of 3/19

  • Fujii-kun and Tanioka-kun join.
  • Mark at LVC meeting
  • Fujii-kun at Kamioka
  • All others at Mitaka
  • --
  • Put four geophones in pods.
  • Make two sets of IM OSEMs
  • Make last in-air pico adapter cable
  • Make three in-air stepper splitter cables for SR2, SR3 and SRM.
  • Set up Dummy BS prism removal.

Plan for week of 3/26

  • Mark vacation.
  • Shoda-san at Mitaka
  • Others at Kamioka
  • --
  • SF Check
    • Check load capacity.
    • Check fit of caps.
    • Add cable clamps to bases.
    • Add cable clamps and Cu segments to caps (only if they fit well).
    • Cable LVDTs and steppers.

To-Do Lists, Schedule

Vacation Info

  • Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
  • Hirata-san vacation, Mon 3/5.
  • Fabian vacation, 3/26-4/27 (then gone).