Line 7: Line 7:
At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san): At Kamioka (Enzo):
 * Enzo (with help from Miyo-kun) fixed the broken actuation coil on PI LVDT #0.
 * Enzo worked on the final cabling plan for BS and SRx.
 * Enzo replaced the LVDT driver again to have one with no dead channels (and free up the partly non-working cards for servicing).
Line 9: Line 12:
 * We craned in the PI.
 * We assembled the thrust bearing holder that receives the PI-SF rod. (The recess for the bearing was very slightly too small and had a burr near a retaining screw hole that prevented the bearing from seating properly, and so it required filing and re-cleaning.)
 * We hooked the SF and lowered the jacks under the SF to suspend the SF/... section.
 * The top filter rose when unlocked, and required about 1.8 kg to send it back down. Therefore we may be OK - the top filter seems to have about 8 kg more capacity than as measured by G&M. The hex cable clamp (≈0.25 kg) and the cables between the PI and SF still have to be added, but we can get an extra 3 kg by removing one of the three Cu damper segments (and rearranging the other two).
 * Hirata-san built and installed three LBB blade units.
 * Enzo kept debugging the SF LVDT. We repaired several broken wires, but it's still not behaving correctly. We suspect the ordering of the three coils (input output and excitation) may not be right. If so, we should be able to fix it with an adapter cable without removing the SF cap.
At Mitaka and Kashiwa (Mark, Hirata-san, Fabian, Enzo):
 * We glued magnets into their holders.
 * We did a walk-through of the gluing procedure at Mitaka and discovered that the secondary prisms were missing.
 * We took the mirror box and gluing tools to Kashiwa to do as much of the gluing as possible.
 * Hirose-san applied First Contact to the BS and he and Kieran moved it into the mirror box.
 * We practiced putting sapphire prisms on the BS but didn't apply glue.
 * We tried the magnet gluing jigs designed by Aso-san and found two major issues: the overall length was about 25 mm too long, and there was no adjustment to allow for the wedge.
 * We designed a simple modification to the jigs that hopefully would be trivial for the ATC to do: the jigs will be cut in half and the bottom section will be mounted with adhesive on an 11 mm rod that slides in the central hole of the top section. Thus the top half can be screwed into the existing recess, and the bottom half with the magnets and glue can be allowed to drop about 3 mm onto the face of the optic. Hirata-san worked with ATC to get this done and it should be ready today (Friday 7/7).
 * Hirata-san also got ATC to make some jigs to hold the old 5-mm prisms so that they can be ground down to 3 mm to replace the missing ones. Hirata-san will do the grinding himself today (Friday 7/7/).
 * We decided to continue the gluing work at Kamioka, so we brought the BS back to Mitaka and will ship it on to Kamioka next Tuesday.
 * Hirata-san did a version of the 3D CAD with the as-built BS Test Hang configuration.
Line 16: Line 24:
==== Plan for coming weeks ====
For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]].
==== Plan for weeks of 7/10, 7/17 ====
Mark, Enzo mostly at Kamioka.
 * More TFs.
 * Receive BS at Kamioka, do gluing if possible.
 * Document LVDT driver rebuild and other changes.
 * Learn how Miyo-kun's pico driver software works and make fixes/improvements.
 * Design/install matrices, blend filters and damping filters.
 * Finish tidying rack and labeling cables.
 * Add temporary ballast to LBB and find total required.
 * Try rearranging arc weights to make room for magic wand.
 * Start on creating SR3 rack.
 * Preparation for BF rebuild.
 
Fabian, Hirata-san at Mitaka.
 * Clean BS secondary prisms and modified gluing jigs (Hirata-san).
 * Ship gluing tools and BS to Kamioka.
 * Do new 3D CAD for final BS install (Hirata-san):
  * On-assembly-frame version.
  * In-tank version.
 * Design SR assembly frame (Fabian).
 * Do 2D Drawings and procurement of final IM/BF/SF ballast masses (Hirata-san).
 * Other purchasing and preparation (spare BS clamps, suspension wire, 8-mm rod receptacles)
 * Do mass budget for LBB - design ballast masses (Fabian)
Line 19: Line 48:
Week of 5/1:
 * No activity (Golden Week).

Week of 5/8:
 * Commence work Tuesday 5/9.
 * Remove PI temporarily.
 * Continue debugging SF LVDT (removing cap if necessary).
 * Investigate possible mis-alignment between the tips of the LBB blades and the holes for the rods going down to the damper ring.
 * Add magnets to upper SF damper ring.
 * Reinstall PI, this time with rods and damper ring.
 * Reinstall PI-SF rod, this time with hex cable clamp.
 * Install PI yaw stepper.
 * Wire up PI yaw stepper and vertical fishing-rod steppers.
 * Route cables from SF to PI (may involve removing part of Cu damper).

Week of 5/15:
 * Enzo from Tuesday 5/16 (driving test), rest of team from Monday.
 * Prepare for PR2 bellows removal on 5/15 (move table with tools).
 * Wire up PI horizontal LVDTs and steppers.
 * Install geophones.
 * Unlock IP, re-level PI to center PI, add arc weights as required.
 
Vacation Info:
Hirata-san: Thu 7/20 through Mon 7/24
Enzo: Sat 7/22 through Sun 8/6
Fabian: Fri 8/4 through Mon 8/21
Mark: TBD Mid-Oct

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Enzo):

  • Enzo (with help from Miyo-kun) fixed the broken actuation coil on PI LVDT #0.
  • Enzo worked on the final cabling plan for BS and SRx.
  • Enzo replaced the LVDT driver again to have one with no dead channels (and free up the partly non-working cards for servicing).

At Mitaka and Kashiwa (Mark, Hirata-san, Fabian, Enzo):

  • We glued magnets into their holders.
  • We did a walk-through of the gluing procedure at Mitaka and discovered that the secondary prisms were missing.
  • We took the mirror box and gluing tools to Kashiwa to do as much of the gluing as possible.
  • Hirose-san applied First Contact to the BS and he and Kieran moved it into the mirror box.
  • We practiced putting sapphire prisms on the BS but didn't apply glue.
  • We tried the magnet gluing jigs designed by Aso-san and found two major issues: the overall length was about 25 mm too long, and there was no adjustment to allow for the wedge.
  • We designed a simple modification to the jigs that hopefully would be trivial for the ATC to do: the jigs will be cut in half and the bottom section will be mounted with adhesive on an 11 mm rod that slides in the central hole of the top section. Thus the top half can be screwed into the existing recess, and the bottom half with the magnets and glue can be allowed to drop about 3 mm onto the face of the optic. Hirata-san worked with ATC to get this done and it should be ready today (Friday 7/7).
  • Hirata-san also got ATC to make some jigs to hold the old 5-mm prisms so that they can be ground down to 3 mm to replace the missing ones. Hirata-san will do the grinding himself today (Friday 7/7/).
  • We decided to continue the gluing work at Kamioka, so we brought the BS back to Mitaka and will ship it on to Kamioka next Tuesday.
  • Hirata-san did a version of the 3D CAD with the as-built BS Test Hang configuration.

Plan for weeks of 7/10, 7/17

Mark, Enzo mostly at Kamioka.

  • More TFs.
  • Receive BS at Kamioka, do gluing if possible.
  • Document LVDT driver rebuild and other changes.
  • Learn how Miyo-kun's pico driver software works and make fixes/improvements.
  • Design/install matrices, blend filters and damping filters.
  • Finish tidying rack and labeling cables.
  • Add temporary ballast to LBB and find total required.
  • Try rearranging arc weights to make room for magic wand.
  • Start on creating SR3 rack.
  • Preparation for BF rebuild.

Fabian, Hirata-san at Mitaka.

  • Clean BS secondary prisms and modified gluing jigs (Hirata-san).
  • Ship gluing tools and BS to Kamioka.
  • Do new 3D CAD for final BS install (Hirata-san):
    • On-assembly-frame version.
    • In-tank version.
  • Design SR assembly frame (Fabian).
  • Do 2D Drawings and procurement of final IM/BF/SF ballast masses (Hirata-san).
  • Other purchasing and preparation (spare BS clamps, suspension wire, 8-mm rod receptacles)
  • Do mass budget for LBB - design ballast masses (Fabian)

Vacation Info: Hirata-san: Thu 7/20 through Mon 7/24 Enzo: Sat 7/22 through Sun 8/6 Fabian: Fri 8/4 through Mon 8/21 Mark: TBD Mid-Oct