At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san): At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):
 * We disconnected the SF/... section and reinstalled the F0-SF rod with the hex cable clamp attached.
 * We debugged an issue with the actuation (the real-time model needed rebooting).
 * We routed all the SF/... cables up to the bottom of the PI, and then to the feedthroughs.
 * We unlocked the F0 keystone and experimented to find the amount of mass needed on the SF (≈845 g).
 * We attached the SF trim mass, adjusting it laterally so that the SF was level in pitch and roll.
 * We corrected some errors on the MEDM screens (some broken links and Take/Restore Safe.snap buttons).
 * We cabled all the PI items through to the rack and did very basic testing.
 * We disconnected the security structure from the assembly frame and adjusted the PI till the SS was vertical.
 * We unlocked the IP and adjusted the PI jacks and FRs till the IP was centered.
 * We passed the halves of the LBB Cu damping ring (less the Cu) into the chamber and joined them.
 * We put the magnets on the LBB damper ring using the template.
 * We locked various combinations of keystones and measured the vertical resonance frequencies of the unlocked filters.
 * We spent time on getting the geophones working. The original descrambler adapters had gone missing, so Enzo created three new ones. We borrowed a cable to replace one that had broken. The geophone distributor (S1402167) failed (no power on the negative rail), and a replacement borrowed from SR3 (S1605513) kept switching off.
Line 9: Line 22:
 * We craned in the PI.
 * We assembled the thrust bearing holder that receives the PI-SF rod. (The recess for the bearing was very slightly too small and had a burr near a retaining screw hole that prevented the bearing from seating properly, and so it required filing and re-cleaning.)
 * We hooked the SF and lowered the jacks under the SF to suspend the SF/... section.
 * The top filter rose when unlocked, and required about 1.8 kg to send it back down. Therefore we may be OK - the top filter seems to have about 8 kg more capacity than as measured by G&M. The hex cable clamp (≈0.25 kg) and the cables between the PI and SF still have to be added, but we can get an extra 3 kg by removing one of the three Cu damper segments (and rearranging the other two).
 * Hirata-san built and installed three LBB blade units.
 * Enzo kept debugging the SF LVDT. We repaired several broken wires, but it's still not behaving correctly. We suspect the ordering of the three coils (input output and excitation) may not be right. If so, we should be able to fix it with an adapter cable without removing the SF cap.
==== Plan for week of 9/13 ====
==== Plan for week of 9/19 ====
No work Mon 9/18 (敬老の日)<<BR>>
Mark, Fabian, Enzo, Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Thu, Fri), Kozu-kun
 * Install LBB damper magnet rings in tank.
 * Remove tank lid.
 *
 * Install suspension.
Line 16: Line 31:
==== Plan for coming weeks ====
For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]].

Week of 5/1:
 * No activity (Golden Week).

Week of 5/8:
 * Commence work Tuesday 5/9.
 * Remove PI temporarily.
 * Continue debugging SF LVDT (removing cap if necessary).
 * Investigate possible mis-alignment between the tips of the LBB blades and the holes for the rods going down to the damper ring.
 * Add magnets to upper SF damper ring.
 * Reinstall PI, this time with rods and damper ring.
 * Reinstall PI-SF rod, this time with hex cable clamp.
 * Install PI yaw stepper.
 * Wire up PI yaw stepper and vertical fishing-rod steppers.
 * Route cables from SF to PI (may involve removing part of Cu damper).

Week of 5/15:
 * Enzo from Tuesday 5/16 (driving test), rest of team from Monday.
 * Prepare for PR2 bellows removal on 5/15 (move table with tools).
 * Wire up PI horizontal LVDTs and steppers.
 * Install geophones.
 * Unlock IP, re-level PI to center PI, add arc weights as required.
 
==== Vacation Info ====
Mark: 10/16-24

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):

  • We disconnected the SF/... section and reinstalled the F0-SF rod with the hex cable clamp attached.
  • We debugged an issue with the actuation (the real-time model needed rebooting).
  • We routed all the SF/... cables up to the bottom of the PI, and then to the feedthroughs.
  • We unlocked the F0 keystone and experimented to find the amount of mass needed on the SF (≈845 g).
  • We attached the SF trim mass, adjusting it laterally so that the SF was level in pitch and roll.
  • We corrected some errors on the MEDM screens (some broken links and Take/Restore Safe.snap buttons).
  • We cabled all the PI items through to the rack and did very basic testing.
  • We disconnected the security structure from the assembly frame and adjusted the PI till the SS was vertical.
  • We unlocked the IP and adjusted the PI jacks and FRs till the IP was centered.
  • We passed the halves of the LBB Cu damping ring (less the Cu) into the chamber and joined them.
  • We put the magnets on the LBB damper ring using the template.
  • We locked various combinations of keystones and measured the vertical resonance frequencies of the unlocked filters.
  • We spent time on getting the geophones working. The original descrambler adapters had gone missing, so Enzo created three new ones. We borrowed a cable to replace one that had broken. The geophone distributor (S1402167) failed (no power on the negative rail), and a replacement borrowed from SR3 (S1605513) kept switching off.

Plan for week of 9/13

Plan for week of 9/19

No work Mon 9/18 (敬老の日)
Mark, Fabian, Enzo, Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Thu, Fri), Kozu-kun

  • Install LBB damper magnet rings in tank.
  • Remove tank lid.
  • Install suspension.