Line 7: Line 7:
At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san): At Kamioka (Mark, Ohishi-san, Enzo, Yoshioka-kun, Kozu-kun):
 * We removed the LBB damper rings from the tank and passed them to Takahashi-san for recleaning. Unfortunately two screws galled, one holding on a Cu segment, and one holding on a joint piece.
 * We removed the LBB blade units from the PI, removed the blades and shipped them off for rework.
 * We pulled out all the old in-air cabling.
 * We laid about 9 new in-air cables.
 * We wrapped/labelled the BS mirror box, the winch system, the trolley adapters, and many other tools that we do not expect to use any time soon.
 * We connected up, tested and calibrated the BF LVDT.
 * We adjusted the ballast mass on the IM to make it hang level and at the right height. However we had to reduce the weight by a further 686 g relative to the plan of 2017-08-09. We found a combination that was good except for the fact that it used round masses on the bottom corners, so we decided to have the 641 g rectangular masses cut down by 60 g each. Mesco was able to do this within 24 hours. We will reclean the parts on Friday afternoon and swap them in on Monday.
At Mitaka (Hirata-san:
 * Hirata-san got a quotation about optical bench from Mirapro and contacted them about reducing cost.
 * He asked Suzuki-san (Tokyo university) to order them (delivery date is 10/24, so far).
 * He modified SR assembly frame design (from Fabian) and asked Mirapro for quotation.
 * He liaised with Koshin-shoko about modification of BS LBB blade springs.
 * He asked ATC for making t4.5 ballast mass for PR. He washed them and sent them to Kamioka with the PR thrust bearing.
 * He worked on the 3D model of SR3 SUS wires, and making a list for quotation.
Line 9: Line 23:
 * We counted the used/broken/unused/need cables for Type B.
 * Hirata-san and Mark installed blades in three LBB blade units.
 * Hirata-san checked the LBB blade units to see how badly the blade tips were misaligned. The bases will need to be moved towards the clamp end by 21 mm. It is probably not feasible to turn the screw holes into slots, so an adapter part will need to be designed.
 * We checked that the new in-vacuum geophone cables that Takahashi-san had got for us were the proper new-style ones. (Thus we will need in-air descrambler cables.)
 * Shoda-san sent Enzo a document by Joris on the tuning of the LVDTs, so he stated working through it. He also researched the specifications of all the coils (PI and SF as well as BF.)
 * We found the damper magnets and the template for placing the magnets on the ring for the SF.
 * Hirata-san installed and wired up the PI yaw stepper. The vertical stepper still needs wiring, and the horizontal stepper wiring needs to be made vacuum-compatible.
 * We installed safety bars on the ±X side of the assembly frame about 3 m off the floor, so they are at waist height for a person standing on one of the tall ladders. The one on the +X side will be very good for safety where it is, but the one on the -X side will need re-doing: it is too close and not very securely attached because of interference from vacuum pump cabling.
 * We unlocked the inverted pendulum and experimented with adding weight. It was still stable with 4 layers of arc weights.
 * We also experimented with getting both the IP centered and the security structure vertical (so that the suspension hang centrally within it). We managed to get it all right with a combination of leveling the PI with the jacks and moving the IP with the fishing rods.
 * Adjusting the verticality of the SS had left the bottom of it off-center in the assembly frame, so we picked the entire system up with the crane and moved it in +Y and -X a few mm to re-center it.
 * We started to remove the PI so we could do various adjustments (check the SF LVDT, reconfigure the Cu damper, add the hex cable clamp on the rod and hang the magnet disk for the SF damper) but gave up when the PI-SF jammed in the SF.
==== Plan for week of 8/21 ====
Vacation: Fabian (Mon)<<BR>>
Internship: Kozu-kun (Mon-Fri)<<BR>>
Line 22: Line 27:
Kamioka: Mark, Ohishi, Fabian (Tue-Fri), Enzo, Yoshioka-kun (Tue, Wed, Fri).
 * Swap in new IM ballast masses; readjust height and levelness.
 * Install side panels of IRM and OSEMs.
 * Route IRM OSEM cables, test/adjust IRM OSEMs.
 * Add BF cap; cable and test BF-1 and BF-2 picos.
 * Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass.
 * Crane in SF.
 * Try TFs with optical sensors.
Mitaka: Hirata-san.
 * SR stuff.
Line 23: Line 38:
==== Plan for coming weeks ====
For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]].
==== Plan for week of 8/28 ====
Kamioka: Mark, Ohishi, Fabian, Enzo, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun.
 *
Line 26: Line 42:
Week of 5/15:
 * Enzo from Tuesday 5/16 (driving test), rest of team from Monday.
 * Fix PI-SF rod jamming.
 * Remove PI and SF cap.
 * Continue debugging SF LVDT.
 * Reconfigure Cu damper ring on SF.
 * Add magnets to upper SF damper ring.
 * Add cable clamps on the PI (a few places are inaccessible when the PI is on the assembly frame).
 * Reinstall PI, this time with rods and damper ring.
 * Reinstall PI-SF rod, this time with hex cable clamp.
 * Prepare for PR2 bellows removal on 5/15 (move table with tools).
 * Cable/test PI horizontal LVDTs and steppers.
 * Install/cable/test geophones.
 
==== Vacation Info ====
Fabian: Fri 8/4 through Mon 8/21
Mark: TBD Mid-Oct

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Ohishi-san, Enzo, Yoshioka-kun, Kozu-kun):

  • We removed the LBB damper rings from the tank and passed them to Takahashi-san for recleaning. Unfortunately two screws galled, one holding on a Cu segment, and one holding on a joint piece.
  • We removed the LBB blade units from the PI, removed the blades and shipped them off for rework.
  • We pulled out all the old in-air cabling.
  • We laid about 9 new in-air cables.
  • We wrapped/labelled the BS mirror box, the winch system, the trolley adapters, and many other tools that we do not expect to use any time soon.
  • We connected up, tested and calibrated the BF LVDT.
  • We adjusted the ballast mass on the IM to make it hang level and at the right height. However we had to reduce the weight by a further 686 g relative to the plan of 2017-08-09. We found a combination that was good except for the fact that it used round masses on the bottom corners, so we decided to have the 641 g rectangular masses cut down by 60 g each. Mesco was able to do this within 24 hours. We will reclean the parts on Friday afternoon and swap them in on Monday.

At Mitaka (Hirata-san:

  • Hirata-san got a quotation about optical bench from Mirapro and contacted them about reducing cost.
  • He asked Suzuki-san (Tokyo university) to order them (delivery date is 10/24, so far).
  • He modified SR assembly frame design (from Fabian) and asked Mirapro for quotation.
  • He liaised with Koshin-shoko about modification of BS LBB blade springs.
  • He asked ATC for making t4.5 ballast mass for PR. He washed them and sent them to Kamioka with the PR thrust bearing.
  • He worked on the 3D model of SR3 SUS wires, and making a list for quotation.

Plan for week of 8/21

Vacation: Fabian (Mon)
Internship: Kozu-kun (Mon-Fri)

Kamioka: Mark, Ohishi, Fabian (Tue-Fri), Enzo, Yoshioka-kun (Tue, Wed, Fri).

  • Swap in new IM ballast masses; readjust height and levelness.
  • Install side panels of IRM and OSEMs.
  • Route IRM OSEM cables, test/adjust IRM OSEMs.
  • Add BF cap; cable and test BF-1 and BF-2 picos.
  • Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass.
  • Crane in SF.
  • Try TFs with optical sensors.

Mitaka: Hirata-san.

  • SR stuff.

Plan for week of 8/28

Kamioka: Mark, Ohishi, Fabian, Enzo, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun.