==== Past week report ====
At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san):
==== Report for week of 1/29 ====
 * Mark made two sets of in-air pico splitter cables (each with a triple for IM and a double for BF) for SR2 and SR3.
 * Fabian, Hirata-san and Kozu-kun worked on cabling and testing the IM pitch/roll/yaw picos, the BF FR and the BF LVDT. The LVDT connections were initially unreliable and Hirata-san had to redo the pins on the coil wires.
 * Fabian installed ballast masses in the BF.
 * Mark worked on schedule.
 * Mark did inventory of the stepper motor drivers (many were not accounted for on the wiki and/or JGWDoc and one is missing) and reserved two for SR3.
 * We emptied out the external cleanroom in preparation for installing SS sheet.
Line 9: Line 14:
 * We counted the used/broken/unused/need cables for Type B.
 * Hirata-san and Mark installed blades in three LBB blade units.
 * Hirata-san checked the LBB blade units to see how badly the blade tips were misaligned. The bases will need to be moved towards the clamp end by 21 mm. It is probably not feasible to turn the screw holes into slots, so an adapter part will need to be designed.
 * We checked that the new in-vacuum geophone cables that Takahashi-san had got for us were the proper new-style ones. (Thus we will need in-air descrambler cables.)
 * Shoda-san sent Enzo a document by Joris on the tuning of the LVDTs, so he stated working through it. He also researched the specifications of all the coils (PI and SF as well as BF.)
 * We found the damper magnets and the template for placing the magnets on the ring for the SF.
 * Hirata-san installed and wired up the PI yaw stepper. The vertical stepper still needs wiring, and the horizontal stepper wiring needs to be made vacuum-compatible.
 * We installed safety bars on the ±X side of the assembly frame about 3 m off the floor, so they are at waist height for a person standing on one of the tall ladders. The one on the +X side will be very good for safety where it is, but the one on the -X side will need re-doing: it is too close and not very securely attached because of interference from vacuum pump cabling.
 * We unlocked the inverted pendulum and experimented with adding weight. It was still stable with 4 layers of arc weights.
 * We also experimented with getting both the IP centered and the security structure vertical (so that the suspension hang centrally within it). We managed to get it all right with a combination of leveling the PI with the jacks and moving the IP with the fishing rods.
 * Adjusting the verticality of the SS had left the bottom of it off-center in the assembly frame, so we picked the entire system up with the crane and moved it in +Y and -X a few mm to re-center it.
 * We started to remove the PI so we could do various adjustments (check the SF LVDT, reconfigure the Cu damper, add the hex cable clamp on the rod and hang the magnet disk for the SF damper) but gave up when the PI-SF jammed in the SF.
==== Plan for week of 2/13 ====
 * No work Monday (建国記念の日の振替休日)
 * Enzo on vacation
 * Hirata-san at Mitaka Tue (self-evaluation interview).
 * Shoda-san at Mitaka.
 * All others at Kamioka.
 * -
 * Build IRM around IM.
 * Cable/test/adjust IM OSEMs.
 * Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw.
Line 22: Line 25:
==== Plan for week of 2/19 ====
 * Enzo back from Tuesday.
 * Shoda-san at Mitaka.
 * Hirata-san at Mitaka Mon+Tue (to receive and wash parts).
 * All others at Kamioka.
 * -
 * Lift BF/... section and check total mass and balance.
 * Cable and test BF picos.
 * Add section of SS up to SF ring.
 * Bring in SF.
 * Hook BF/... section.
 * Route cables up to under SF.
 * Check/adjust total mass of BF/... section.
Line 23: Line 39:
==== Plan for coming weeks ====
For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]].
==== Plan for week of 2/26 ====
 * Shoda-san at Mitaka.
 * -
 * Add Cu segments to SF cap.
 * Lift SF/... section and check total mass and balance.
Line 26: Line 45:
Week of 5/15:
 * Enzo from Tuesday 5/16 (driving test), rest of team from Monday.
 * Fix PI-SF rod jamming.
 * Remove PI and SF cap.
 * Continue debugging SF LVDT.
 * Reconfigure Cu damper ring on SF.
 * Add magnets to upper SF damper ring.
 * Add cable clamps on the PI (a few places are inaccessible when the PI is on the assembly frame).
 * Reinstall PI, this time with rods and damper ring.
 * Reinstall PI-SF rod, this time with hex cable clamp.
 * Prepare for PR2 bellows removal on 5/15 (move table with tools).
 * Cable/test PI horizontal LVDTs and steppers.
 * Install/cable/test geophones.
 
==== Vacation Info ====
 * Enzo 1/30-2/19.
 * Fabian 4/2-4/27 vacation (then gone).

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 1/29

  • Mark made two sets of in-air pico splitter cables (each with a triple for IM and a double for BF) for SR2 and SR3.
  • Fabian, Hirata-san and Kozu-kun worked on cabling and testing the IM pitch/roll/yaw picos, the BF FR and the BF LVDT. The LVDT connections were initially unreliable and Hirata-san had to redo the pins on the coil wires.
  • Fabian installed ballast masses in the BF.
  • Mark worked on schedule.
  • Mark did inventory of the stepper motor drivers (many were not accounted for on the wiki and/or JGWDoc and one is missing) and reserved two for SR3.
  • We emptied out the external cleanroom in preparation for installing SS sheet.

Plan for week of 2/13

  • No work Monday (建国記念の日の振替休日)
  • Enzo on vacation
  • Hirata-san at Mitaka Tue (self-evaluation interview).
  • Shoda-san at Mitaka.
  • All others at Kamioka.
  • -
  • Build IRM around IM.
  • Cable/test/adjust IM OSEMs.
  • Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw.

Plan for week of 2/19

  • Enzo back from Tuesday.
  • Shoda-san at Mitaka.
  • Hirata-san at Mitaka Mon+Tue (to receive and wash parts).
  • All others at Kamioka.
  • -
  • Lift BF/... section and check total mass and balance.
  • Cable and test BF picos.
  • Add section of SS up to SF ring.
  • Bring in SF.
  • Hook BF/... section.
  • Route cables up to under SF.
  • Check/adjust total mass of BF/... section.

Plan for week of 2/26

  • Shoda-san at Mitaka.
  • -
  • Add Cu segments to SF cap.
  • Lift SF/... section and check total mass and balance.

Vacation Info

  • Enzo 1/30-2/19.
  • Fabian 4/2-4/27 vacation (then gone).