Differences between revisions 142 and 185 (spanning 43 versions)
Revision 142 as of 2017-05-18 17:18:39
Size: 2573
Editor: MarkBarton
Comment:
Revision 185 as of 2017-09-01 14:32:36
Size: 2339
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 7: Line 7:
At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san): At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):
 * We solved the problem with the OSEMs: cables had been plugged into the confusingly named "PD current monitor" outputs (actually LED current monitors), not the "OSEM outputs".
 * We solved a problem with the real-time model freezing which turned out to be the IO chassis having lost power.
 * We took some mass off the IM to allow for the weight of the cables, and readjusted it in pitch and roll.
 * We aligned the IRM to the IM and set the OSEMs to mid-range.
 * We added ballast to the BF.
 * We changed the receptacles for the SF-BF rod. The low receptacle did not fit properly into the BF keystone and Hirata-san had to file it.
 * We fixed a broken wire on the BF yaw pico, retested the pico and added the BF cap.
 * We cabled and tested the BF cap picos.
 * We lifted the BF and weighed and balanced it.
 * We installed the SF ring and brought in the SF.
 * We installed the Cu segments on the SF.
 * We cabled the SF LVDT and did a quick test (not a full calibration).
 * We replaced non-vacuum compatible cables in the PI, removed various sticky labels and wiped it with ethanol.
 * We tried to hook the SF-BF rod but found the hole in the hex cable clamp was too small for the 8 mm rod head. We enlarged the hole but then found the PEEK pieces were too loose. We tried using foil, but then managed to lose a PEEK piece into the BF, so we will need to remove the cap of the BF to get it.
Line 9: Line 23:
 * We removed the PI from the assembly frame.
 * We encountered a problem with the PI-SF rod jamming in the SF. We finally got it out by clamping a pig of vice grips to the rod and hammering. We found that the receptacle part was the right size (7.0 mm) but had been deformed around the edge. Hirata-san used a knife and sandpaper to lean up the edge and then ultrasonically cleaned it.
 * We cleared space for the PR2 team to remove a bellows from their tank.
 * We installed safety bars near the assembly frame at about waist height for someone on the tall ladder. We reinforced the clamps with cable ties.
 * We removed the LLB blade units from the PI, removed the blades from the clamps and sent the blades away for more rework to fix the length problem. Fortunately the tab section at the tip is fairly long, so we can just add a second hole further from the end.
 * We removed the SF cap and stored it on crossbars within the assembly frame.
 * We tested the SR fishing rod again, but it would only go up, not down. We found that reseting the driver fixed it, but we also moved the driver boxes into the cleanbooth to reduce the length of the motor cables. (Instead, we had to run some long DC and LAN cables.)
 * We adjusted the limit nut on the SF fishing rod to increase the range.
 * We removed one segment of the Cu ring on the SF cap and reconfigured the rest to be symmetrical.
 * Fabian designed a layout for the SF damper ring magnets that would work with the modified Cu ring, and placed the magnets with the template. The poles of the magnets were not on the expected faces so we had to stand the magnets up with the ,
==== Plan for week of 9/4 ====
Mark, Fabian, Enzo (Tue-Fri), Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun (Thu, Fri)
 * Retrieve PEEK piece from BF.
 * Crane SF back in.
 * Suspend BF/IRM/IM/RM/BS.
 * Test SF FR.
 * Calibrate SF LVDT.
 * Install SF cap; route cables.
 * Lift and weigh SF/BF/IRM/IM/RM/BS.
 * Adjust SF ballast.
Line 20: Line 34:
==== Plan for week of 9/13 ====
Mark (except Wed), Fabian (except ASJ), Enzo, Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun
 * Prepare magnet ring.
 * Bring in PI.
 * Route cables.
 * Suspend SF/..., adjust tilt of SF and total mass.
 * Adjust damper gap.
  
Line 21: Line 43:
==== Plan for coming weeks ====
For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]].

Week of 5/15:
 * Enzo from Tuesday 5/16 (driving test), rest of team from Monday.
 * Fix PI-SF rod jamming.
 * Remove PI and SF cap.
 * Continue debugging SF LVDT.
 * Reconfigure Cu damper ring on SF.
 * Add magnets to upper SF damper ring.
 * Add cable clamps on the PI (a few places are inaccessible when the PI is on the assembly frame).
 * Reinstall PI, this time with rods and damper ring.
 * Reinstall PI-SF rod, this time with hex cable clamp.
 * Prepare for PR2 bellows removal on 5/15 (move table with tools).
 * Cable/test PI horizontal LVDTs and steppers.
 * Install/cable/test geophones.
 
==== Vacation Info ====
Mark: 10/16-24

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):

  • We solved the problem with the OSEMs: cables had been plugged into the confusingly named "PD current monitor" outputs (actually LED current monitors), not the "OSEM outputs".
  • We solved a problem with the real-time model freezing which turned out to be the IO chassis having lost power.
  • We took some mass off the IM to allow for the weight of the cables, and readjusted it in pitch and roll.
  • We aligned the IRM to the IM and set the OSEMs to mid-range.
  • We added ballast to the BF.
  • We changed the receptacles for the SF-BF rod. The low receptacle did not fit properly into the BF keystone and Hirata-san had to file it.
  • We fixed a broken wire on the BF yaw pico, retested the pico and added the BF cap.
  • We cabled and tested the BF cap picos.
  • We lifted the BF and weighed and balanced it.
  • We installed the SF ring and brought in the SF.
  • We installed the Cu segments on the SF.
  • We cabled the SF LVDT and did a quick test (not a full calibration).
  • We replaced non-vacuum compatible cables in the PI, removed various sticky labels and wiped it with ethanol.
  • We tried to hook the SF-BF rod but found the hole in the hex cable clamp was too small for the 8 mm rod head. We enlarged the hole but then found the PEEK pieces were too loose. We tried using foil, but then managed to lose a PEEK piece into the BF, so we will need to remove the cap of the BF to get it.

Plan for week of 9/4

Mark, Fabian, Enzo (Tue-Fri), Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun (Thu, Fri)

  • Retrieve PEEK piece from BF.
  • Crane SF back in.
  • Suspend BF/IRM/IM/RM/BS.
  • Test SF FR.
  • Calibrate SF LVDT.
  • Install SF cap; route cables.
  • Lift and weigh SF/BF/IRM/IM/RM/BS.
  • Adjust SF ballast.

Plan for week of 9/13

Mark (except Wed), Fabian (except ASJ), Enzo, Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun

  • Prepare magnet ring.
  • Bring in PI.
  • Route cables.
  • Suspend SF/..., adjust tilt of SF and total mass.
  • Adjust damper gap.

Vacation Info

Mark: 10/16-24

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)