3633
Comment:
|
2614
|
Deletions are marked like this. | Additions are marked like this. |
Line 7: | Line 7: |
At Kamioka (Mark, Fabian, Enzo, Hirata-san): | At Kamioka (Mark, Ohishi-san, Enzo, Yoshioka-kun, Kozu-kun): * We removed the LBB damper rings from the tank and passed them to Takahashi-san for recleaning. Unfortunately two screws galled, one holding on a Cu segment, and one holding on a joint piece. * We removed the LBB blade units from the PI, removed the blades and shipped them off for rework. * We pulled out all the old in-air cabling. * We laid about 9 new in-air cables. * We wrapped/labelled the BS mirror box, the winch system, the trolley adapters, and many other tools that we do not expect to use any time soon. * We connected up, tested and calibrated the BF LVDT. * We adjusted the ballast mass on the IM to make it hang level and at the right height. However we had to reduce the weight by a further 686 g relative to the plan of 2017-08-09. We found a combination that was good except for the fact that it used round masses on the bottom corners, so we decided to have the 641 g rectangular masses cut down by 60 g each. Mesco was able to do this within 24 hours. We will reclean the parts on Friday afternoon and swap them in on Monday. At Mitaka (Hirata-san: * Hirata-san got a quotation about optical bench from Mirapro and contacted them about reducing cost. * He asked Suzuki-san (Tokyo university) to order them (delivery date is 10/24, so far). * He modified SR assembly frame design (from Fabian) and asked Mirapro for quotation. * He liaised with Koshin-shoko about modification of BS LBB blade springs. * He asked ATC for making t4.5 ballast mass for PR. He washed them and sent them to Kamioka with the PR thrust bearing. * He worked on the 3D model of SR3 SUS wires, and making a list for quotation. |
Line 9: | Line 23: |
* Inspected LLB in tank - in a good position, but not very clean - apparent water spots and dirt. * Found the geophone adapter plates. * Retested SF FR stepper - still good. * Finally got SF LVDT working: * Found a short in the primary coil due to Al foil used for mechanical reinforcement at vacuum feedthrough connection. * Did a full calibration and found that linear range was too small (0.75 mm!) and did not cover nominal keystone height. * Decreased gain to increase linear range. * Adjusted the height of the yoke and secondary coil unit to center the linear region around the nominal keystone height. * Implemented velocity damping. * Found all parts for the LBB and damper rings. * Cu segments and some other parts were very dirty - wiped carefully for now, but should be properly cleaned before final install. * Outrigger parts for LBB have M16 thread cut directly into Al but should have had M16 helicoils. This is a galling risk with Ag-coated rod receptacles. Hirata-san organized rework. * Some special lock nuts are in short supply and are being borrowed from supply at ATC for next batch of BFs. * Made remaining two geophone in-air descrambler cables (total three). * Installed a thermometer supplied by Kokeyama-san on the tower around the BS tank. * Prepared the SF damper. * Designed a pattern of magnets for the two-segment arrangement of SF damper and laid it out on the magnet ring with the template. * Moved the Cu segments on SF cap by 30° (the cap had not been in the right position earlier). * Reinstalled PI: * Raised the PI with the crane and hooked the SF damper ring. Some of the rods did not fit the receptacles due to tolerance issue, but by going through a large number of rods and receptacles, we found three working sets. * Craned the PI onto the frame and suspended the SF/... section, this time with the hex cable clamp on the F0-SF rod. * Tensioned the PI yaw return spring, installed (but did not cable) the yaw stepper and adjusted the yaw of the SF/... section. We worry the return spring is not stiff enough. * Installed (but did not cable) the geophones. * Recentered the IP. The extra weight from the geophones (≈42 kg) and SF damper ring (≈17 kg) had brought the IP to near the point of instability, so we removed one arc weight (≈17 kg) and rearranged the other two in the top row to be symmetrical. * Added ballast to set the height of the F0 keystone. We now have about 6 kg in hand (due to removing one of the Cu segments for the SF damper). This should be enough margin for cables, temperature fluctuations etc. |
==== Plan for week of 8/21 ==== Vacation: Fabian (Mon)<<BR>> Internship: Kozu-kun (Mon-Fri)<<BR>> |
Line 35: | Line 27: |
==== Plan for coming weeks ==== For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]]. |
Kamioka: Mark, Ohishi, Fabian (Tue-Fri), Enzo, Yoshioka-kun (Tue, Wed, Fri). * Swap in new IM ballast masses; readjust height and levelness. * Install side panels of IRM and OSEMs. * Route IRM OSEM cables, test/adjust IRM OSEMs. * Add BF cap; cable and test BF-1 and BF-2 picos. * Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass. * Crane in SF. * Try TFs with optical sensors. Mitaka: Hirata-san. * SR stuff. |
Line 38: | Line 38: |
Week of 5/29, 6/6: * Cabling: * Route BF/... cabling up past SF to PI. * Route SF cabling up to PI. * Add Type 3 extensions to SF/... cables. * Move vacuum flanges to positions on assembly frame more convenient for next stage (accessible from second floor, one on each corner of frame). * Move in-air cabling to match flange positions. * Cable and test PI vertical LVDT. * Calibrate PI vertical LVDT. * Set yoke on PI vertical LVDT (if necessary). * Cable and test PI yaw stepper. * Cable and test PI vertical stepper. * Cable and test PI horizontal steppers. * Cable and test PI horizontal LVDTs. * Calibrate PI horizontal LVDTs. * Crane into tank. |
==== Plan for week of 8/28 ==== Kamioka: Mark, Ohishi, Fabian, Enzo, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun. * ==== Vacation Info ==== Fabian: Fri 8/4 through Mon 8/21 Mark: TBD Mid-Oct |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past week report
At Kamioka (Mark, Ohishi-san, Enzo, Yoshioka-kun, Kozu-kun):
- We removed the LBB damper rings from the tank and passed them to Takahashi-san for recleaning. Unfortunately two screws galled, one holding on a Cu segment, and one holding on a joint piece.
- We removed the LBB blade units from the PI, removed the blades and shipped them off for rework.
- We pulled out all the old in-air cabling.
- We laid about 9 new in-air cables.
- We wrapped/labelled the BS mirror box, the winch system, the trolley adapters, and many other tools that we do not expect to use any time soon.
- We connected up, tested and calibrated the BF LVDT.
- We adjusted the ballast mass on the IM to make it hang level and at the right height. However we had to reduce the weight by a further 686 g relative to the plan of 2017-08-09. We found a combination that was good except for the fact that it used round masses on the bottom corners, so we decided to have the 641 g rectangular masses cut down by 60 g each. Mesco was able to do this within 24 hours. We will reclean the parts on Friday afternoon and swap them in on Monday.
At Mitaka (Hirata-san:
- Hirata-san got a quotation about optical bench from Mirapro and contacted them about reducing cost.
- He asked Suzuki-san (Tokyo university) to order them (delivery date is 10/24, so far).
- He modified SR assembly frame design (from Fabian) and asked Mirapro for quotation.
- He liaised with Koshin-shoko about modification of BS LBB blade springs.
- He asked ATC for making t4.5 ballast mass for PR. He washed them and sent them to Kamioka with the PR thrust bearing.
- He worked on the 3D model of SR3 SUS wires, and making a list for quotation.
Plan for week of 8/21
Vacation: Fabian (Mon)
Internship: Kozu-kun (Mon-Fri)
Kamioka: Mark, Ohishi, Fabian (Tue-Fri), Enzo, Yoshioka-kun (Tue, Wed, Fri).
- Swap in new IM ballast masses; readjust height and levelness.
- Install side panels of IRM and OSEMs.
- Route IRM OSEM cables, test/adjust IRM OSEMs.
- Add BF cap; cable and test BF-1 and BF-2 picos.
- Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass.
- Crane in SF.
- Try TFs with optical sensors.
Mitaka: Hirata-san.
- SR stuff.
Plan for week of 8/28
Kamioka: Mark, Ohishi, Fabian, Enzo, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun.
Vacation Info
Fabian: Fri 8/4 through Mon 8/21 Mark: TBD Mid-Oct