Line 7: Line 7:
At Kamioka (Mark, Fabian, Enzo, Hirata-san):
Line 9: Line 8:
 * Inspected LLB in tank - in a good position, but not very clean - apparent water spots and dirt.
 * Found the geophone adapter plates.
 * Retested SF FR stepper - still good.
 * Finally got SF LVDT working:
  * Found a short in the primary coil due to Al foil used for mechanical reinforcement at vacuum feedthrough connection.
  * Did a full calibration and found that linear range was too small (0.75 mm!) and did not cover nominal keystone height.
  * Decreased gain to increase linear range.
  * Adjusted the height of the yoke and secondary coil unit to center the linear region around the nominal keystone height.
  * Implemented velocity damping.
 * Found all parts for the LBB and damper rings.
  * Cu segments and some other parts were very dirty - wiped carefully for now, but should be properly cleaned before final install.
  * Outrigger parts for LBB have M16 thread cut directly into Al but should have had M16 helicoils. This is a galling risk with Ag-coated rod receptacles. Hirata-san organized rework.
  * Some special lock nuts are in short supply and are being borrowed from supply at ATC for next batch of BFs.
 * Made remaining two geophone in-air descrambler cables (total three).
 * Installed a thermometer supplied by Kokeyama-san on the tower around the BS tank.
 * Prepared the SF damper.
  * Designed a pattern of magnets for the two-segment arrangement of SF damper and laid it out on the magnet ring with the template.
  * Moved the Cu segments on SF cap by 30° (the cap had not been in the right position earlier).
 * Reinstalled PI:
  * Raised the PI with the crane and hooked the SF damper ring. Some of the rods did not fit the receptacles due to tolerance issue, but by going through a large number of rods and receptacles, we found three working sets.
  * Craned the PI onto the frame and suspended the SF/... section, this time with the hex cable clamp on the F0-SF rod.
  * Tensioned the PI yaw return spring, installed (but did not cable) the yaw stepper and adjusted the yaw of the SF/... section. We worry the return spring is not stiff enough.
  * Installed (but did not cable) the geophones.
  * Recentered the IP. The extra weight from the geophones (≈42 kg) and SF damper ring (≈17 kg) had brought the IP to near the point of instability, so we removed one arc weight (≈17 kg) and rearranged the other two in the top row to be symmetrical.
  * Added ballast to set the height of the F0 keystone. We now have about 6 kg in hand (due to removing one of the Cu segments for the SF damper). This should be enough margin for cables, temperature fluctuations etc.
 * Mark and Fabian did a huge cleanup of the SR2 area and prepared a workspace for assembling the IM.
 * Fabian did a stocktake of the screws for the SR.
  * We have all we need for the IM, except one type that can be added after the rest of the IP is assembled.
  * We have most of what we need for the rest of the payload, and Hirata-san has ordered the others.
 * Hirata-san worked on SR procurement:
  * Suspension wire
  * SR additional parts (compensation masses, clamps etc)
  * Regular, SDC and BUMAX screws.
  * Additional machining on the BS sapphire prism jig to allow it to be used on the PR/SR mirror box.
  * LBB blade design.
 * Enzo and Kozu-kun (with help from Fujii-kun) worked on export from SUMCON to Matlab, and on filter design).
Line 35: Line 20:
==== Plan for coming weeks ====
For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]].
==== Plan for week of 11/20 ====
 * Holiday on Thu 3/23
 * All at Mitaka.
 * SR procurement, planning (Mark, Hirata-san)
 * SR mass budget (Fabian)
 * BS modeling filter design (Enzo, Kozu-kun)
Line 38: Line 27:
Week of 5/29, 6/6:
 * Cabling:
  * Route BF/... cabling up past SF to PI.
  * Route SF cabling up to PI.
  * Add Type 3 extensions to SF/... cables.
  * Move vacuum flanges to positions on assembly frame more convenient for next stage (accessible from second floor, one on each corner of frame).
  * Move in-air cabling to match flange positions.
  * Cable and test PI vertical LVDT.
  * Calibrate PI vertical LVDT.
  * Set yoke on PI vertical LVDT (if necessary).
  * Cable and test PI yaw stepper.
  * Cable and test PI vertical stepper.
  * Cable and test PI horizontal steppers.
  * Cable and test PI horizontal LVDTs.
  * Calibrate PI horizontal LVDTs.
 * Crane into tank.

==== Plan for week of 11/27 ====
 * Fabian at commissioning workshop
 *

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

  • Mark and Fabian did a huge cleanup of the SR2 area and prepared a workspace for assembling the IM.
  • Fabian did a stocktake of the screws for the SR.
    • We have all we need for the IM, except one type that can be added after the rest of the IP is assembled.
    • We have most of what we need for the rest of the payload, and Hirata-san has ordered the others.
  • Hirata-san worked on SR procurement:
    • Suspension wire
    • SR additional parts (compensation masses, clamps etc)
    • Regular, SDC and BUMAX screws.
    • Additional machining on the BS sapphire prism jig to allow it to be used on the PR/SR mirror box.
    • LBB blade design.
  • Enzo and Kozu-kun (with help from Fujii-kun) worked on export from SUMCON to Matlab, and on filter design).

Plan for week of 11/20

  • Holiday on Thu 3/23
  • All at Mitaka.
  • SR procurement, planning (Mark, Hirata-san)
  • SR mass budget (Fabian)
  • BS modeling filter design (Enzo, Kozu-kun)

Plan for week of 11/27

  • Fabian at commissioning workshop